Project Overview
The 44 MWp Culcairn Solar Farm spans across 1000 hectares of land and will be Neoen's largest solar asset in Australia once it goes into operations.
Neoen secured development approval for Culcairn Solar Farm from the NSW Government in 2021, with an option to build a 100MW / 200MWh battery in the future.
It will connect into the on-site 330kV transmission line managed by Transgrid.
Bouygues Construction Australia signals the commencement of Phase of the project which will take between 18-24 months to complete. At peak their will be 400 Staff Onsite including subcontractors, labour hire and management.
How to Register an Expression of Interest for Listed Packages
Work Packages currently available to submit an EOI for are listed on the 'Work Packages' tab above
To submit an initial EOI for the Work Scopes, companies must have an ICN Gateway capability profile.
Information on how to create your capability profile on ICN Gateway is detailed below.
ICN Gateway Capability Profile Creation
Click on "Join Now", at the top of this screen, to complete your capability profile on ICN Gateway.
Your company summary and company description are used to assess your ability to complete projects when you lodge an EOI - please ensure that your company invests the time and energy required to represent your company in the most effective manner possible. Click below to download the guide to setting up your Gateway profile
Arborist Services
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Plant Equipment Hire - 3 seater and 6 seater Buggy for a period of approximately 23 weeks.
Please see BOQ and specification requirements attached
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Plant Equipment Hire - 12 seater Bus 2WD and 4WD for a period of approximately 23 weeks
Please see BOQ and specification requirements attached
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Seeking supplier for Coir Logs 200-250 mm wide/ Length 2.4 m
Price per item
Quantity: 30
Include delivery price to Culcairn Solar Farm Project
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Cleaning the construction facilities of a solar farm construction site that will host up to 400 workers at the peak. Cleaning of offices, toilets and satellite bases, Scope to start approximately mid may
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Required for laying down cables on trenches.
Available from 01/08/2024
Minimum 2 weeks hire however it may be extended
Seeking daily hire rates/weekly rates or purchase prices
Datasheet of stand must be submitted if available
Freight cost for mobilization and demobilization to be considered
Quantity: 1
Lead time for delivery : to be informed
Payment terms and conditions: 30 days after invoice
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Quantity Required: 1
Approximately 40 days of hire over a 4 month period may be extended
Must be able to provide the datasheet of the truck showing reach and have the lifting capacity of 20T
Hiring conditions
o Stand down charges and when they apply
o Price per day including operators
Lead Time required for delivery.
Include mobilization and demobilization costs to the Culcairn Solar Farm Project
Ability of truck replacement or fitter in case of breakdown
Payment terms and conditions: 30 days after invoice
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
The Culcairn solar project is seeking to hire of purchase a flat bed truck with 3.5 tonne towing capacity. Hire purchase will be approx 3 months
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Supply and install of 3-4 IBC containers.
These will be connected to portable buildings or other Units already installed on site.
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Bouygues Construction Australia is looking for a business to design their O& M Building as well as a Storage Area onsite at the Culcairn Solar Farm.
Design company must have references for commercial buildings and drawing must be in line with NSW standards and certifications
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
looking for local providers to paint approximately 14 x 40ft sea containers with wording and information as well as 10 x 40ft containers with aboriginal artwork and other significant pieces.
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Local suppliers to undertake regular maintenance of pest control management onsite and checks - details to be confirmed.
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Supply of Rigid Truck or FlatBed Truck to move torquetubes on Solar Farm (11m long)
Approximately 20 weeks of hire.
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Lifting capacity 1.5-2t load
Must have Extended forks -> 2.4m
Hire duration - 6 weeks or more
Quantity: 4-5 machines
Mobilization: ASAP
Material to be lifted torque tubes
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Approximately 200 test to be completed on site at Culcairn Solar Farm every 250m on trenching works completed to install underground cabling.
Aim would be to have this work done in a series of 3 testing periods starting in early September
Mobilization and demobilization costs to site to be included in quotes
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Supply of temporary shelving racks and workbenches for installation in Sea Containers
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Tree planting services
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Bouygues Construction Australia and Equans Solar & Storage is seeking company to design and construction of a Warehouse onsite at the Culcairn Solar Farm
More details will be provided during the tender submission process
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Seeking washdown bay suitable for Heavy Good vehicles (including entry and exit ramps). Water collection to be contained.
Prices to include the following:
. Purchase price or hire price per week or month
. Mobilization Transport
. Install
. Commissioning
. Demobilization Transport:
. Decomissioning
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.