SA Australia
BOC Limited and ATCO Australia Pty Ltd
The South Australian Government is implementing the Hydrogen Jobs Plan which includes the following infrastructure to be constructed at Whyalla:
- 250MWe of electrolysers;
- 200MW of power generation to be powered by hydrogen produced by the electrolysers; and
- the Hydrogen Reticulation and Storage System (HRSS).
A consortium made up of ATCO Australia and BOC (ABC) has been engaged by the South Australian Government to provide Early Contractor Involvement (ECI) Services to deliver the hydrogen facility at Whyalla.
ATCO Australia is part of the $29B global ATCO Group, with 25 years of Australian experience in natural gas infrastructure construction and operations, including the 180MW Osborne Power Station in Adelaide.
BOC is a subsidiary of Linde, one of the world's leading industrial gases and engineering companies with global revenue of US$33 billion and an established hydrogen business along the entire value chain.
Both ATCO and BOC have had operations in SA for over 60 years.
ABC is interested in receiving expressions of interest from organisations who consider they have the skills and experience to contribute to the development of the Whyalla Hydrogen Facility
Scope will include:
- Inspect and test subgrade
- Remove non-compliant subgrade and replace with compliant material
- Provide engineered fill for sub-base
- Spread engineered fill
- Compact Engineered fill to design level
Indicative timeline:
- RFT issued to the market early Sept 2024
- Looking to award the Early package(s) Nov 2024
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Scope will include:
- Scrape topsoil and load onto trucks
- Transport topsoil and stockpile in designated areas
- Cover/treat topsoil for storage
- Carry out Excavation from 'cut' areas and load into trucks
- Provide Transport from cut areas to fill areas and dump
- Spread fill material in layers
- Compact in layers to specification
- Carry out Compaction testing
- Provide Dust suppression/Water Cart
Indicative timeline:
- RFT issued to the market early Sept 2024
- Looking to award the Early package(s) Nov 2024
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Scope will include:
- Fell vegetation
- Gather vegetation and mulch
- Carry out Grub/remove root balls and mulch
- Stockpile mulch in designated areas
- Remove topsoil and load into trucks
- Deliver and stockpile topsoil in designated areas
Indicative timeline:
- RFT issued to the market early Sept 2024
- Looking to award the Early package(s) Nov 2024
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Scope will include:
- Carry out Survey peg-out laydown and hardstand areas
- Provide (or produce) engineered fill and deliver to hardstand and laydown areas
- Spread engineered fill
- Compact in layers to specification and complete compaction testing
- Carry out Compaction testing
Indicative timeline:
- RFT issued to the market early Sept 2024
- Looking to award the Early package(s) Nov 2024
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Scope will include:
- Carry out Survey peg-out kerb and gutters
- Carry out excavation for kerb, gutters and side drains
- Provide and Install side drains and connect to pits
- Provide and Install kerb and gutter formwork
- Provide Kerb and gutter reinforcement
- Provide Concrete and cure coat
Indicative timeline:
- RFT issued to the market early Sept 2024
- Looking to award the Early package(s) Nov 2024
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Scope will include:
- Carry out Peg out fence location
- Carry out Excavate strip footings
- Reinforcement placement
- Provide Concreting of foundations
- Carry out Fencing installation
- Provide and install permanent gates installation
- Provide and install temporary security hut and boom gate at entrance
Indicative timeline:
- RFT issued to the market early Sept 2024
- Looking to award the Early package(s) Nov 2024
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Scope will include:
- Clearing and hardstand for temporary site establishment
-Provide Temporary upgrade to entry/exit from Lincoln Highway and track in
- Provide Temporary hardstand area for temporary site establishment
- Provide and Install temporary buildings
- Provide Temporary power via diesel generator
- Provide Pump out services for ablutions
- Provide Potable water supply procurement
- Provide Diesel to carry out site works
Indicative timeline:
- RFT issued to the market early Sept 2024
- Looking to award the Early package(s) Nov 2024
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Scope will include:
- Install Main Project Information Board
- Provide and install temporary chain wire fence at entrance with shadecloth
Indicative timeline:
- RFT issued to the market early Sept 2024
- Looking to award the Early package(s) Nov 2024
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Scope will include:
- Carry out Survey peg-out stormwater infrastructure
- Provide and Install precast concrete pits
- Install oily water separators
- Provide and Install interconnecting stormwater piping
- Carry out excavation and construct stormwater retention basin
- Provide and install culvert between basin and Lincoln Highway
Indicative timeline:
- RFT issued to the market early Sept 2024
- Looking to award the Early package(s) Nov 2024
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Express interest to be kept updated for any opportunities that may arise for this project.
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
The scope of work includes detailed design, manufacture, assembly, testing, packing and delivery of the following packages of electrical equipment -
a. Switchgears - Four Hybrid GIS Switchgear units insulated with SF6 gas and rated for 275kV/2000A.
b. Circuit Breakers - Four 11kV Gas Circuit Breakers.
c. Transformers - Four 275kV Transformers -
i. Two double wound 275/33/33 kV transformers used to step down voltage from 275kV to 33 KV.
ii. Two double wound 275/11.5/11.5 kV transformers used to step down voltage from 275kV to 11.5 KV.
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.