Project Details
Fortescue is committed to decarbonising its Australian iron ore operations in mining, port, rail, Non-process Infrastructure and mobile fleet in the Pilbara in Western Australia to achieve zero terrestrial emissions (Scope 1 and 2) by 2030. Real zero refers to no fossil fuels and wherever possible, no offsets.
Scope Overview
Fortescue's decarbonisation plan includes the deployment of 2-3 GW of renewable (wind and solar) energy generation and substantial battery storage. The renewable power generated will be transmitted to Fortescue's electrical network via dedicated connections.
Indicative Timeline
Procurement activities are scheduled to commence Q2 of CY2023.
Construction is scheduled to commence Q1 CY2024.
The Project is planned to be completed by Q4 CY2030.
Local and Indigenous participation
In line with Fortescue's commitment to supporting local Western Australian communities, requirements relating to the engagement of local and First Nations vendors will be included in the selection criteria for the Project tendering opportunities.
WA Australia
Please refer to the SOW for further details pertaining to the package.
*Now included in the Earthworks RFT
Please refer to the SOW document for additional details pertaining to this package.
Please refer to the Scope of Work for further Information.
Please refer to the scope of work document for additional information in relation to this package.
Please refer to the SOW for further details pertaining to the package.
Please refer to the SOW for further details pertaining to the package.
Please refer to the SOW for further details pertaining to the package.
Please refer to the SOW for further details pertaining to the package.
Please refer to the Scope of Work for further Information.
Please refer to the Scope of Work for further Information.
Please refer to the Scope of Work for further Information.
Please refer to the Scope of Work for further Information.
Please refer to the scope of work for additional information in relation to this package.
Please refer to the scope of work for additional information.
Please refer to the Scope of Work for further Information.
Please refer to the Scope of Work for further Information.
Please refer to the Scope of Work for further detail pertaining to this package.
Please refer to the Scope of Work for further detail pertaining to this package.
Please refer to the scope of work for additional information.
Please refer to the Scope of Work for further Information.
Please refer to the scope of work for additional information.
Please refer to the SOW for further details pertaining to the package.
This package has been awarded as a non-exclusive Framework Agreement to the following Service Providers for the Fortescue Decarbonisation Portfolio. Fortescue intends to update this package for each project engagement.
Consultant Awarded: Alliance Power & Data Pty Ltd trading as APD Engineering
Date Awarded: 02/10/2024
Contact Details: Jasraj Sekhon
Phone: 08 9212 1500
Email: jasraj.sekhon@apdeng.com.au
Consultant Awarded: Emtek Pty Ltd
Date Awarded: 27/09/2024
Contact Details: Joel Herron
Phone: 0427 087 667
Email: joel.herron@emtek.com.au
Consultant Awarded: Resources Services Group X Pty Ltd
Date Awarded: 15/10/2024
Contact Details: Frank Daly
Phone: 0411 532 660
Email: frank.daly@rsgx.com
Please refer to the Scope of Work for further detail pertaining to this package.
Please refer to the SOW for further details pertaining to the package.
Please refer to the scope of work document for additional information pertaining to this package.
This package has been relocated from Pilbara Transmission Project Stage 4 to Fortescue Decarbonisation Project ICN Gateway websites. This package has been awarded as a non-exclusive Framework Agreement with a selected Original Equipment Manufacture or and Service Provider for the Fortescue Decarbonisation Portfolio. Fortescue intends to update this package for each project engagement.
All award information has been updated in previous project Pilbara Transmission Project Stage 4.
This package has been relocated from Pilbara Transmission Project Stage 4 to Fortescue Decarbonisation Project ICN Gateway websites. This package has been awarded as a non-exclusive Framework Agreement with a selected Original Equipment Manufacture or and Service Provider for the Fortescue Decarbonisation Portfolio. Fortescue intends to update this package for each project engagement.
All award information has been updated in previous project Pilbara Transmission Project Stage 4.
This package has been relocated from Pilbara Transmission Project Stage 4 to Fortescue Decarbonisation Project ICN Gateway websites. This package has been awarded as a non-exclusive Framework Agreement with a selected Original Equipment Manufacture or and Service Provider for the Fortescue Decarbonisation Portfolio. Fortescue intends to update this package for each project engagement.
All award information has been updated in previous project Pilbara Transmission Project Stage 4.
This package has been relocated from Pilbara Transmission Project Stage 4 to Fortescue Decarbonisation Project ICN Gateway websites. This package has been awarded as a non-exclusive Framework Agreement with a selected Original Equipment Manufacture or and Service Provider for the Fortescue Decarbonisation Portfolio. Fortescue intends to update this package for each project engagement.
This package has been relocated from Pilbara Transmission Project Stage 4 to Fortescue Decarbonisation Project ICN Gateway websites. This package has been awarded as a non-exclusive Framework Agreement with a selected Original Equipment Manufacture or and Service Provider for the Fortescue Decarbonisation Portfolio. Fortescue intends to update this package for each project engagement.
All award information has been updated in previous project Pilbara Transmission Project Stage 4.
This package has been relocated from Pilbara Transmission Project Stage 4 to Fortescue Decarbonisation Project ICN Gateway websites. This package has been awarded as a non-exclusive Framework Agreement with a selected Original Equipment Manufacture or and Service Provider for the Fortescue Decarbonisation Portfolio. Fortescue intends to update this package for each project engagement.
All award information has been updated in previous project Pilbara Transmission Project Stage 4.
This package has been relocated from Pilbara Transmission Project Stage 4 to Fortescue Decarbonisation Project ICN Gateway websites. This package has been awarded as a non-exclusive Framework Agreement with a selected Original Equipment Manufacture or and Service Provider for the Fortescue Decarbonisation Portfolio. Fortescue intends to update this package for each project engagement.
All award information has been updated in previous project Pilbara Transmission Project Stage 4.
This package has been relocated from Pilbara Transmission Project Stage 4 to Fortescue Decarbonisation Project ICN Gateway websites. This package has been awarded as a non-exclusive Framework Agreement with a selected Original Equipment Manufacture or and Service Provider for the Fortescue Decarbonisation Portfolio. Fortescue intends to update this package for each project engagement.
All award information has been updated in previous project Pilbara Transmission Project Stage 4.
Awarded Company
**Please note that 540PTP0021 - was split into two packages (540PTP0021 and 540PTP0030), as follows:
540PTP0021- Supply of OPGW Conductors (PTP4) and Framework Agreement were awarded to:
Contractor Awarded: ZTT Australia Pty Ltd
Date Awarded: 8 December 2023
Contact Details: Owen Suen - (Country Manager of Australia & NZ International Division)
Email: owen.sun@zttcable.com
Mobile: +61 435296580
540PTP0030 - Supply of Primary OPGW Conductors (PTP4) and Framework Agreement were awarded to:
Contractor Awarded: AFL Telecommunications Pty Ltd
Date Awarded: 8 December 2023
Contact Details: Justin Whitten (National Market Manager - Mining)
Email: Justin.Whitten@AFLglobal.com
Phone: 08 6253 2204
Please refer to the SOW for further details pertaining to the package.
Please refer to the scope of work for additional information.
Please refer to the scope of work for additional information.
Please refer to the scope of work for additional information.
Please refer to the scope of work for additional information pertaining to this package.
Please refer to the SOW for further details pertaining to the package.
Please refer to the Scope of Work for additional information.
Please refer to the SOW for further details pertaining to the package.
Please refer to the Scope of Work for further information.
Please refer to the scope of work for further information.
Please refer to the Scope of Work for further detail pertaining to this package.
Please refer to the Scope of Work for further detail pertaining to this package.
Please refer to the scope of work for additional information pertaining to this package.
Please refer to the SOW for further details pertaining to the package.
Please refer to the scope of work for additional information.
Please refer to the scope of work for additional information.
Please refer to the scope of work for additional information.
Please refer to the scope of work for additional information.
Please refer to the SOW for further details pertaining to the package.
Please refer to the Scope of Work for additional information.
Design and Construction of 33Kv Distribution for Solomon, Eliwana and Christmas Creek mines.
Please refer to the SOW for further details pertaining to the package.
Please refer to the SOW for further details pertaining to the package.
*Please refer to the scope of work for additional information:-
Construction of HME (Heavy Mining Equipment, PIT POWER and LME/SME (Light Mining Equipment / Support Mining Equipment) Charging Facilities - Eliwana and Flying Fish.
Please refer to the SOW for further details pertaining to the package.
Please refer to the Scope of Work for further Information
Please refer to the Scope of Work Provided for further information.
Please refer to the Scope of Work for further information.
Please refer to the scope of work for additional information.
Please refer to the scope of work for further information.
Please refer to the scope of work for additional information.
Please refer to the scope of work for additional information.
Please refer to the scope of work for additional information.
Please refer to the Scope of Work for further information.
Please refer to the scope of work for additional information.
Please refer to the scope of work for additional information.
Please refer to the scope of work for additional information.
Please refer to the scope of work for additional information.
Please refer to the scope of work for additional information.
Please refer to the scope of work for additional information.
Please refer to the scope of work for additional information.
Please refer to the Scope of Work Provided for further information.