BHP Olympic Dam Corporation Pty Ltd (BHP) is seeking expressions of interest from suitably qualified contractors and contractor teams with capability and availability to support the Copper SA Growth Enabling Non-Process Infrastructure Program at Olympic Dam. The EOI is intended to seek market capability across construction contractors (Construct Only, Design and Construct (D&C), and Engineering, Procurement and Construction (EPC) delivery models) before BHP determines the contracting and packaging strategy for each project.
This is an early market-sounding activity only. Physical construction on some of the packages is not expected to start until 2028. Respondents are asked to provide information on their capability, relevant experience, delivery model appetite, capacity and availability. Pricing, rates, estimates or commercial offers should not be provided at this stage.
NOTE: In 2025, BHP conducted the CuSA Trade Contractor EOI to understand construction contractor capability, capacity, employee relations and delivery experience across the broader Major Projects Copper SA portfolio. This EOI is a separate, local Asset project-specific market engagement seeking current information on the Growth Enabling NPI projects. Responses will help BHP begin shaping delivery model strategies across the Growth Enabling NPI Program.
Program overview
The program comprises a portfolio of enabling infrastructure projects supporting Copper SA growth. The projects remain discrete investments and may progress under different schedules, packaging strategies and delivery models. Current project areas are:
P1 Accommodation
Expansion of the existing ODS Village to accommodation for additional workforce requirements, including accommodation, central facilities, utilities and supporting infrastructure. Delivery options may include supply-led, integrated D&C or construct-only models.
P2 SMA Switchyard / SPARK
New HV power infrastructure at Olympic Dam, including upgrades to the existing 132kV switchyard, new overhead powerlines and a new switchyard supporting 132kV, 33kV and 11kV infrastructure.
P3 Transitional Water
Temporary water infrastructure to support construction and early commissioning, including a temporary desalination plant, 10-15 boreholes across the Southern Mine Lease, connecting pipelines, a transfer main, storage and associated site infrastructure.
P4 Northern Water Integration
Integration of the Northern Water supply into existing site networks, including pipelines, pumping, storage, tie-ins, controls and associated infrastructure.
P5 Airport
Targeted airport airside upgrades to support increased passenger demands and operation requirements.
P6 Reactive Power
Reactive power compensation and associated electrical infrastructure, integration, controls, protection, testing and commissioning. Scope and packaging remain under development.