IBERDROLA AUSTRALIA LIMITED/ENERVEN ENERGY INFRASTRUCTURE

Tungkillo BESS Project

Overview

The Tungkillo BESS (Battery Energy Storage System) site is located approximately 40 km east of Adelaide and 8.5 km east of Mount Torrens, on Peramangk Country within the Mid Murray Council local government area (LGA).

  • Location: Electronet Road, Tungkillo (6 km south of Tungkillo township)
  • Capacity: Up to 270 MW supplying up to 1,080 megawatt-hours (MWh) of battery storage capacity.
  • Connection to: the adjacent ElectraNet Tungkillo substation via a new 275 kV overhead cable.
  • Transmission line: approximately 700 metres

Once complete, it will play an important role in supporting more renewables into the South Australian network and helping keep the system stable as supply and demand shift throughout the day.


Big battery projects like Tungkillo are becoming a key part of the energy system. They store energy when there's excess generation and release it when it's needed, helping smooth out variability from renewables and supporting overall grid reliability.

About Iberdrola Australia:


Iberdrola Australia is a long term developer, owner, and operator of renewable energy and firming assets in Australia. Our portfolio includes 21 renewable energy and firming assets totalling more than 2.7 GW of operating capacity.

About Enerven:


Enerven is a national energy services business delivering major projects across the National Electricity Market (NEM). Our growing portfolio spans transmission infrastructure, substations, renewable energy connections and large-scale battery energy storage systems (BESS). Our design, construction, and maintenance services ensure reliable power generation, transmission, and distribution to homes and businesses nationwide - and our commitment to renewable energy and resilient grid infrastructure sets us apart in the industry.

About Enerven's involvement in this project:


Enerven's scope includes:

  • Civil works and site preparation
  • Local road upgrades, foundations and construction platforms
  • Electrical infrastructure including cabling, earthing, auxiliary systems and balance-of-plant
  • A 275kV substation
  • More than 700 metres of 275kV overhead transmission line connecting to the existing Tungkillo Substation.
For further details please see the link below:

Tungkillo Battery | Iberdrola Australia

Enerven

Tungkillo BESS Project

IBERDROLA AUSTRALIA LIMITED/ENERVEN ENERGY INFRASTRUCTURE

location_on

SA Australia


Project Primary Contact
person_outline
Alex Vojdani
badge
Supply Chain Manager
phone
+61 04 4727 7175
mail Send Email

ENERVEN ENERGY INFRASTRUCTURE

Work Package
EOI Open Date
EOI Close Date
Status
lock
Login to View Details
Login
If you do not have a business profile, you can
create one to get started

Construction of the O&M Facility. The contractor shall submit design documentation including drawings, calculations, reports, certifications, and product data for Principal review.

Status
Open
EOI Open Date
••••••••
EOI Close Date
••••••••
brightness_1 Full Scope
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
lock
Login to View Details
Login
If you do not have a business profile, you can
create one to get started

Supply the 33kV MV RMU. This is a medium-voltage secondary switchgear assembly used for the switching, protection, isolation and earthing of medium-voltage electrical circuits within the Facility.

Status
Open
EOI Open Date
••••••••
EOI Close Date
••••••••
brightness_1 Full Scope
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Loading...