PSD Energy

Northern Battery Project

Overview

PROJECT OWNER AND CONTRACTOR

The Northern Battery is being developed by AMPYR in partnership with Green Gold Energy (GGE) to provide South Australia with energy reliability and security through energy storage. PSD Energy has been engaged as the Balance of Plant (BOP) / EPC contractor. PSD Energy is an Adelaide-headquartered electrical engineering, design and construction company established in 2005 and is a Quanta Services company. PSD Energy delivers solar farms, battery energy storage systems (BESS), substations and transmission works across Australia.

PROJECT OVERVIEW

The Northern Battery will comprise modular batteries and inverters installed in rows, with a nameplate capacity of 270 MW and a total storage capacity of 1,145 MWh at the point of connection. The project includes battery containers and associated inverter / medium voltage skids supplied by the battery manufacturer, installed on concrete foundations, together with 33 kV collection cabling, earthing and lightning protection, site roads and drainage, stormwater and fire water retention, fire services, security fencing, CCTV and access control, lighting, and permanent operations buildings including staff amenities and storage.

A new substation will be developed adjacent to the battery area and connected to ElectraNet's Davenport substation via a new underground transmission line. The substation and transmission line are being constructed by a separate contractor and are not part of the work packages listed on this portal.

LOCATION

The site is on part of the former Northern Power Station site at Port Paterson, approximately 6 km south of the Port Augusta town centre in regional South Australia. Construction vehicle access is via the Augusta Highway and Northern Power Station Road. The battery area is approximately 7.7 ha. The site is a low-lying coastal location with hot, dry summers, and suppliers should allow for regional logistics and the site's environmental conditions.

PROJECT TIMEFRAMES (INDICATIVE)

  • Site mobilisation and establishment: January 2027
  • Site set-up and bulk earthworks: January to May 2027
  • Civil works and foundations: May to October 2027
  • Cabling and electrical works: June to December 2027
  • Battery and inverter deliveries: From March 2027, with installation from July to November 2027
  • Testing and commissioning: August 2027 to mid-2028, with operation expected around mid-2028

Standard site hours are Monday to Saturday, 7:00 am to 7:00 pm. PSD Energy's on-site workforce is expected to peak at around 50 people in mid to late 2027.

All dates are indicative and depend on the final construction program.

WORK PACKAGES

Work packages are listed on this portal in groups aligned to the construction program:

  • Site establishment and support services: Needed from mobilisation, including security, temporary facilities, temporary power, waste, water and septic services, fuel, traffic management, accommodation, surveying, testing, environmental services, consumables, precast footings, electrical bulk materials and crane hire.
  • Civil, materials and plant packages: For 2027, including concrete and reinforcement, quarry products, drainage and fire water pond works, precast products, plant hire, labour hire, steel fabrication, MV and DC cable supply, fencing and security systems, and fire services.
  • Finishing packages: Including supply and erection of the O&M shed, site lighting and small power supply, and revegetation and landscaping.

PSD Energy will self-perform a number of scopes, including cable installation, HV jointing and testing, earth grid testing, fibre optic installation, the O&M crib and office building, piling and workforce transport.

Further packages may be added, and listed packages may be split, combined, varied or withdrawn as the design and program develop. Partial scope registrations are welcomed from lower-tier suppliers where indicated.

PROCUREMENT PROCESS

1 - Suppliers register an Expression of Interest (EOI) through ICN Gateway against each relevant work package and answer the package questions.

2 - PSD Energy reviews EOIs for capability, capacity, relevant experience, WHS, quality and environmental performance, insurances and licensing, and local and First Nations participation.

3 - Shortlisted suppliers are invited to submit a quotation or tender against a Scope of Works and PSD Energy's subcontract or purchase order terms.

4 - Quotations and tenders are evaluated on value for money, which includes price, safety, capability, program, quality and local content.

5 - Successful suppliers are engaged under PSD Energy's subcontract or purchase order terms, which include relevant flow-down obligations from the head contract. No work is to start until a subcontract or purchase order has been executed.

Registering an EOI does not guarantee an invitation to quote or the award of any work. PSD Energy will not reimburse any costs incurred in responding to an EOI or request for quotation.

REQUIREMENTS FOR SUPPLIERS AND SUBCONTRACTORS

Depending on the package, suppliers and subcontractors will be required to demonstrate the following:

  • Work health and safety: A WHS management system appropriate to the scope, Safe Work Method Statements for high-risk construction work, compliance with the Work Health and Safety Act 2012 (SA) and Regulations, and participation in PSD Energy's site inductions and safety systems as Principal Contractor.
  • Insurances: Public and products liability (typically not less than $20 million), workers compensation (ReturnToWorkSA or equivalent), motor vehicle and plant insurance, and professional indemnity where design or advice is provided.
  • Licences and accreditations: Relevant to the scope, for example SA electrical contractor licences, security licences, EPA licences for waste transport, NATA accreditation for testing services, HV jointing competencies, and DIT-recognised traffic management accreditations.
  • Quality: Inspection and test plans and records consistent with ISO 9001 principles, and materials supplied with compliance certificates to the relevant Australian Standards.
  • Environment: Compliance with the project Construction Environmental Management Plan and EPA licence conditions, including dust, noise, erosion and sediment control and waste management.
  • Workplace relations: Workers employed and paid in accordance with the applicable modern award or registered enterprise agreement and the Fair Work Act 2009 (Cth), with superannuation and portable long service leave obligations met. Labour hire may only be supplied by providers licensed under the Labour Hire Licensing Act 2017 (SA). Subcontractors and suppliers remain responsible for employing, directing and paying their own workers.
  • Ethical sourcing: Commitment to identifying and addressing modern slavery risks consistent with the Modern Slavery Act 2018 (Cth), and adherence to PSD Energy's supplier code of conduct.

LOCAL AND FIRST NATIONS PARTICIPATION

PSD Energy is committed to maximising opportunities for local people and businesses on the Northern Battery. Where suppliers are available and competitive, PSD Energy will:

  • Consider local workforce and supplier capacity when selecting subcontractors and suppliers.
  • Invite First Nations-owned businesses to quote, and encourage subcontractors to do the same.
  • Use local apprentices and trainees where the scope allows.
  • Use local suppliers and accommodation providers.

Roles are advertised locally, including through the Spencer Gulf Jobs and Skills Hub and TAFE SA.

INDIVIDUALS SEEKING EMPLOYMENT

This portal is for businesses. Individuals seeking employment should email nbessenquiries@psdenergy.com with their name, contact details, trade or skills, and any licences or tickets held. All roles are filled through PSD Energy's standard recruitment processes.

NEXT STEPS

Following the close of each work package listing, PSD Energy will review registrations and contact shortlisted businesses with request for quotation or tender documents. Questions about this portal can be directed to ICN SA. General project information is available at www.northernbattery.com.au.

All information on this page, including scope, quantities and dates, is indicative only. It may change as the design and construction program develop and does not form part of any contract.

Northern Battery Project

PSD Energy

location_on

SA Australia


Project Primary Contact
person_outline
Rodrigo Rech dos Santos
badge
Supply Chain Consultant
phone
+61 04 3568 9768
mail Send Email

GENERAL EXPRESSIONS OF INTEREST

Work Package
EOI Open Date
EOI Close Date
Status
lock
Login to View Details
Login
If you do not have a business profile, you can
create one to get started

Express interest for any opportunities that may arise for this project. Specific Work Packages to be Released at a Later Date.

Status
Open
EOI Open Date
••••••••
EOI Close Date
••••••••
brightness_1 Full Scope
Note: You can fill out an Expression of Interest form exclusively on a computer or laptop device.
Loading...