PARRAMATTA LIGHT RAIL - STAGE 2 ENABLING WORKS
Transport for NSW awarded the $322 million contract for the delivery of the Parramatta Light Rail - Stage Two Enabling Works package to John Holland.
These works include delivery of a 320-metre bridge over the Parramatta River between Wentworth Point and Melrose Park and bridge approaches on either side, totalling 1.3 kilometres. Parramatta Light Rail Stage 2 will connect Stage 1 and the Parramatta CBD to Sydney Olympic Park via Camellia, Rydalmere, Ermington, Melrose Park and Wentworth Point.
The new bridge will connect communities on the north and south of the river, and will feature an innovative, long-span cast in situ balanced cantilever design. The design means the bridge will only have two piers in the river, minimising disruption to boats and other waterway users and protecting the sensitive marine environment.
It marks the first major bridge crossing the Parramatta River since the Ryde Bridge was completed nearly 40 years ago. This work will also see upgrades to surrounding public spaces including Archer Park.
Bridge construction will commence towards the end of 2025 with a completion date of early 2028.
ICN GATEWAY COMPANY REGISTRATION
Your ICN Gateway company profile and any registrations of interest you submit are used to assess your organisation's ability to complete projects.
Click here to create a new company profile or to login to your existing company profile.
Please ensure your business invests the time and energy required to represent itself in the most effective manner possible when completing and/or updating your company profile.
John Holland strongly encourages suppliers to contact ICN in the first instance to gain an understanding of the EOI process and work packages, such as their ICN Gateway Profile Improvement Workshops. Additional ICN resources can be found at:
- Gateway by ICN User Guide
- Gateway by ICN EOI User Guide
ADDITIONAL INFORMATION TO CONSIDER:
- Incomplete registrations may not be considered.
- Information on how to create a company profile and/or submit a registration of interest on Gateway by ICN is provided below (refer to User Guides available in the 'Key Documents' section)
- An ICN Gateway company profile that accurately and effectively summarises your company is critical to using the services of the ICN Group - please ensure that your company invests the time and energy required to represent your company in the most effective manner possible.
- It is important that businesses registering their interest are aware that their registration does not guarantee that they will progress further in any procurement.
- Please organise a Business Visit with Raquel Bloom Regional Manager - Greater Western Sydney M: +61 (0) 400 264 678 E: rbloom@icnnsw.org.au if you would like to discuss your Gateway profile upon registering your (EOI) submission.
Work Packages
General Scaffold Supply and Install
Full Scope
Fencing and Gates - Permanent
Full Scope
CSR Pit Supply
Full Scope
Bearing and expansion joint Supply
Full Scope
Stormwater drainage installation
Full Scope
CSR Conduit Supply
Full Scope
ATL stairs - Supply precast treads, riser and landings
Full Scope
Asphalt Supply and Install
Full Scope
Supply and Install Amenities building
Full Scope
Rail sand blasting for priming
Full Scope
Supply and Install Pavers to Car Park
Full Scope
Supply 225mm pipe for Land Bridge Drainage.
Full Scope
Retaining wall Construction - Installation
Full Scope
Kerb and Gutter
Full Scope
Precast Barrier Supply
Full Scope
Road pavements
Full Scope
Supply SS Pipe Hangers for Land Bridge Drainage CSR
Full Scope
Bridge metalwork ATL stairs
Balustrade and Handrail, barrier railings
Full Scope
Landscaping
Full Scope
ITS Install
Full Scope
Aluminothermic Welding of Rail Install Only
Full Scope
Ultrasonic Testing of Aluminothermic Welding
Full Scope
Rail to Earth Testing Subcontractor
Full Scope
FRP structures - footpaths, lighting pile cap, L wall
Full Scope
Scupper Supply
Full Scope
Waterproofing Supply and Install (Deck)
Full Scope
Streetlighting
Full Scope
Permanent Barriers, Railings and Handrails Supply
Full Scope
Road signage
Full Scope
Stormwater Pipe Supply and Fittings Deck drainage
Full Scope
Bridge Name Plate Supply
Full Scope
Supply Cover Plates to Bridges and Barriers
Full Scope
Gabian Mattress Supply
Full Scope
Supply and Install - Anti Graffiti Paint
Full Scope
Rail grinding
Full Scope
Temporary Handrail Supply Bridge Decks