The Kangwinan Project is located in Norman Creek, Cape York Peninsula, approximately 60 km South of Weipa. The Bauxite process plant will be constructed on the Southern side of the Norman Creek and then transported approximately 15 km southeast via overland conveyor to the existing Amrun stockyard.
Proposed project components include:
Rio Tinto has appointed Bechtel Australia Pty Ltd as the project Engineering, Procurement and Construction Manager (EPCM). All major agreements will be made directly with Rio Tinto.
DELIVERY SCHEDULE
In October 2026, the Rio Tinto Board approved the Kangwinan project, strengthening long-term supply certainty with additional volumes of high-quality Amrun bauxite and sustaining Rio Tinto's bauxite production as Andoom and Gove mines mature.
Construction of associated Kangwinan mine infrastructure is anticipated to take 32 months with first output targeted in 2029 and full production by 2032.
EXPRESSIONS OF INTEREST
Rio Tinto encourages local industry interested in supplying to the project to register an expression of interest (EOI) through the ICN Gateway webpage.
Information on specific supply opportunities will be communicated on the ICN Gateway project page as it becomes available, with local industry able to register its interest against them.
Please ensure that:
Your company profile on the ICN Gateway is complete, up-to-date and accurate, including electing to be notified via e-mail of supply opportunities
It is important that businesses submitting an EOI are aware that their submission does not guarantee that they will progress further in the procurement process. Only companies that can demonstrate capability and capacity in accordance with Rio Tinto's standards will be invited to pre-qualify for specific opportunities.
FURTHER ASSISTANCER
Rio Tinto strongly encourage local industry to contact the ICN Queensland in the first instance to improve their understanding of the EOI process.