Project at a glance


NSW Australia (Onshore)
Procurement Phase
CPB CONTRACTORS PTY LIMITED & UGL ENGINEERING PTY LIMITED
$1.5 Billion

Contact Details


Geoff Reardon
Regional Manager - Murray/Riverina NSW
+61 402 632 027

Project Overview

Transgrid has contracted UGL Engineering Pty Ltd and CPB Contractors Pty Ltd (UGL-CPB JV) to deliver the western portion of the HumeLink project.
HumeLink West involves the expansion of the existing Wagga Wagga 500 kV substation, the design and construction of a new substation at Gugaa and connection works to the future Maragle 500 kV substation. The project also includes a new 500 kV double circuit transmission line to connect the substations at the Wondalga interface point with HumeLink East.

Initial activities include site investigations and engineering design, followed by enabling civil works primarily for temporary roads and facilities.

The HumeLink West team is now establishing procurement and resourcing relationships with local and regional suppliers to support a wide range of activities including:


  • Geotech, survey and engineering design-related works
  • Civil works and traffic management to install or upgrade approximately 300 kilometres of access tracks
  • Works to establish 2 temporary 520 and 420-person worker accommodation facilities
  • Establishment of 7 construction equipment laydown areas along the alignment
  • Transport services for the delivery of steel, concrete and equipment
  • Design, preparation and construction of a new substation at Gugaa
  • Required connection works at the future Maragle substation
  • Expansion of the existing Wagga Wagga substation
  • Erection and stringing of approximately 360 transmission towers
  • Rerouting of approximately 2 km of existing transmission line to the Wagga Wagga substation
  • Required works at the Wondalga interface point.

The HumeLink project is committed to working with Transgrid to maximise the social and economic benefits of HumeLink West for local and regional communities and is establishing a range of initiatives that aim to drive local business, employment and trainee participation throughout project delivery.

Interested parties are encouraged to contact the HumeLink West project team via email at humelink@transgrid.com.au or by calling 1800 317 367.


Additional information about the project is available on the HumeLink website here:

Connecting Wagga Wagga, Bannaby and Maragle | Transgrid



How to Register an Expression of Interest for Listed Packages

Work Packages currently available to submit an EOI for are listed on the 'Work Packages' tab above

To submit an initial EOI for the Work Scopes, companies must have an ICN Gateway capability profile.

Information on how to create your capability profile on ICN Gateway is detailed below.


ICN Gateway Capability Profile Creation

Click on "Join Now", at the top of this screen, to complete your capability profile on ICN Gateway.

Your company summary and company description are used to assess your ability to complete projects when you lodge an EOI - please ensure that your company invests the time and energy required to represent your company in the most effective manner possible. Click below to download the guide to setting up your Gateway profile


Project Documents
ICN Gateway Guide

Share this project on:

FB Twitter LinkedIn

Work Package
Documents
Full Scope EOI
Partial Scope EOI
Status
Accordian collapse

General Requirements

AccordianPlus Ecologist

Full Scope EOI

Create EOI
Closes: 
30 Apr 2024 (AEST)

Partial Scope EOI

  Open

Full Scope EOI

Closed: 
08 Mar 2024 (AEST)

Partial Scope EOI

  Closed
AccordianPlus Concrete Pumping

Full Scope EOI

Closed: 
20 Mar 2024 (AEST)

Partial Scope EOI

  Closed

Full Scope EOI

Closed: 
14 Mar 2024 (AEST)

Partial Scope EOI

  Closed
AccordianPlus Indigenous Artist

Full Scope EOI

Closed: 
31 Mar 2024 (AEST)

Partial Scope EOI

  Closed
AccordianPlus Major Concrete Supply

Full Scope EOI

Closed: 
14 Mar 2024 (AEST)

Partial Scope EOI

  Closed
AccordianPlus Minor Civil Works

Full Scope EOI

Closed: 
08 Mar 2024 (AEST)

Partial Scope EOI

  Closed
AccordianPlus Minor Roadworks

Full Scope EOI

Closed: 
04 Apr 2024 (AEST)

Partial Scope EOI

  Closed

Full Scope EOI

Closed: 
14 Mar 2024 (AEST)

Partial Scope EOI

  Closed
AccordianPlus PPE Supply

Full Scope EOI

Closed: 
08 Mar 2024 (AEST)

Partial Scope EOI

  Closed

Full Scope EOI

Closed: 
08 Mar 2024 (AEST)

Partial Scope EOI

  Closed
AccordianPlus Quarry Supplies

Full Scope EOI

Closed: 
20 Mar 2024 (AEST)

Partial Scope EOI

  Closed
AccordianPlus Reinforcing Bar

Full Scope EOI

Closed: 
14 Mar 2024 (AEST)

Partial Scope EOI

  Closed

Full Scope EOI

Closed: 
14 Mar 2024 (AEST)

Partial Scope EOI

  Closed

Full Scope EOI

Closed: 
01 Mar 2024 (AEST)

Partial Scope EOI

  Closed
AccordianPlus Survey Requirements

Full Scope EOI

Closed: 
08 Mar 2024 (AEST)

Partial Scope EOI

  Closed

Full Scope EOI

Closed: 
20 Mar 2024 (AEST)

Partial Scope EOI

  Closed
Note: The closing date/s for expressions of interest are subject to change.
PROJECT
NSW AUSTRALIA

Acciona Genus Joint Venture have been awarded the HumeLink East Portion of the Project spanning from Bannaby to Wondalga which will reinforce Transgrid's transmission network in southern NSW to improve the flow of electricity from new generation sources in southern and western NSW to major demand centres in the State, and to customers across the NEM.

Acciona Genus Joint Venture have been tasked to complete Humelink East, which includes all works and activities associated with:
1. Augmenting the existing Bannaby 500kV Substation;
2. Delivering a new 500kV double circuit transmission line connecting the augmented Bannaby 500kV substation to the interface point with HumeLink West;
3. Delivering all infrastructure required for the 500kV double circuit transmission Line; and