Collie Battery Energy Storage System (BESS)


Project at a glance


WA Australia (Onshore)
EPC - Project Construction Phase
UGL ENGINEERING PTY LIMITED

Contact Details


Robert McCullagh
Senior Consultant
+61 8 9365 7595

Neoen have engaged UGL for design and construction of the Collie Battery Energy Storage System (CLBESS) Stage 1, which will have a generation capacity of up to 219MW/877MWh.


The Collie Battery Energy Storage System Project (the Project) involves the implementation of a 219MW/877MWh battery energy storage system facility including all required mechanical, electrical, controls and civil/structural balance of plant (the Facility) located within the Collie region of Western Australia and Shire of Collie council local government area, south of Perth, approximately 5km east of Palmer, 15km northeast of Collie and 75km east of Bunbury on the eastern edge of Collie Basin. Major equipment will be installed by UGL to complete delivery of the overall facility.


Early works commenced on 15-May-23 and practical completion will be on 30-Nov-24.


Procurement will be done through competitive bidding between shortlisted vendors.

Suppliers can share that EOI through the ICN Gateway for the available packages.

Interested vendors will need to complete Felix onboarding for being included in the RFQ process.

Vendors are expected to contribute towards the AIP planned target achievement for the relevant packages. The template will be provided in RFQ pack.



Scope of the project includes

i. 219MW/877MWh BESS facility

ii. Tesla MP2XL batteries

iii. Central inverters

iv. Underground cabling

v. 330/33kV substation

vi. Associated civil works

vii. Testing and commissioning


Current engagement opportunities

Plant hire

Accommodation

Temp Fencing

Water supply

Quarry material

Cleaning

Electrical Wholesaler

Plumbing Services

PPE Supplier

Transport and logistics

O&M building

Fencing & Gates

Labour hire

General Construction Supplies

Commercial Landscaping


Share this project on:

FB Twitter LinkedIn

Work Package
Documents
Full Scope EOI
Partial Scope EOI
Status
AccordianPlus Labour Hire

Full Scope EOI

Closed: 
15 Nov 2023 (AWST)

Partial Scope EOI

Closed: 
15 Nov 2023 (AWST)
  Closed

Full Scope EOI

Closed: 
15 Nov 2023 (AWST)

Partial Scope EOI

Closed: 
15 Nov 2023 (AWST)
  Closed

Full Scope EOI

Closed: 
15 Nov 2023 (AWST)

Partial Scope EOI

Closed: 
15 Nov 2023 (AWST)
  Closed
AccordianPlus Temporary Fencing

Full Scope EOI

Closed: 
22 Dec 2023 (AWST)

Partial Scope EOI

Closed: 
22 Dec 2023 (AWST)
  Closed
AccordianPlus Fencing and Gates

Full Scope EOI

Closed: 
10 Jan 2024 (AWST)

Partial Scope EOI

Closed: 
10 Jan 2024 (AWST)
  Closed
AccordianPlus Quarry Material

Full Scope EOI

Closed: 
10 Jan 2024 (AWST)

Partial Scope EOI

Closed: 
10 Jan 2024 (AWST)
  Closed
Note: The closing date/s for expressions of interest are subject to change.