Gibson Island Project


Project at a glance


QLD Australia (Onshore)
FEED
GIBSON ISLAND H2 PTY LTD

Contact Details


Nimmi Pushparajan
Procurement Engineering Specialist
+61 7 3364 0670

Andie Pfaff
Project Officer
+61 8 9365 7442

The Gibson Island Project (Project) has been identified as an opportunity to develop a green ammonia hub in Brisbane, Queensland through construction of a green hydrogen production facility alongside an existing gas-based facility owned and run by Incitec Fertilizers Pty Limited. Incitec's facility will convert Gibson Island H2's green hydrogen into green ammonia for both domestic and export markets.


The Project, which is subject to a Final Investment Decision, is proposing a 500 mega-watt (MW) plant which shall be capable of producing 70,000 tonnes of renewable hydrogen each year.


Gibson Island H2 is seeking expressions of interest from suitably qualified contractors and suppliers for Project tendering opportunities for the hydrogen facility only.

Share this project on:

FB Twitter LinkedIn

Work Package
Documents
Full Scope EOI
Partial Scope EOI
Status

Full Scope EOI

Create EOI
Closes: 
22 Dec 2023 (AEST)

Partial Scope EOI

Create EOI
Closes: 
22 Dec 2023 (AEST)
  Open

Full Scope EOI

Closed: 
25 Jan 2023 (AEST)

Partial Scope EOI

Closed: 
25 Jan 2023 (AEST)
  Closed

Full Scope EOI

Closed: 
06 Feb 2023 (AEST)

Partial Scope EOI

Closed: 
06 Feb 2023 (AEST)
  Closed

Full Scope EOI

Closed: 
10 Feb 2023 (AEST)

Partial Scope EOI

Closed: 
10 Feb 2023 (AEST)
  Closed

Full Scope EOI

Closed: 
20 Feb 2023 (AEST)

Partial Scope EOI

Closed: 
20 Feb 2023 (AEST)
  Closed

Full Scope EOI

Closed: 
20 Feb 2023 (AEST)

Partial Scope EOI

Closed: 
20 Feb 2023 (AEST)
  Closed

Full Scope EOI

Closed: 
28 Mar 2023 (AEST)

Partial Scope EOI

Closed: 
28 Mar 2023 (AEST)
  Closed

Full Scope EOI

Closed: 
28 Mar 2023 (AEST)

Partial Scope EOI

Closed: 
28 Mar 2023 (AEST)
  Closed

Full Scope EOI

Closed: 
28 Mar 2023 (AEST)

Partial Scope EOI

Closed: 
28 Mar 2023 (AEST)
  Closed

Full Scope EOI

Closed: 
31 Mar 2023 (AEST)

Partial Scope EOI

Closed: 
31 Mar 2023 (AEST)
  Closed

Full Scope EOI

Closed: 
31 Mar 2023 (AEST)

Partial Scope EOI

Closed: 
31 Mar 2023 (AEST)
  Closed

Full Scope EOI

Closed: 
26 May 2023 (AEST)

Partial Scope EOI

Closed: 
26 May 2023 (AEST)
  Closed
AccordianPlus AUS1004P0011 Pumps

Full Scope EOI

Closed: 
26 May 2023 (AEST)

Partial Scope EOI

Closed: 
26 May 2023 (AEST)
  Closed

Full Scope EOI

Closed: 
26 May 2023 (AEST)

Partial Scope EOI

Closed: 
26 May 2023 (AEST)
  Closed

Full Scope EOI

Closed: 
09 Aug 2023 (AEST)

Partial Scope EOI

Closed: 
09 Aug 2023 (AEST)
  Closed

Full Scope EOI

Closed: 
04 Sep 2023 (AEST)

Partial Scope EOI

Closed: 
04 Sep 2023 (AEST)
  Closed

Full Scope EOI

Closed: 
18 Sep 2023 (AEST)

Partial Scope EOI

Closed: 
18 Sep 2023 (AEST)
  Closed

Full Scope EOI

Closed: 
18 Sep 2023 (AEST)

Partial Scope EOI

Closed: 
18 Sep 2023 (AEST)
  Closed

Full Scope EOI

Closed: 
18 Sep 2023 (AEST)

Partial Scope EOI

Closed: 
18 Sep 2023 (AEST)
  Closed

Full Scope EOI

Closed: 
18 Sep 2023 (AEST)

Partial Scope EOI

Closed: 
18 Sep 2023 (AEST)
  Closed

Full Scope EOI

Closed: 
18 Sep 2023 (AEST)

Partial Scope EOI

Closed: 
18 Sep 2023 (AEST)
  Closed
AccordianPlus AUS1004P0020 Statcom

Full Scope EOI

Closed: 
18 Sep 2023 (AEST)

Partial Scope EOI

Closed: 
18 Sep 2023 (AEST)
  Closed

Full Scope EOI

Closed: 
27 Sep 2023 (AEST)

Partial Scope EOI

Closed: 
27 Sep 2023 (AEST)
  Closed

Full Scope EOI

Closed: 
27 Sep 2023 (AEST)

Partial Scope EOI

Closed: 
27 Sep 2023 (AEST)
  Closed

Full Scope EOI

Closed: 
27 Sep 2023 (AEST)

Partial Scope EOI

Closed: 
27 Sep 2023 (AEST)
  Closed
Note: The closing date/s for expressions of interest are subject to change.