Project at a glance
The Project will include the following components:
(a) Western Range Run-of-Mine (ROM) Pad with single tip point for 830E autonomous haulage system (AHS) trucks and four finger stockpiles;
(b) New production hub at Western Range including offices, amenities and heavy vehicle (HV) park-up facilities;
(c) HV refuelling facility at Western Range;
(d) Heavy vehicle and light vehicle (LV) road networks, including an LV access road from the Construction Village to both Western Range and Paraburdoo Central Facilities;
(e) Surface water management structures, including pit diversion drains and levees;
(f) Water infrastructure, including bores, tanks and pump station at the Paraburdoo Mine, and water pipeline to Western Range;
(g) New single tip, indirect fed gyratory Primary Crushing facility (PCF) at Western Range and discharge conveyor;
(h) Three (3) flight (17.8 km) 4,400/6,000 tph Overland Conveyor (OLC) to Paraburdoo Central Facilities;
(i) Modification to the existing Coarse Ore Stockpile (COS) at Paraburdoo Central Facilities;
(j) Upgraded scalping screens at Paraburdoo Central Facilities;
(k) Modifications and upgrades to existing plant at Paraburdoo Central Facilities;
(l) 33 kV overhead transmission lines and associated infrastructure
(m) Communications infrastructure, including four radio base stations; and
(n) 1,600 room Construction Accommodation Village.
In the Pilbara region of Western Australia, Rio Tinto operates the world's largest integrated portfolio of iron ore assets with industry-leading margins. Rio Tinto is well positioned to benefit from continuing demand across China and the developing world. The premium product suite, including our flagship Pilbara blend, drives strong customer relationships and is supported by technical and commercial marketing expertise. The business continues to be a proud leader in automated mining technologies.
The Rio Tinto BS1 project is a greenfield satellite mine development to the Brockman 4 (B4) mine site, located within the Greater Brockman Hub in the West Pilbara, approximately 8km north of the existing B4 operations. The BS1 project is located on the country of the Puutu Kunti Kurrama people (PKKP), and on the country of the traditional owners of Muntulgura Guruma people (MG).
The Hope Downs 1 Sustaining project includes the development of the Hope Downs 2 and Bedded Hill Top deposits located in the Hope Downs 1 Hub in the East Pilbara.