Navy Capability Infrastructure Subprogram - 3 (NCIS-3) Building Works Stage 1



Contact Details


Andie Pfaff
ICN Coordinator
+61 8 9365 7735
 CONTACT EMAIL

  Locations: WA Australia
  Project Status: Live
  Project Owner LENDLEASE BUILDING CONTRACTORS PTY LIMITED

Project Details


Location

HMAS Stirling and Henderson, Western Australia


Sub-projects:

NCIS-3 Building Works Stage 1, comprising:

  • N2262 SEA1654-3 Maritime Operational Support Capability Facilities Project
  • N2263 SEA1180-1 Arafura Class Offshore Patrol Vessels Facilities Project
  • N2265 SEA5000-1 Hunter Class Frigates Facilities Project


Project Objectives:

  • Deliver estate infrastructure that fulfils future Navy capability requirements, safely, securely and compliantly.
  • Maximise local industry and indigenous business enterprise participation.


Project Details:

The project will provide the first stage of essential, land-based facilities and infrastructure requirements at HMAS Stirling (Garden Island) and Henderson, Western Australia, primarily to support the introduction into service of the Maritime Operational Support Capability (MOSC), the Arafura Class Offshore Patrol Vessel (ACOPV) and the Hunter Class Frigate (HCF).

Works will include facilities with the following end use functions;

  • Office Accommodation
  • Warehousing
  • Living-in Accommodation (LIA)
  • Supporting Services Infrastructure


Indicative Timing

Expression of Interest – February 2021
Request for Tender – April 2021
Project Complete – Late 2024
Subcontractors are encouraged to register for further communications regarding the project including for notification of the commencement of formal expression of interest for the project via the ICN Gateway Website (https://ncis-3.icn.org.au/)


Subcontractor / Supplier Requirements:

  • Compliance with the Code for Tendering and Performance of Building Work 2016 The Code for the Tendering and Performance of
    Building Work 2016 applies to the Building Work associated with this project. By submitting an expression of interest in, or tender for, this project, you will become subject to the Code for the Tendering and Performance of Building Work 2016.
  • Demonstrating how local benefit and participation will be maximised will be considered in assessment criteria
  • Demonstrating commitment to indigenous businesses and/or those with indigenous employees will be considered in assessment criteria
  • Lendlease Building Contractors Pty Limited has been engaged under the Managing Contractor Contract model. For more information on this form of contract please visit https://www.defence.gov.au/EstateManagement/

To submit the Expression of Interest (EOI), please click on the Full Scope EOI and follow the prompts. Download the ITR (Invitation To Register) document, filling in the required forms (pages 18-33) and reuploading as a pdf. The EOI closes strictly on 19th March 2021.


More Information:

Visit: https://ncis-3.icn.org.au/
Email: wa.ncis3@lendlease.com
Phone: 08 9223 2888
Local Industry Participation Office
(Note due to Covid-19 the office is currently closed – please email or call)
Podium Level, 152-158 St Georges Terrace
Perth, Western Australia, 6009

SHOW LESS

Work Packages


To edit or submit an expression of interest, select the icon next to the package you are interested in.
Note: The closing date/s for expressions of interest shown below are subject to change.

OPEN LISTINGS    AWARDED    CLOSED LISTINGS    OTHER
OPEN    INCOMPLETE    COMPLETE

STANDARD LISTINGS        ▲ CONTRACT
STATUS       ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
Access Flooring24 Feb 202119 Mar 202119 Mar 2021
Please refer to the Documents for further details
Blockwork24 Feb 202119 Mar 202119 Mar 2021
Please refer to Documents for further details
Builders Works24 Feb 202119 Mar 202119 Mar 2021
Please refer to the Documents for further details
Carpentry/Doors24 Feb 202119 Mar 202119 Mar 2021
Please refer to the Documents for further details
Carpet and Vinyl24 Feb 202119 Mar 202119 Mar 2021
Please refer to the Documents for further details
Civil Works24 Feb 202119 Mar 202119 Mar 2021
Please refer to the Documents for further details
Commercial Kitchen24 Feb 202119 Mar 202119 Mar 2021
Please refer to the Documents for further details
Communication24 Feb 202119 Mar 202119 Mar 2021
Please refer to the Documents for further details
Concrete Structures23 Feb 202119 Mar 202119 Mar 2021
Please refer to Documents for further details
Concrete Supply24 Feb 202119 Mar 202119 Mar 2021
Please refer to the Documents for further details
Curtains/Blinds24 Feb 202119 Mar 202119 Mar 2021
Please refer to the Documents for further details
Electrical24 Feb 202119 Mar 202119 Mar 2021
Please refer to the Documents for further details
External Works24 Feb 202119 Mar 202119 Mar 2021
Please refer to the Documents for further details
Facade Glazing24 Feb 202119 Mar 202119 Mar 2021
Please refer to the Documents for further details
Final Clean24 Feb 202119 Mar 202119 Mar 2021
Please refer to the Documents for further details
Fire Services23 Feb 202119 Mar 202119 Mar 2021
Please refer to Documents for further details
Formwork24 Feb 202119 Mar 202119 Mar 2021
Please refer to Documents for further details
Furniture Fixtures and Equipment/ Workstations24 Feb 202119 Mar 202119 Mar 2021
Please refer to the Documents for further details
Hydraulic24 Feb 202119 Mar 202119 Mar 2021
Please refer to the Documents for further details
Inground Services23 Feb 202119 Mar 202119 Mar 2021
Please refer to Documents for further details
Joinery23 Feb 202119 Mar 202119 Mar 2021
Please refer to Documents for further details
Mechanical23 Feb 202119 Mar 202119 Mar 2021
Please refer to Documents for further details
Metal Work23 Feb 202119 Mar 202119 Mar 2021
Please refer to Documents for further details
Painting24 Feb 202119 Mar 202119 Mar 2021
Please refer to the Documents for further details
Partitions/Ceilings24 Feb 202119 Mar 202119 Mar 2021
Please refer to the Documents for further details
Post Tensioning24 Feb 202119 Mar 202119 Mar 2021
Please refer to the Documents for further details
Precast Concrete24 Feb 202119 Mar 202119 Mar 2021
Please refer to the Documents for further details
Reinforcement24 Feb 202119 Mar 202119 Mar 2021
Please refer to the Documents for further details
Roofing24 Feb 202119 Mar 202119 Mar 2021
Please refer to Documents for further details
Security Services24 Feb 202119 Mar 202119 Mar 2021
Please refer to the Documents for further details
Signage23 Feb 202119 Mar 202119 Mar 2021
Please refer to Documents for further details
Structural Steel24 Feb 202119 Mar 202119 Mar 2021
Please refer to the Documents for further details
Survey24 Feb 202119 Mar 202119 Mar 2021
Please refer to the Documents for further details
Tiling23 Feb 202119 Mar 202119 Mar 2021
Please refer to Documents for further details
Waterproofing/Epoxy24 Feb 202119 Mar 202119 Mar 2021
Please refer to the Documents for further details