Caboolture Hospital Redevelopment



Contact Details


Jatin Patel
Procurement Engineering Specialist
+61 7 3364 0670
 CONTACT EMAIL

  Locations: QLD Australia
  Project Value: A$225m
  Project Status: Detailed Design (in progress) & Early Enabling Works (in progress)
  Project Owner LENDLEASE BUILDING PTY LIMITED

Project Details


Caboolture hospital provides services to a rapidly growing region and population. There is a requirement to expand the breadth and depth of services available, to improve local access to services, better align the service profile with projected demand, and to provide improved environment for patients, families, and staff.


Metro North Hospital and Health Service (Metro North) is the project principal/client and Lendlease Building has been appointed as the Managing Contractor for Stage 1 of the Caboolture Hospital Redevelopment project which includes detailed design and construction responsibility.


Project delivery objectives include delivery of a new Clinical Services Building, refurbishment to parts of the existing Caboolture Hospital and provision of a new Multi Story Carpark – providing the latest in standards and technologies to meet the health demands of the Caboolture region.



 A summary of the key project objectives & outcomes is as follows:

  • meet the needs of the Caboolture Hospital catchment population
  • provide support for patients and their families by reducing stress for example, efficient wayfinding, positive distraction, natural light and views and access to external space
  • provide for efficient patient, staff and service flows - the design must facilitate the maintenance of patient privacy and dignity both internally and externally
  • support workforce recruitment, retention and development
  • facilitate avoidance of healthcare associated infection
  • maintain delivery of fully functional adjoining services during the development and construction of the project while minimising the impact of construction on Hospital staff, patients and public
  • be considerate of the existing hospital / environment along with providing a high quality environment that responds to the service needs and priorities on site
  • reduce the overall environmental impact, aiming for a minimum of 4 star green star rating
  • provide value for money in capital and recurrent costs without compromising service provision
  • provide simple, cost effective, functional solutions – aiming for minimal recurrent costs
  • consider life cycle costing parameters for engineering systems, materials and finishes.


The client Metro North and the managing contractor Lendlease are seeking quality subcontractors to partner with in the delivery of these key project objectives and we look forward to receiving your expressions of interest submissions for this project.


The Caboolture redevelopment project will comprise the following work areas and scope of work:



EARLY WORKS

These include the essential works required to divert existing services, alter current carparking configuration and alter existing access routes to clear the footprint for the main redevelopment and MSCP. It will also include the establishment of a new intersection on McKean Street. 


Separable Portion 1- New Clinical Services Building (CSB)

These include the construction of a new four storey clinical services building (CSB) (with a fifth floor for plant) The new CSB will provide new operating theatres, additional ward space and new Emergency Department.


Separable Portion 2 - Multi-storey Carpark (MSCP) Works

The MSCP scope includes the provision of a multi-level reinforced concrete structure with provision  for a total of 1,039 new car spaces.


Separable Portion 3 -  Refurbishment Works

This component of the works involves the relocation and refurbishment of multiple departments including, Emergency Department, Medical Day Unit, Theatres, Pathology, CSD (Central Sterilising Department) and Pharmacy within the existing clinical services building.



DELIVERY SCHEDULE


Overall Project

Present – May 2023


Detailed design

Currently in progress and is anticipated to be complete by Mid-August 2020


Early Works

Construction activities have commenced onsite with site establishment, services diversion and site wide enabling works in progress. It is anticipated enabling works will be complete by mid-February 2021


Separable Portion 1- New Clinical Services Building (CSB)

Procurement of trades for the new CSB will commence late June 2020 and run through until mid-October 2021.

Construction Works to the new CSB are due to commence in Mid October 2020 and run through until late July 2022


Separable Portion 2 - Multi-storey Carpark (MSCP) Works

Procurement of trades for the new MSCP will commence June 2020 and run through until mid-October 2021

Construction Works to the new MSCP are due to commence in Mid October 2020 and run through until late July 2022


Separable Portion 3 -  Refurbishment Works

Procurement of trades for the Refurbishment Works will commence June 2020 and run through until mid-October 2021

Construction Works to the Refurbishment areas are due to commence in August 2022 and run through until May 2023



EXPRESSIONS OF INTEREST

Lendlease encourages local industry interested in supplying to the project to register an expression of interest (EOI) through the ICN Gateway webpage. Information on specific supply opportunities will be communicated on the ICN Gateway project page allowing industry to register its interest against them during EOI open period.


Please ensure that:

  • Your company profile on the ICN Gateway is complete, up-to-date and accurate including electing to be notified via e-mail of supply opportunities.
  • You register your interest as a full or partial scope supplier (where applicable), and
  • You respond to all project and work package-specific questions.
     

It is important that businesses submitting an EOI are aware that their submission does not guarantee that they will progress further in the procurement process. Only companies that can demonstrate capability and capacity in accordance with CHRP project requirements will be invited to pre-qualify for specific opportunities.


Businesses which demonstrate local benefits and demonstrate ability to meet other qualification criteria will be highly regarded.



FURTHER ASSISTANCE

 Lendlease encourage local industry to contact the ICN Queensland in the first instance to seek assistance with the EOI process.


The Lendlease project team can be emailed at: CabooltureHospital@lendlease.com

SHOW LESS

Work Packages


To edit or submit an expression of interest, select the icon next to the package you are interested in.
Note: The closing date/s for expressions of interest shown below are subject to change.

OPEN LISTINGS    AWARDED    CLOSED LISTINGS    OTHER
OPEN    INCOMPLETE    COMPLETE

STANDARD LISTINGS        ▲ CONTRACT
STATUS       ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
HV Services (Inground Pacakge)31 Jul 202014 Aug 202014 Aug 2020
-Supply & Installation inground component of the High Voltage electrical
services scope.
Hydraulic Services (Temporary and Main Works) Package31 Jul 202014 Aug 202014 Aug 2020
-Supply, installation, relocation & removal of all temporary water supplies, water points, connections to temporary amenities and drinking fountains throughout the project.
-Supply & Installation of the hydraulics services inground, including inground fire mains & booster cabinets.
-Supply and installation of all hydraulics services scope including supply of sanitary hardware.
Labour Hire31 Jul 202014 Aug 202014 Aug 2020
Labour Hire
Detailed Excavation and Foundations31 Jul 202017 Aug 202017 Aug 2020
-Detailed Excavation for foundations
-Formwork
-Pile trimming
-Reo supply and fix
-Concrete supply, place and Finish
-Below ground waterproofing
Post Tensioning31 Jul 202021 Aug 202021 Aug 2020
-Design and construct Post tension system to CSB & Multi-story carpark suspended slabs
-Option to provide full concrete structure re-design within this trade package
Vertical Transportation31 Jul 202021 Aug 202021 Aug 2020
-Supply and install lifts
Concrete Pump Place and Finish31 Jul 202004 Sep 202004 Sep 2020
-Concrete place and finish to the new CSB and Multi-story carpark
-Supply concrete pumping equipment
Concrete Supply31 Jul 202004 Sep 202004 Sep 2020
-Concrete supply to CSB and Multi-story concrete structure, includes all vertical
and horizontal concrete structure elements.
Electrical and Communications Services (Main works Temporary Works package)31 Jul 202004 Sep 202004 Sep 2020
-Supply, Installation, relocation and removal of all temporary power & lighting
circuits for the project.
-Supply, installation, relocation, periodic testing/certification and removal of all
temporary power boards, distribution boards, access lighting and exit lights.
-Supply and Installation of all Inground electrical services scope including
installation and commissioning of all novated procurement items.
-Supply and Installation of all Inground communications services scope.
-Supply and Installation of all electrical services scope including installation and
commissioning of novated procurement items.
-Supply and Installation of communications services scope.
Facade Cladding31 Jul 202004 Sep 202004 Sep 2020
Supply & Install new cladding (CFC/Aluminium panels/Prefinished FC or similar) including all necessary secondary framing
Facade Glazing31 Jul 202004 Sep 202004 Sep 2020
-Supply and install Insulated Glass units (IGU's) and pre glazed face panels
(External)
Fire Protection Services31 Jul 202004 Sep 202004 Sep 2020
-Undertake wet & dry fire isolations as required to execute the works.
-Supply install and periodic test of fire extinguishers.
-Supply, install, relocate and remove any temporary detection, EWIS systems as required.
-Supply and install fire detectors, alarms/EWIS, sprinklers and VESDA.
-Supply and install of new fire panels.
Formwork31 Jul 202004 Sep 202004 Sep 2020
-Supply and install formwork to the CSB building & multi-level carpark, includes all vertical and horizontal concrete structure elements
Mechanical Services (Main Works) Package31 Jul 202004 Sep 202004 Sep 2020
-Supply and install all mechanical services scope including the supply, install and commissioning mechanical equipment.
-Demolition of redundant mechanical services
-Supply and install all mechanical-electrical items including MSSB's
-Provide temporary ventilation strategies during refurbishment works.
Reinforcement Fixing31 Jul 202004 Sep 202004 Sep 2020
-Reinforcement fix to CSB & Multi-story concrete structure, includes all vertical and horizontal concrete structure elements.
Reinforcement Supply31 Jul 202004 Sep 202004 Sep 2020
-Reinforcement Supply
Loading Bays31 Jul 202011 Sep 202011 Sep 2020
-Supply and install retractable loading bays
Scaffolding31 Jul 202011 Sep 202011 Sep 2020
-Expansion works - Temporary access and perimeter edge protection to structure, voids, stairs and lift shafts, scaffold loading bays.
-Temporary egress gantries
Masonry31 Jul 202025 Sep 202025 Sep 2020
-Supply and installation of masonry
Medical Gas (Main Works Package) Package31 Jul 202025 Sep 202025 Sep 2020
-Supply and install all medical gas services scope including the supply, install and commissioning of all pipework and equipment.
Metal Deck Roofing and Wall Cladding31 Jul 202025 Sep 202025 Sep 2020
-Metal deck roofing and wall cladding including roof access systems
Metalwork31 Jul 202025 Sep 202025 Sep 2020
-Supply and installation of miscellaneous metalwork
Pneumatic Tube Package31 Jul 202025 Sep 202025 Sep 2020
-Supply and install Pneumatic tube trade package
Structural Steel31 Jul 202025 Sep 202025 Sep 2020
-Operable wall steel supports, penetration lintels & slab strengthening.
-CSB & MSCP roof structure, facade mullions, girts & mullions, facade screen framing & catwalks.
Metal Louvers31 Jul 202009 Oct 202009 Oct 2020
Supply and install metal louvers
Carpet and Vinyl Supply and Install31 Jul 202030 Oct 202030 Oct 2020
-Carpet and vinyl supply and install including floor preparation, sundries, edge
strips, stair nosings and the like.
Ceilings Partitions Doors and Hardware31 Jul 202030 Oct 202030 Oct 2020
-Supply and install all internal plasterboard and glazed partitions, toilet partitions, ceilings, doors, frames, door hardware.
-Supply and installation of Amenities fitments - toilet roll holders, soap
dispensers, grab rails, hand dryers and the like.
Demolition31 Jul 202030 Oct 202030 Oct 2020
Internal strip out of refurbishment areas within the existing hospital building including but not limited to walls, ceilings, joinery and floor finishes
Operable Walls31 Jul 202030 Oct 202030 Oct 2020
-Supply and install Operable walls
Roller Doors31 Jul 202030 Oct 202030 Oct 2020
Roller Doors supply and install
Tiling31 Jul 202030 Oct 202030 Oct 2020
-Tiling supply and lay wall and floor tiling, levelling screed, exp joints. Includes wet area waterproofing.
Security BMS and ICT31 Jul 202020 Nov 202020 Nov 2020
-Supply and install Security, Building Management Systems(BMS) and Information and communications technology (ICT)
Furniture Fixtures and Equipment (FF and E) Supply and Install31 Jul 202027 Nov 202027 Nov 2020
-Supply and install FF and E
-Installation of Novated FF and E
-Relocate existing FF and E
Major Medical Equipment Supply and Install31 Jul 202027 Nov 202027 Nov 2020
-Supply and install Major Medical Equipment (MME)
Waterproofing and Epoxy Flooring31 Jul 202027 Nov 202027 Nov 2020
-Waterproofing & epoxy floor finishes
Joinery31 Jul 202030 Nov 202030 Nov 2020
-Joinery supply and install.
Painting31 Jul 202030 Nov 202030 Nov 2020
-Repair, patch and painting to existing plasterboard walls, ceilings, soffits, doors and frames. Includes for providing access for all internal surfaces.
-Painting to new finishes
Curtains and Blinds31 Jul 202018 Dec 202018 Dec 2020
-Curtains and blinds supply and install
Final Clean31 Jul 202018 Dec 202018 Dec 2020
-Final clean
General Expression of Interest31 Jul 202018 Dec 202018 Dec 2020
Businesses or providers not specifically covered by the trade packages listed on the
ICN
Landscaping Hard Soft and Irrigation31 Jul 202018 Dec 202018 Dec 2020
-Supply and place all hard and soft landscaping including irrigation, street furniture, concrete pavements, bollards in landscaping pavements.
Medical Pendants31 Jul 202018 Dec 202018 Dec 2020
Supply and install medical pendants
Signage Internal and External31 Jul 202018 Dec 202018 Dec 2020
-Supply and install all new internal and external signage
Civil Works10 Jul 202024 Jul 2020 
  
- Site clearing & stripping to CSB and MSCP
- Bulk excavation
- Piling platform and hardstands.
- Trunk Sewer & stormwater
- Site environmental controls & dewatering
General Waste - Rubbish Removal10 Jul 202024 Jul 2020 
  
Bin hire, emptying and disposal. Disposal & Recycling in accordance with
statutory & Lendlease recycling targets. Scope Excludes demolition waste & civil
works spoil.
Piling10 Jul 202024 Jul 2020 
  
Design and construct piling solution
Precast10 Jul 202024 Jul 2020 
  
Supply and install hollow core planks and beams
Survey and Setting Out Including Dilapidation Report10 Jul 202024 Jul 2020 
  
- Supply of base survey gridlines & datum's on each level of the new buildings
and existing building as required
- Existing services Setout
- As construed survey
- Dilapidation survey and report
Time Lapse Camera10 Jul 202024 Jul 2020 
  
Supply, Installation and Maintenance of Time Lapse Camera
Tower Cranes and Hoists10 Jul 202024 Jul 2020 
  
- Design of structural supports, erect, hire and dismantle of tower crane and
hoists
- Labour hire for crane driver and dogmen
- Hire of ancillary crane equipment eg. first aid box
Traffic Control10 Jul 202024 Jul 2020 
  
Traffic Control Services to the site - including preparation and submission of
traffic control permits and preparation of traffic management plans and
traffic guidance schemes.