Secure Energy JV

EnergyConnect - SecureEnergy

Overview

About the Project Contractor

SecureEnergy (a venture of Elecnor Australia) was awarded the engineering, construction and procurement (EPC) contract for a new 700km 330kv transmission line extending from Wagga Wagga NSW to the South Australian border of Transgrid's EnergyConnect project in June 2021. Construction on this project started in 2022 and is anticipated to be completed within the next 12 months.
Throughout the delivery phase, Elecnor has been committed to providing economic benefit to the local and Indigenous communities along the project route. As of May 2025, almost $240 million has been spent procuring good and services from businesses and suppliers based in the local government areas, and almost $18 m has been spent with First Nations groups and businesses.
Elecnor Australia aims to maximise procurement of local suppliers, where possible, prioritised by three levels of business location:

Level 1

Regional Development Australia - Riverina

Regional Development Australia - Murray

Mildura Regional Development

Local Aboriginal Land Councils Areas including Language Group areas intersected by the Project route

Level 2

Postcodes within NSW, excluding Level 1

Level 3

Postcodes within Australia, excluding Levels 1 and 2


To submit an expression of interest for work on EnergyConnect, please email your business capability statement to: sejvprocurement@elecnor.es

Reference documents for prospective suppliers and partners

* Subcontractor Pre-Qualification requirements
https://www.secureenergyjv.com.au/wp-content/uploads/2024/12/SecureEnergy-JV-Subcontractor-Pre-Qualification-Questionnaire.pdf


* Substation Primary Design Standards
https://www.transgrid.com.au/media/zgogqoqg/1-1-substation-primary-design-standard-rev-2.pdf


* Transmission Line Design Standards
https://www.transgrid.com.au/media/2wfirnkf/1-3-transmission-line-design-standard-rev-2.pdf


* Supplier Information Guide
https://www.secureenergyjv.com.au/wp-content/uploads/2022/05/45860-CM-GD-G-0001-Supplier-Information-Guide.pdf



EnergyConnect - SecureEnergy

Secure Energy JV

location_on

NSW Australia


Project Primary Contact
person_outline
Geoff Reardon
badge
Regional Manager - Murray/Riverina NSW
phone
+61 04 0263 2027
mail Send Email