Western Turner Syncline Phase 2 Stage 2 Project



Contact Details


  Ray Loh
  +61 8 9365 7499
 CONTACT EMAIL

  Locations: WA Australia (Onshore)
  Project Status: Feasibility Study
  Project Owner RIO TINTO LIMITED

Project Details


The Project, the subject of a feasibility study, involves the expansion and development of iron ore deposits to sustain the existing Greater Tom Price production. The Tom Price mine is located approximately 32 kilometres west of Tom Price.


The Project includes the following components;

a) ROM pad and primary crushing facility; 
b) the new 13km overland conveyor transports primary crushed ore from B1 and S17 (WTS2) to S10 (WTS1). Ore from WTS2 and WTS1 is then transported to Tom Price on existing overland conveyors;  
c) modifications to the existing Tom Price dry crushing and screening processing plant; 
d) non-process infrastructure; 
e) ammonium nitrate and fuel oil (ANFO) facility; 
f) 33kV power transmission network; 
g) communications infrastructure; 
h) water supply and reticulation; 
i) heavy and light vehicle roads; and 
j) upgrades to existing water feed infrastructure in Tom Price town. 


It is a Rio Tinto requirement that standards utilised are either Australian or internationally recognised equivalents, unless otherwise justified due to specific technological, commercial, intellectual property or similar requirements. All requests for proposal (RFP), tender and contract document references will stipulate any standards requirements. In certain circumstances, materials specifications in RFPs may be met by using either Australian or internationally recognised standards. Otherwise it is the project’s intent that standards in RFPs do not seek to exclude Australian business from participating in Tier 1 supply opportunities.


Delivery schedule: Subject to approval, construction of the project will take approximately two years.


Potential supplier information:

SHOW LESS

Work Packages


To submit an expression of interest, select the icon next to the work package scope you are interested in.
Note: The closing date/s for expressions of interest shown below are subject to change.

OPEN LISTINGS    AWARDED    CLOSED LISTINGS    OTHER
OPEN FOR EOI    INCOMPLETE EOI    EOI COMPLETED
STATUS   MISCELLANEOUS    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
Isolation Gates27 Nov 1913 Dec 1913 Dec 19
Please refer to the scope of works document for details of the package.
Low Profile Belt Feeders27 Nov 1913 Dec 1913 Dec 19
Please refer to the scope of works document for details of the package.
Conveyor Drives27 Nov 1927 Dec 1927 Dec 19
Please refer to the scope of works document for details of the package.
Paramedical Services3 Dec 193 Jan 203 Jan 20
Please refer to SOW for further details pertaining to this package.
Modular Buildings for Non-Process Infrastructure (NPI)9 Dec 1910 Jan 2010 Jan 20
Please refer to SOW for further details pertaining to package.
Supply and Manufacture of Transformers3 Dec 1910 Jan 2010 Jan 20
Please refer to SOW for further details pertaining to this package.
Supply and Manufacture of Vibrating Screens9 Dec 1910 Jan 2010 Jan 20
Please refer to SOW for further details pertaining to this package.
HV VSDs and HV Motors9 Dec 1917 Jan 2017 Jan 20
Please refer to SOW for further details pertaining to this package.
SMP E and I Brownfields26 Nov 196 Dec 196 Dec 19
Please refer to the scope of works document for details of the package