Mount Keith Debottlenecking



Contact Details


  Linus O'Brien
  +61 8 9365 7556
 CONTACT EMAIL

  Locations: WA Australia (Onshore)
  Project Status: Concept Phase
  Project Owner BHP BILLITON NICKEL WEST PTY LTD

Project Details


BHP Nickel West is currently studying options to debottleneck processing infrastructure at its Mount Keith operation. The development is currently in concept phase, which may comprise of the following:


Processing

Inflow
- Discharge from primary crusher to COS

- Reclaim from COS via feeder(s) discharge onto inflow conveyor


Mill

- Twin Pinion, single stage semi-autonomous grinding (SAG) mill

- 12-pack cyclone cluster

- Double-deck pebble discharge screen

- Liner handler


Outflow
- Cyclone overflow trash screen

- Particle size analyser

- Transfer pumps and hoppers



NPI

Sub-station
- HV 132 kV > 11 kV sub-station, MCC and switch yard

- Reticulation to processing infrastructure


Buildings
- Relocation of existing demountable offices


 

The scope of this package will extend from early design to completion of construction, inclusive of engineering and design, procurement, construction, construction services and reporting.


BHP Nickel West is seeking expressions of interest from Contractors who are experienced in performing similar scope (under a Design & Construct or Construct Only model) whom are willing to engage in a competitive Request for Tender (RFT) process.


For more information about BHP please refer to the company website www.bhp.com

SHOW LESS

Work Packages


There are currently no open work packages for this project.
Note: The closing date/s for expressions of interest shown below are subject to change.

OPEN LISTINGS    AWARDED    CLOSED LISTINGS    OTHER
OPEN FOR EOI    INCOMPLETE EOI    EOI COMPLETED
STATUS       ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
Mt Keith Project Debottlenecking EOI12 Nov 1910 Dec 1910 Dec 19
Please refer to the scope of works document for details of the package