BHP Olympic Dam Accommodation Project



Contact Details


  Merril Kirk
  (08) 8303 2383
 CONTACT EMAIL

  Eddie Ivar, ICN SA
  (08) 8226 3011
 CONTACT EMAIL

  Locations: SA Australia
  Project Status: Investigation Phase Study (IPS)
  Project Owner BHP Olympic Dam Corporation Pty Ltd (BHP)

Project Details


The Olympic Dam Accommodation Project is reviewing options to provide accommodation facilities that are of suitable quality and quantity to support operations over the next decade and beyond.


Accommodation facilities for Olympic Dam's commute workforce are provided in two camps:

1) Olympic Dam Village (2500 rooms); and

2) Roxby Downs Village (500 rooms).


Stage 1 of the Project will supply additional rooms (up to 1500 rooms) and associated facilities with rooms and facilities available from March 2021.


The purpose of the Early Contractor Engagement (ECI) Services is for the contractor to plan and perform initial designs to enable the Company to contract with a single contractor to perform either a Design and Construct (D&C), Build Own Operate (BOO) or a Build Own Operate Transfer (BOOT) works and/or services. 


The contractor will be required to develop its design to a level which will enable the contractor to deliver a guaranteed schedule and maximum cost for the accommodation. The contractor will be performing the services in parallel with other contractors. The Company will select one (1) contractor to award a D&C or BOO or BOOT for the design, construction and potentially operation of the facilities, upon completion of the ECI process.



SHOW LESS

Work Packages


To submit an expression of interest, select the icon next to the work package scope you are interested in.
Note: The closing date/s for expressions of interest shown below are subject to change.

OPEN LISTINGS    AWARDED    CLOSED LISTINGS    OTHER
OPEN FOR EOI    INCOMPLETE EOI    EOI COMPLETED
STATUS   ACCOMMODATION VILLAGE ECI    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
ACM015 - Accommodation Early Contractor Involvement20 Aug 193 Sep 19 
BHP is seeking expressions of interest from contractors who are experienced in performing the
design, construction and operation of accommodation facilities whom are willing to engage in a
competitive Early Contractor Involvement (ECI) process to support the Company's Selection
Phase Study (SPS) and provide deliverables to facilitate the further engagement of the ECI
Contractor(s).

See attached file for further information.
STATUS   MISCELLANEOUS    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
BHP Olympic Dam Accommodation Project - Any (subcontract) Opportunities16 Aug 1931 Dec 19 
Express interest for any opportunities that may arise for this project.