  Project Value: $30 million
  Project Status: Open
  Project Owner SIGNATURE ONFARM PTY LTD

Project Details


Signature Onfarm is a unique, greenfield, 5,500sqm beef processing facility being built to strengthen the value chain in the local, Central Queensland region. Personnel will be able to reside on-property in a 70-person maximum, rural accommodation village with support services.


It will bring beef processing to the location of cattle production, improve district capabilities and outcomes, and optimise returns back to producers at farm gate. High-value production, at a rate of 200 head per day, will deliver hand-crafted beef products to domestic and international customers.


Signature Onfarm have just completed design and construction drawings, to building approval issue standard. The project is being broken-up into several construction components (work packages), to be completed individually, and supervised by a builder acting as an agent for the proponent. Signature Onfarm are seeking expressions of interest on the current, open work packages - listed below. Estimated building start date is during the 3rd quarter (August) of 2019, with 12-month build time.


Timing


  • Detailed engineering and construction design is complete
  • Final investment decision is expected mid-2019
  • Commencement of construction is expected in 3rd Quarter (August), 2019
    • Construction is anticipated to take 12 months


    About the Proponent


    Signature Onfarm will manage the beef processing plant, integrating the value chain created by the Angus family. 


    Angus Pastoral Company run a cattle herd of 35,000 head, bearing years of finely tuned genetics, across 160,000 hectares in Central and Northern Queensland. 18 years ago, they began selling their own branded beef products, creating Signature Beef to market them. Today customers span 30 countries and the height of Australia’s eastern seaboard. 


    Building their own abattoir reduces the company’s risk of continuing to outsource processing, offers greater mastery over production, and expands the opportunities of their home region.  


    Expressions of Interest (EOI)


    • This is an initial EOI submission process to create a shortlist and pre-qualify capable trade contractors or suppliers for the Signature Onfarm project.
    • Current work packages open for EOI are listed below. 
    • To register your interest for a scope(s) of work, submit an EOI, but first set-up a company profile on the ICN Gateway. Click here for help. 
    • Your company description is used to assess your ability to complete scopes of work when you submit an EOI. Ensuring that you invest the time and energy to represent it most accurately, will give you the best chance of being shortlisted.
    • Submitting an EOI does not guarantee procurement from your company. It demonstrates how your capability and capacity align with the project standards. Only shortlisted businesses may be invited to prepare a quotation for specific supply opportunities.


    For further assistance, contact ICN in the first instance to help with the EOI process.

    SHOW LESS

    Work Packages


    There are currently no open work packages for this project.
    Note: The closing date/s for expressions of interest shown below are subject to change.

    OPEN LISTINGS    AWARDED    CLOSED LISTINGS    OTHER
    OPEN FOR EOI    INCOMPLETE EOI    EOI COMPLETED
    STATUS   1. ACCOMMODATION VILLAGE    ▲ CONTRACT OPENS FULL
    SCOPE
    CLOSES
    PARTIAL
    SCOPE
    CLOSES
    DOCS FULL
    SCOPE
    EOI
    PARTIAL
    SCOPE
    EOI
    Accommodation Village - Permanent and Modular16 May 1930 Jun 1930 Jun 19
    Scope of works includes the supply and establishment of a permanent, modular accommodation village onsite for minimum 50 people.

    Please refer to the attached PDF document for a detailed scope of works.

    Respondents are advised to allow a minimum of 30 minutes to complete this EOI.
    STATUS   2. SITE SERVICES    ▲ CONTRACT OPENS FULL
    SCOPE
    CLOSES
    PARTIAL
    SCOPE
    CLOSES
    DOCS FULL
    SCOPE
    EOI
    PARTIAL
    SCOPE
    EOI
    Air Compressors16 May 1930 Jun 1930 Jun 19
    Scope of works involves the supply and set-up of air compressors.

    Please refer to the attached PDF document for a detailed scope of works.

    Respondents are advised to allow a minimum of 30 minutes to complete this EOI.
    Generators16 May 1930 Jun 1930 Jun 19
    Scope of works involves the supply and set-up of generators for regular and continuous electrical supply.

    Please refer to the attached PDF document for a detailed scope of works.

    Respondents are advised to allow a minimum of 30 minutes to complete this EOI.
    Water Supply (Holding Storage and Pumping)16 May 1930 Jun 1930 Jun 19
    Scope of works involves the supply, holding/storage and pumping of water.

    Please refer to the attached PDF document for a detailed scope of works.

    Respondents are advised to allow a minimum of 30 minutes to complete this EOI.
    STATUS   3. CONCRETE    ▲ CONTRACT OPENS FULL
    SCOPE
    CLOSES
    PARTIAL
    SCOPE
    CLOSES
    DOCS FULL
    SCOPE
    EOI
    PARTIAL
    SCOPE
    EOI
    Concrete - Supply and Batching16 May 1930 Jun 1930 Jun 19
    Scope of works involves the supply and batching of all concrete for the 5,500sqm main plant, access points, village and ancillary works sites (minimum 1,000sqm).

    Please refer to the attached PDF document for a detailed scope of works.

    Respondents are advised to allow a minimum of 30 minutes to complete this EOI.
    STATUS   4. PLANT CONSTRUCTION    ▲ CONTRACT OPENS FULL
    SCOPE
    CLOSES
    PARTIAL
    SCOPE
    CLOSES
    DOCS FULL
    SCOPE
    EOI
    PARTIAL
    SCOPE
    EOI
    Concrete - Installation16 May 1930 Jun 1930 Jun 19
    Scope of works involves the forming up and pouring of footings, main concrete slab, small tilt-ups, and retaining walls.

    Please refer to the attached PDF document for a detailed scope of works.

    Respondents are advised to allow a minimum of 30 minutes to complete this EOI.
    Floor Coatings16 May 1930 Jun 1930 Jun 19
    Scope of works involves the supply and application of floor coatings throughout the plant.

    Please refer to the attached PDF document for a detailed scope of works.

    Respondents are advised to allow a minimum of 30 minutes to complete this EOI.
    Insulation and Cool Room Panelling16 May 1930 Jun 1930 Jun 19
    Scope of works involves the supply and installation of insulated cool room panelling and doors.

    Please refer to the attached PDF document for a detailed scope of works.

    Respondents are advised to allow a minimum of 30 minutes to complete this EOI.
    Site Supervisor16 May 1930 Jun 1930 Jun 19
    Scope of works involves the provision of site supervision services to ensure all work supplied by contractors meets engineering specifications and BCA requirements.

    Please refer to the attached PDF document for a detailed scope of works.

    Respondents are advised to allow a minimum of 30 minutes to complete this EOI.
    Structural Steel16 May 1930 Jun 1930 Jun 19
    Scope of works involves the supply and/or installation of steel frames, support structures and roof sheeting.

    Please refer to the attached PDF document for a detailed scope of works.

    Respondents are advised to allow a minimum of 30 minutes to complete this EOI.
    STATUS   5. PLANT AND VILLAGE CONSTRUCTION    ▲ CONTRACT OPENS FULL
    SCOPE
    CLOSES
    PARTIAL
    SCOPE
    CLOSES
    DOCS FULL
    SCOPE
    EOI
    PARTIAL
    SCOPE
    EOI
    Drainage Plumbing Hydraulics and Fire Services16 May 1930 Jun 1930 Jun 19
    Scope of works involves the supply, lay and fit of all drainage and plumbing, fire emergency delivery and hose reel systems.

    Please refer to the attached PDF document for a detailed scope of works.

    Respondents are advised to allow a minimum of 30 minutes to complete this EOI.
    STATUS   6. PLANT FIT-OUT    ▲ CONTRACT OPENS FULL
    SCOPE
    CLOSES
    PARTIAL
    SCOPE
    CLOSES
    DOCS FULL
    SCOPE
    EOI
    PARTIAL
    SCOPE
    EOI
    Boiler Heat Exchangers Mixing Tank and Pumps16 May 1930 Jun 1930 Jun 19
    Scope of works involves the supply and installation of plant for onsite water heating and delivery throughout the facility.

    Please refer to the attached PDF document for a detailed scope of works.

    Respondents are advised to allow a minimum of 30 minutes to complete this EOI.
    Refrigeration and Mechanical Ventilation16 May 1930 Jun 1930 Jun 19
    Scope of works involves the supply and installation of refrigeration and ventilation equipment throughout the facility.

    Please refer to the attached PDF document for a detailed scope of works.

    Respondents are advised to allow a minimum of 30 minutes to complete this EOI.
    STATUS   7. ANCILLARY BUILDING WORKS    ▲ CONTRACT OPENS FULL
    SCOPE
    CLOSES
    PARTIAL
    SCOPE
    CLOSES
    DOCS FULL
    SCOPE
    EOI
    PARTIAL
    SCOPE
    EOI
    Ancillary Sheds16 May 1930 Jun 1930 Jun 19
    Scope of works involves the pad preparation, concrete lay and shed structure for a dry store and workshop.

    Please refer to the attached PDF document for a detailed scope of works.

    Respondents are advised to allow a minimum of 30 minutes to complete this EOI.
    Boundary Fences and Gates16 May 1930 Jun 1930 Jun 19
    Scope of works involves the supply and installation of fencing and gates around the site perimeter to ensure safety and security.

    Please refer to the attached PDF document for a detailed scope of works.

    Respondents are advised to allow a minimum of 30 minutes to complete this EOI.
    Cattle Yards and Race (Covered and Concreted)16 May 1930 Jun 1930 Jun 19
    Scope of works involves the pad preparation, concrete lay, roof structure, cattle rails and gates.

    Please refer to the attached PDF document for a detailed scope of works.

    Respondents are advised to allow a minimum of 30 minutes to complete this EOI.
    Waste Water Screening16 May 1930 Jun 1930 Jun 19
    Scope of works involves the supply and installation of waste water screening and treatment equipment.

    Please refer to the attached PDF document for a detailed scope of works.

    Respondents are advised to allow a minimum of 30 minutes to complete this EOI.
    STATUS   8. PLANT HIRE    ▲ CONTRACT OPENS FULL
    SCOPE
    CLOSES
    PARTIAL
    SCOPE
    CLOSES
    DOCS FULL
    SCOPE
    EOI
    PARTIAL
    SCOPE
    EOI
    Plant Hire - Crane and 4 Scissor Lift16 May 1930 Jun 1930 Jun 19
    Scope of works involves the supply (wet hire) of crane and 4 scissor lifts with operators for the applicable construction period.

    Please refer to the attached PDF document for a detailed scope of works.

    Respondents are advised to allow a minimum of 30 minutes to complete this EOI.
    STATUS   9. OTHER    ▲ CONTRACT OPENS FULL
    SCOPE
    CLOSES
    PARTIAL
    SCOPE
    CLOSES
    DOCS FULL
    SCOPE
    EOI
    PARTIAL
    SCOPE
    EOI
    Signature Onfarm - Any Opportunities16 May 1930 Jun 19 
    Express interest for any opportunities that may arise for this project (outside of those with scopes of work).

    Please refer to the attached PDF document for a detailed scope of works.

    Respondents are advised to allow a minimum of 30 minutes to complete this EOI.