Jansz-Io Compression



Contact Details


  Linus O'Brien
  +61 8 9365 7556
 CONTACT EMAIL

  Locations: WA Australia (Offshore)
  Project Status: Phase 3 (Front End Engineering and Design)
  Project Owner Chevron Australia Pty Ltd

Project Details


Opportunities listed below are for Chevron Australia Pty Ltd packages specifically for Janz-Io Compression. Australia-wide contracts utilised for Jansz-Io Compression will be listed on the Chevron Australia Operations page. 


Project Description

The Chevron Australia operated Gorgon Project is one of the world's largest natural gas projects and the largest single resource development in Australia's history. The Jansz-Io Compression (J-IC) Project objective is to unlock low pressure reserves from the Jansz-Io reservoir and maintain plateau production rates to the Gorgon Project facilities on Barrow Island (BWI). The J-IC Project is therefore an upgrade to an existing facility.

 

The development will comprise of two subsea compression stations connected via a manifold structure to the Jansz-Io Midline Pipeline Termination Structure and the installation of the following supporting infrastructure:

·         New power generation capacity (as required) and cross-island High Voltage (HV) power cables

          on BWI;

 

·         Offshore (subsea) HV cables; and

 

·         Field Control Station (FCS), an offshore normally unattended installation semi-submersible

          electrical and controls distribution platform.


For more details of the project visit Chevron website: https://australia.chevron.com


The Project is Operated by Chevron Australia Pty Ltd (Operator) on behalf of the Gorgon Joint Venturers and the Jansz-Io Unit Joint Ventures.

 

1) the Gorgon Joint Venturers being: Chevron Australia Pty Ltd; Chevron (TAPL) Pty Ltd; Shell Australia Pty Ltd; Mobil Australia Resources Company Pty Ltd; Osaka Gas Gorgon Pty Ltd; Tokyo Gas Gorgon Pty Ltd; and JERA Gorgon Pty Ltd; and

2) the Jansz-Io Unit Joint Ventures being the same parties as the above.

 

Project Location

 The Jansz-Io gas fields are situated approximately 190 kilometres offshore and Barrow Island (BWI) approximately 70 kilometres off the north-west coast of Western Australia.

 

Further information on Accessing Opportunities with Chevron Australia on Jansz-Io Packages can be found under Project Documents below

SHOW LESS

Work Packages


To submit an expression of interest, select the icon next to the work package scope you are interested in.
Note: The closing date/s for expressions of interest shown below are subject to change.

OPEN LISTINGS    AWARDED    CLOSED LISTINGS    OTHER
OPEN FOR EOI    INCOMPLETE EOI    EOI COMPLETED
STATUS   MISCELLANEOUS    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
Module Parking Structure re Subsea Compression Station5 Dec 198 Jan 208 Jan 21
Please refer to SOW for further details pertaining to this package.
6.6kV Packaged substation26 Jul 1922 Aug 1922 Aug 20
Please refer to the scope of works document for details of the packages
Hydraulic Power Unit28 Jul 1929 Aug 1929 Aug 20
Please refer to scope of works document for details of the package
Spools Piperacks and Structural Steel28 Jul 1929 Aug 1929 Aug 20
Please refer to the scope of works document for details of the package
Completions Pre-commissioning and Commissioning28 Jul 1930 Nov 195 Sep 20
Please refer to the scope of works document for details of the package
Electrical Buildings28 Jul 195 Sep 195 Sep 20
Please refer to the scope of works document for details of the package
Deck Integrated Fire Fighting System28 Jul 1912 Sep 1912 Sep 20
Please refer to scope of works document for details of the package
Essential Diesel Generator28 Jul 1912 Sep 1912 Sep 20
Please refer to the scope of works document for details of the package
Barrow Island (BWI) Cross Island Cable Trenching and Installation (EOI-02)2 May 1916 May 1916 Sep 20
please refer to scope of works document for details of the package
HVAC28 Jul 1919 Sep 1919 Sep 20
Please refer to the scope of works document for details of the package
Telecom Equipment28 Jul 1919 Sep 1919 Sep 20
Please refer to the scope of works document for details of the package
Emergency Diesel Generator26 Jul 1922 Aug 1921 Sep 20
Please refer to the scope of work document for details of the package
Subsea Compression Manifold Station (SCMS) and Seabed Tie-in Spools26 Sep 1924 Oct 1924 Oct 20
Please refer to the scope of works document for details of the package
Subsea Compression Station Foundations26 Sep 1924 Oct 1924 Oct 20
Please refer to the scope of works document for details of the package
Rock Supply - Secondary Stabilisation26 Sep 1931 Oct 1931 Oct 20
Please refer to the scope of works document for details of the package
Subsea Concrete Mattresses26 Sep 1931 Oct 1931 Oct 20
Please refer to the scope of works document for details of the package
High Voltage (HV) Power Cable Subsea Repair Clamp26 Sep 197 Nov 197 Nov 20
Please refer to the scope of works document foe details of the package
Subsea Spool Insulation Retrofit26 Sep 197 Nov 197 Nov 20
Please refer to the scope of works document for details of the package
Barrow Island (BWI) Horizontal Directional Drilling (HDD) Shore Crossing (EOI-01)2 May 1916 May 1916 Sep 21
Please refer to the scope of works document for details of the package