Iron Bridge Magnetite Project

Project owner: IB Operations Pty Ltd, as agent for Iron Bridge Joint Venture between FMG Magnetite Pty Ltd and Formosa Steel IB Pty Ltd


Project Details:

The Iron Bridge Magnetite Project (Project) is for the development of a new magnetite mine (including processing and transport facilities) and associated infrastructure at the Iron Bridge Magnetite Project site to deliver 22 million tonnes per annum (mtpa) of high grade 67% Fe, magnetite concentrate product. The Iron Bridge site comprises the world class North Star and Glacier Valley magnetite ore bodies, located 145km south of Port Hedland. 


First production is expected by December 2022, with ramp up to full production run rate in 12 to 18 months.


IB Operations is seeking expressions of interest from suitably qualified contractors and suppliers for Project tendering opportunities on the ICN Gateway.


Scope Overview:

The Project scope will require the establishment of new facilities, including:

  • mine
  • ore processing facility
  • slurry and return water pipeline
  • raw water pipeline
  • port infrastructure
  • non-process infrastructure, such as airstrip, village extension, telecommunications networks, electricity, water, sewage, and wastewater facilities. 


The Iron Bridge Project will be operated by IB Operations Pty Ltd, as agent for the Iron Bridge Joint Venture between FMG Magnetite Pty Ltd and Formosa Steel IB Pty Ltd.  IB Operations Pty Ltd is an Australian private company, which is owned by FMG Magnetite Pty Ltd and Formosa Steel IB Pty Ltd, each a participant in the unincorporated Iron Bridge Joint Venture.


Local and Indigenous participation:


In line with Fortescue’s commitment to supporting local Western Australian communities, requirements relating to the engagement of local and Indigenous vendors will be included in the selection criteria for the Iron Bridge Magnetite Project tendering opportunities.

Share this project on:

FB Twitter LinkedIn

Project at a glance


WA Australia (Onshore)
Project Execution Phase
IB OPERATIONS PTY LTD

Contact Details


Georgie McInerney
Supply Chain Consultant
+61 8 9365 7491

Work Package
Documents
Full Scope EOI
Partial Scope EOI
Status
Accordian collapse

Operations

Full Scope EOI

Create EOI
Closes: 
29 Nov 2021

Partial Scope EOI

Create EOI
Closes: 
29 Nov 2021
  Open

Full Scope EOI

Create EOI
Closes: 
29 Nov 2021

Partial Scope EOI

Create EOI
Closes: 
29 Nov 2021
  Open

Full Scope EOI

Create EOI
Closes: 
30 Nov 2021

Partial Scope EOI

Create EOI
Closes: 
30 Nov 2021
  Open

Full Scope EOI

Closed: 
16 Aug 2019

Partial Scope EOI

Closed: 
16 Aug 2019
  Awarded
AccordianPlus 662NSP1001 Mine Fleet

Full Scope EOI

Closed: 
26 Apr 2019

Partial Scope EOI

Closed: 
26 Apr 2019
  Closed

Full Scope EOI

Closed: 
10 Jan 2020

Partial Scope EOI

Closed: 
10 Jan 2020
  Closed

Full Scope EOI

Closed: 
10 Jan 2020

Partial Scope EOI

Closed: 
10 Jan 2020
  Closed

Full Scope EOI

Closed: 
27 Feb 2020

Partial Scope EOI

Closed: 
27 Feb 2020
  Closed

Full Scope EOI

Closed: 
04 Mar 2020

Partial Scope EOI

Closed: 
04 Mar 2020
  Closed

Full Scope EOI

Closed: 
09 Mar 2020

Partial Scope EOI

Closed: 
09 Mar 2020
  Closed

Full Scope EOI

Closed: 
26 Mar 2020

Partial Scope EOI

Closed: 
26 Mar 2020
  Closed

Full Scope EOI

Closed: 
13 Oct 2020

Partial Scope EOI

Closed: 
13 Oct 2020
  Closed
AccordianPlus NSC0034 Lubricants

Full Scope EOI

Closed: 
06 Nov 2020

Partial Scope EOI

Closed: 
06 Nov 2020
  Closed

Full Scope EOI

Closed: 
09 Dec 2020

Partial Scope EOI

Closed: 
09 Dec 2020
  Closed

Full Scope EOI

Closed: 
10 Dec 2020

Partial Scope EOI

Closed: 
10 Dec 2020
  Closed

Full Scope EOI

Closed: 
15 Dec 2020

Partial Scope EOI

Closed: 
15 Dec 2020
  Closed

Full Scope EOI

Closed: 
16 Dec 2020

Partial Scope EOI

Closed: 
16 Dec 2020
  Closed

Full Scope EOI

Closed: 
17 Dec 2020

Partial Scope EOI

Closed: 
17 Dec 2020
  Closed

Full Scope EOI

Closed: 
24 Dec 2020

Partial Scope EOI

Closed: 
24 Dec 2020
  Closed

Full Scope EOI

Closed: 
29 Dec 2020

Partial Scope EOI

Closed: 
29 Dec 2020
  Closed

Full Scope EOI

Closed: 
04 Jan 2021

Partial Scope EOI

Closed: 
04 Jan 2021
  Closed

Full Scope EOI

Closed: 
12 Jan 2021

Partial Scope EOI

Closed: 
12 Jan 2021
  Closed

Full Scope EOI

Closed: 
14 Jan 2021

Partial Scope EOI

Closed: 
14 Jan 2021
  Closed

Full Scope EOI

Closed: 
01 Feb 2021

Partial Scope EOI

Closed: 
01 Feb 2021
  Closed

Full Scope EOI

Closed: 
05 Feb 2021

Partial Scope EOI

Closed: 
05 Feb 2021
  Closed

Full Scope EOI

Closed: 
06 Feb 2021

Partial Scope EOI

Closed: 
06 Feb 2021
  Closed

Full Scope EOI

Closed: 
08 Feb 2021

Partial Scope EOI

Closed: 
08 Feb 2021
  Closed

Full Scope EOI

Closed: 
01 Mar 2021

Partial Scope EOI

Closed: 
01 Mar 2021
  Closed

Full Scope EOI

Closed: 
14 Apr 2021

Partial Scope EOI

Closed: 
14 Apr 2021
  Closed

Full Scope EOI

Closed: 
19 Apr 2021

Partial Scope EOI

Closed: 
19 Apr 2021
  Closed

Full Scope EOI

Closed: 
19 Apr 2021

Partial Scope EOI

Closed: 
19 Apr 2021
  Closed

Full Scope EOI

Closed: 
06 Sep 2021

Partial Scope EOI

Closed: 
06 Sep 2021
  Closed

Full Scope EOI

Closed: 
07 Sep 2021

Partial Scope EOI

Closed: 
07 Sep 2021
  Closed

Full Scope EOI

Closed: 
20 Oct 2021

Partial Scope EOI

Closed: 
20 Oct 2021
  Closed

Full Scope EOI

Closed: 
08 Nov 2021

Partial Scope EOI

Closed: 
08 Nov 2021
  Closed

Full Scope EOI

Closed: 
22 Nov 2021

Partial Scope EOI

Closed: 
22 Nov 2021
  Closed
Accordian collapse

Project Phase

Full Scope EOI

Closed: 
24 Apr 2019

Partial Scope EOI

Closed: 
24 Apr 2019
  Awarded

Full Scope EOI

Closed: 
26 Apr 2019

Partial Scope EOI

Closed: 
26 Apr 2019
  Awarded
AccordianPlus 662NSC1006 Airport

Full Scope EOI

Closed: 
02 May 2019

Partial Scope EOI

Closed: 
02 May 2019
  Awarded

Full Scope EOI

Closed: 
02 May 2019

Partial Scope EOI

Closed: 
02 May 2019
  Awarded

Full Scope EOI

Closed: 
09 May 2019

Partial Scope EOI

Closed: 
09 May 2019
  Awarded

Full Scope EOI

Closed: 
17 May 2019

Partial Scope EOI

Closed: 
17 May 2019
  Awarded

Full Scope EOI

Closed: 
22 May 2019

Partial Scope EOI

Closed: 
22 May 2019
  Awarded

Full Scope EOI

Closed: 
22 May 2019

Partial Scope EOI

Closed: 
22 May 2019
  Awarded

Full Scope EOI

Closed: 
22 May 2019

Partial Scope EOI

Closed: 
22 May 2019
  Awarded

Full Scope EOI

Closed: 
22 May 2019

Partial Scope EOI

Closed: 
22 May 2019
  Awarded

Full Scope EOI

Closed: 
22 May 2019

Partial Scope EOI

Closed: 
22 May 2019
  Awarded

Full Scope EOI

Closed: 
22 May 2019

Partial Scope EOI

Closed: 
22 May 2019
  Awarded

Full Scope EOI

Closed: 
22 May 2019

Partial Scope EOI

Closed: 
22 May 2019
  Awarded

Full Scope EOI

Closed: 
28 May 2019

Partial Scope EOI

Closed: 
28 May 2019
  Awarded
AccordianPlus 662NSP2032 Water Pumps

Full Scope EOI

Closed: 
28 May 2019

Partial Scope EOI

Closed: 
28 May 2019
  Awarded

Full Scope EOI

Closed: 
28 May 2019

Partial Scope EOI

Closed: 
28 May 2019
  Awarded

Full Scope EOI

Closed: 
28 May 2019

Partial Scope EOI

Closed: 
29 May 2019
  Awarded

Full Scope EOI

Closed: 
31 May 2019

Partial Scope EOI

Closed: 
31 May 2019
  Awarded

Full Scope EOI

Closed: 
05 Jun 2019

Partial Scope EOI

Closed: 
05 Jun 2019
  Awarded

Full Scope EOI

Closed: 
05 Jun 2019

Partial Scope EOI

Closed: 
05 Jun 2019
  Awarded

Full Scope EOI

Closed: 
11 Jun 2019

Partial Scope EOI

Closed: 
11 Jun 2019
  Awarded

Full Scope EOI

Closed: 
14 Jun 2019

Partial Scope EOI

Closed: 
14 Jun 2019
  Awarded

Full Scope EOI

Closed: 
17 Jun 2019

Partial Scope EOI

Closed: 
17 Jun 2019
  Awarded

Full Scope EOI

Closed: 
19 Jun 2019

Partial Scope EOI

Closed: 
19 Jun 2019
  Awarded

Full Scope EOI

Closed: 
19 Jun 2019

Partial Scope EOI

Closed: 
19 Jun 2019
  Awarded

Full Scope EOI

Closed: 
19 Jun 2019

Partial Scope EOI

Closed: 
19 Jun 2019
  Awarded

Full Scope EOI

Closed: 
28 Jun 2019

Partial Scope EOI

Closed: 
28 Jun 2019
  Awarded

Full Scope EOI

Closed: 
01 Jul 2019

Partial Scope EOI

Closed: 
01 Jul 2019
  Awarded

Full Scope EOI

Closed: 
15 Jul 2019

Partial Scope EOI

Closed: 
15 Jul 2019
  Awarded

Full Scope EOI

Closed: 
19 Jul 2019

Partial Scope EOI

Closed: 
19 Jul 2019
  Awarded

Full Scope EOI

Closed: 
19 Jul 2019

Partial Scope EOI

Closed: 
19 Jul 2019
  Awarded

Full Scope EOI

Closed: 
19 Jul 2019

Partial Scope EOI

Closed: 
19 Jul 2019
  Awarded

Full Scope EOI

Closed: 
25 Jul 2019

Partial Scope EOI

Closed: 
25 Jul 2019
  Awarded

Full Scope EOI

Closed: 
25 Jul 2019

Partial Scope EOI

Closed: 
25 Jul 2019
  Awarded

Full Scope EOI

Closed: 
26 Jul 2019

Partial Scope EOI

Closed: 
26 Jul 2019
  Awarded

Full Scope EOI

Closed: 
08 Aug 2019

Partial Scope EOI

Closed: 
08 Aug 2019
  Awarded

Full Scope EOI

Closed: 
08 Aug 2019

Partial Scope EOI

Closed: 
08 Aug 2019
  Awarded

Full Scope EOI

Closed: 
08 Aug 2019

Partial Scope EOI

Closed: 
08 Aug 2019
  Awarded

Full Scope EOI

Closed: 
12 Aug 2019

Partial Scope EOI

Closed: 
12 Aug 2019
  Awarded

Full Scope EOI

Closed: 
12 Aug 2019

Partial Scope EOI

Closed: 
12 Aug 2019
  Awarded
AccordianPlus 662NSP0018 Dart Valves

Full Scope EOI

Closed: 
19 Aug 2019

Partial Scope EOI

Closed: 
19 Aug 2019
  Awarded
AccordianPlus 662NSP2034 Agitators

Full Scope EOI

Closed: 
21 Aug 2019

Partial Scope EOI

Closed: 
21 Aug 2019
  Awarded

Full Scope EOI

Closed: 
22 Aug 2019

Partial Scope EOI

Closed: 
22 Aug 2019
  Awarded

Full Scope EOI

Closed: 
23 Aug 2019

Partial Scope EOI

Closed: 
23 Aug 2019
  Awarded

Full Scope EOI

Closed: 
26 Aug 2019

Partial Scope EOI

Closed: 
26 Aug 2019
  Awarded

Full Scope EOI

Closed: 
27 Aug 2019

Partial Scope EOI

Closed: 
27 Aug 2019
  Awarded

Full Scope EOI

Closed: 
27 Aug 2019

Partial Scope EOI

Closed: 
27 Aug 2019
  Awarded
AccordianPlus 662NSP0001 Water Tanks

Full Scope EOI

Closed: 
28 Aug 2019

Partial Scope EOI

Closed: 
28 Aug 2019
  Awarded

Full Scope EOI

Closed: 
28 Aug 2019

Partial Scope EOI

Closed: 
28 Aug 2019
  Awarded

Full Scope EOI

Closed: 
29 Aug 2019

Partial Scope EOI

Closed: 
29 Aug 2019
  Awarded
AccordianPlus 662NSP0040 Steel Tanks

Full Scope EOI

Closed: 
30 Aug 2019

Partial Scope EOI

Closed: 
30 Aug 2019
  Awarded
AccordianPlus 662NSC5011 Car Hire

Full Scope EOI

Closed: 
03 Sep 2019

Partial Scope EOI

Closed: 
03 Sep 2019
  Awarded
AccordianPlus 662NSP2052 Dam Pumps

Full Scope EOI

Closed: 
03 Sep 2019

Partial Scope EOI

Closed: 
03 Sep 2019
  Awarded

Full Scope EOI

Closed: 
09 Sep 2019

Partial Scope EOI

Closed: 
09 Sep 2019
  Awarded

Full Scope EOI

Closed: 
09 Sep 2019

Partial Scope EOI

Closed: 
09 Sep 2019
  Awarded

Full Scope EOI

Closed: 
10 Sep 2019

Partial Scope EOI

Closed: 
10 Sep 2019
  Awarded

Full Scope EOI

Closed: 
11 Sep 2019

Partial Scope EOI

Closed: 
11 Sep 2019
  Awarded

Full Scope EOI

Closed: 
17 Sep 2019

Partial Scope EOI

Closed: 
17 Sep 2019
  Awarded

Full Scope EOI

Closed: 
17 Sep 2019

Partial Scope EOI

Closed: 
17 Sep 2019
  Awarded

Full Scope EOI

Closed: 
17 Sep 2019

Partial Scope EOI

Closed: 
17 Sep 2019
  Awarded

Full Scope EOI

Closed: 
17 Sep 2019

Partial Scope EOI

Closed: 
17 Sep 2019
  Awarded

Full Scope EOI

Closed: 
18 Sep 2019

Partial Scope EOI

Closed: 
18 Sep 2019
  Awarded

Full Scope EOI

Closed: 
18 Sep 2019

Partial Scope EOI

Closed: 
18 Sep 2019
  Awarded

Full Scope EOI

Closed: 
20 Sep 2019

Partial Scope EOI

Closed: 
20 Sep 2019
  Awarded

Full Scope EOI

Closed: 
20 Sep 2019

Partial Scope EOI

Closed: 
20 Sep 2019
  Awarded

Full Scope EOI

Closed: 
23 Sep 2019

Partial Scope EOI

Closed: 
23 Sep 2019
  Awarded

Full Scope EOI

Closed: 
24 Sep 2019

Partial Scope EOI

Closed: 
24 Sep 2019
  Awarded

Full Scope EOI

Closed: 
25 Sep 2019

Partial Scope EOI

Closed: 
25 Sep 2019
  Awarded

Full Scope EOI

Closed: 
04 Oct 2019

Partial Scope EOI

Closed: 
04 Oct 2019
  Awarded

Full Scope EOI

Closed: 
04 Oct 2019

Partial Scope EOI

Closed: 
04 Oct 2019
  Awarded

Full Scope EOI

Closed: 
04 Oct 2019

Partial Scope EOI

Closed: 
04 Oct 2019
  Awarded

Full Scope EOI

Closed: 
04 Oct 2019

Partial Scope EOI

Closed: 
04 Oct 2019
  Awarded
AccordianPlus 662NSP2023 Analysers

Full Scope EOI

Closed: 
04 Oct 2019

Partial Scope EOI

Closed: 
04 Oct 2019
  Awarded

Full Scope EOI

Closed: 
04 Oct 2019

Partial Scope EOI

Closed: 
04 Oct 2019
  Awarded

Full Scope EOI

Closed: 
08 Oct 2019

Partial Scope EOI

Closed: 
08 Oct 2019
  Awarded

Full Scope EOI

Closed: 
14 Oct 2019

Partial Scope EOI

Closed: 
14 Oct 2019
  Awarded

Full Scope EOI

Closed: 
15 Oct 2019

Partial Scope EOI

Closed: 
15 Oct 2019
  Awarded

Full Scope EOI

Closed: 
15 Oct 2019

Partial Scope EOI

Closed: 
15 Oct 2019
  Awarded

Full Scope EOI

Closed: 
28 Oct 2019

Partial Scope EOI

Closed: 
28 Oct 2019
  Awarded

Full Scope EOI

Closed: 
28 Oct 2019

Partial Scope EOI

Closed: 
28 Oct 2019
  Awarded

Full Scope EOI

Closed: 
28 Oct 2019

Partial Scope EOI

Closed: 
28 Oct 2019
  Awarded

Full Scope EOI

Closed: 
29 Oct 2019

Partial Scope EOI

Closed: 
29 Oct 2019
  Awarded

Full Scope EOI

Closed: 
07 Nov 2019

Partial Scope EOI

Closed: 
07 Nov 2019
  Awarded

Full Scope EOI

Closed: 
08 Nov 2019

Partial Scope EOI

Closed: 
08 Nov 2019
  Awarded

Full Scope EOI

Closed: 
28 Nov 2019

Partial Scope EOI

Closed: 
28 Nov 2019
  Awarded
AccordianPlus 662NSP0011 Cable

Full Scope EOI

Closed: 
09 Dec 2019

Partial Scope EOI

Closed: 
09 Dec 2019
  Awarded

Full Scope EOI

Closed: 
20 Dec 2019

Partial Scope EOI

Closed: 
20 Dec 2019
  Awarded

Full Scope EOI

Closed: 
20 Dec 2019

Partial Scope EOI

Closed: 
20 Dec 2019
  Awarded

Full Scope EOI

Closed: 
31 Jan 2020

Partial Scope EOI

Closed: 
31 Jan 2020
  Awarded

Full Scope EOI

Closed: 
31 Jan 2020

Partial Scope EOI

Closed: 
31 Jan 2020
  Awarded

Full Scope EOI

Closed: 
20 Feb 2020

Partial Scope EOI

Closed: 
20 Feb 2020
  Awarded

Full Scope EOI

Closed: 
20 Feb 2020

Partial Scope EOI

Closed: 
20 Feb 2020
  Awarded
AccordianPlus 662NSP0036 CCTV System

Full Scope EOI

Closed: 
21 Feb 2020

Partial Scope EOI

Closed: 
21 Feb 2020
  Awarded

Full Scope EOI

Closed: 
26 Feb 2020

Partial Scope EOI

Closed: 
26 Feb 2020
  Awarded

Full Scope EOI

Closed: 
14 Apr 2020

Partial Scope EOI

Closed: 
14 Apr 2020
  Awarded

Full Scope EOI

Closed: 
22 Apr 2020

Partial Scope EOI

Closed: 
22 Apr 2020
  Awarded

Full Scope EOI

Closed: 
31 May 2020

Partial Scope EOI

Closed: 
31 May 2020
  Awarded

Full Scope EOI

Closed: 
01 Jul 2020

Partial Scope EOI

Closed: 
01 Jul 2020
  Awarded

Full Scope EOI

Closed: 
17 Jul 2020

Partial Scope EOI

Closed: 
17 Jul 2020
  Awarded

Full Scope EOI

Closed: 
09 Sep 2020

Partial Scope EOI

Closed: 
09 Sep 2020
  Awarded

Full Scope EOI

Closed: 
14 Oct 2020

Partial Scope EOI

Closed: 
14 Oct 2020
  Awarded

Full Scope EOI

Closed: 
28 Aug 2019

Partial Scope EOI

Closed: 
28 Aug 2019
  Closed

Full Scope EOI

Closed: 
29 Aug 2019

Partial Scope EOI

Closed: 
29 Aug 2019
  Closed

Full Scope EOI

Closed: 
06 Sep 2019

Partial Scope EOI

Closed: 
06 Sep 2019
  Closed

Full Scope EOI

Closed: 
18 Sep 2019

Partial Scope EOI

Closed: 
18 Sep 2019
  Closed
AccordianPlus 662NSP0020 HV Motors

Full Scope EOI

Closed: 
18 Sep 2019

Partial Scope EOI

Closed: 
18 Sep 2019
  Closed

Full Scope EOI

Closed: 
25 Sep 2019

Partial Scope EOI

Closed: 
25 Sep 2019
  Closed

Full Scope EOI

Closed: 
14 Nov 2019

Partial Scope EOI

Closed: 
14 Nov 2019
  Closed

Full Scope EOI

Closed: 
28 Nov 2019

Partial Scope EOI

Closed: 
28 Nov 2019
  Closed

Full Scope EOI

Closed: 
29 Nov 2019

Partial Scope EOI

Closed: 
29 Nov 2019
  Closed

Full Scope EOI

Closed: 
29 Nov 2019

Partial Scope EOI

Closed: 
29 Nov 2019
  Closed

Full Scope EOI

Closed: 
12 Feb 2020

Partial Scope EOI

Closed: 
12 Feb 2020
  Closed

Full Scope EOI

Closed: 
12 Feb 2020

Partial Scope EOI

Closed: 
12 Feb 2020
  Closed

Full Scope EOI

Closed: 
21 Feb 2020

Partial Scope EOI

Closed: 
21 Feb 2020
  Closed

Full Scope EOI

Closed: 
25 Feb 2020

Partial Scope EOI

Closed: 
25 Feb 2020
  Closed

Full Scope EOI

Closed: 
26 Feb 2020

Partial Scope EOI

Closed: 
26 Feb 2020
  Closed

Full Scope EOI

Closed: 
14 Apr 2020

Partial Scope EOI

Closed: 
14 Apr 2020
  Closed

Full Scope EOI

Closed: 
14 Apr 2020

Partial Scope EOI

Closed: 
14 Apr 2020
  Closed

Full Scope EOI

Closed: 
06 May 2020

Partial Scope EOI

Closed: 
06 May 2020
  Closed

Full Scope EOI

Closed: 
09 Oct 2020

Partial Scope EOI

Closed: 
09 Oct 2020
  Closed

Full Scope EOI

Closed: 
14 Oct 2020

Partial Scope EOI

Closed: 
14 Oct 2020
  Closed

Full Scope EOI

Closed: 
02 Nov 2020

Partial Scope EOI

Closed: 
02 Nov 2020
  Closed

Full Scope EOI

Closed: 
13 Nov 2020

Partial Scope EOI

Closed: 
13 Nov 2020
  Closed

Full Scope EOI

Closed: 
18 Jan 2021

Partial Scope EOI

Closed: 
18 Jan 2021
  Closed

Full Scope EOI

Closed: 
02 Apr 2021

Partial Scope EOI

Closed: 
02 Apr 2021
  Closed

Full Scope EOI

Closed: 
02 Apr 2021

Partial Scope EOI

Closed: 
02 Apr 2021
  Closed

Full Scope EOI

Closed: 
02 Apr 2021

Partial Scope EOI

Closed: 
02 Apr 2021
  Closed

Full Scope EOI

Closed: 
02 Apr 2021

Partial Scope EOI

Closed: 
02 Apr 2021
  Closed

Full Scope EOI

Closed: 
02 Apr 2021

Partial Scope EOI

Closed: 
02 Apr 2021
  Closed

Full Scope EOI

Closed: 
02 Apr 2021

Partial Scope EOI

Closed: 
02 Apr 2021
  Closed

Full Scope EOI

Closed: 
02 Apr 2021

Partial Scope EOI

Closed: 
02 Apr 2021
  Closed

Full Scope EOI

Closed: 
02 Apr 2021

Partial Scope EOI

Closed: 
02 Apr 2021
  Closed

Full Scope EOI

Closed: 
02 Apr 2021

Partial Scope EOI

Closed: 
02 Apr 2021
  Closed

Full Scope EOI

Closed: 
12 May 2021

Partial Scope EOI

Closed: 
12 May 2021
  Closed

Full Scope EOI

Closed: 
04 Oct 2021

Partial Scope EOI

Closed: 
04 Oct 2021
  Closed
Note: The closing date/s for expressions of interest are subject to change.
PROJECT
WA AUSTRALIA

FMG Solomon, a subsidiary of Fortescue Metals Group, will develop the Eliwana Project, following board approval in May 2018.


View Project
PROJECT
WA AUSTRALIA

Fortescue Metals Group is a global leader in the iron ore industry, recognised for its unique culture, innovation and industry-leading development of world class infrastructure and mining assets in the Pilbara, Western Australia.

View Project
PROJECT
WA AUSTRALIA

Pilbara Transmission Project

View Project
PROJECT
WA AUSTRALIA

The Pilbara Generation Project (Project) will enhance Fortescue’s existing power generation capacity through the inclusion of 150MW of gas fired reciprocating engine-based power generation, together with 150MW of solar photovoltaic (PV) generation and 50MW of battery storage and will be constructed, owned and operated by Fortescue through its subsidiary Pilbara Energy (Generation) Pty Ltd. 

View Project
PROJECT
WA AUSTRALIA

Fortescue Metals Group Ltd (Fortescue) subsidiary FMG Magnetite Pty Ltd and joint venture partner Formosa Steel IB Pty Ltd (Formosa) have approved the development of Stage 2 of the Iron Bridge Magnetite Project (the Project).

View Project