TechnipFMC GS2 Subsea Installation



Contact Details


Carla Chilvers
Local Content and AIP Adviser
+61 8 9365 7543
 CONTACT EMAIL

  Locations: WA Australia (Offshore)
  Project Status: Execution
  Project Owner Technip Oceania Pty Ltd

Project Details



TechnipFMC has been awarded the Subsea Installation Contract by Chevron Australia for Gorgon Stage 2.

 

The Project supplements the existing Gorgon and Jansz-IO gas field development with the following additional wells and supporting infrastructure:

 

  1. Three (3) additional infill wells to the existing Gorgon M1 Manifold.
  2. Four (4) wells tied back to a new Gorgon M4 Manifold which in turn is connected to the existing Gorgon gas gathering system via a PTS and 9 km 24-inch M4 Production Flowline (CRA Clad), 8-inch Gorgon M4 MEG Pipeline and 6-inch Gorgon M4 Utility Pipeline.
  3. Four (4) wells tied back to a new Jansz Drill Centre 3 (DC-3) combined Manifold/PTS which in turn is connected to the existing Jansz gas gathering system via a 6.6 km long 18-inch JanszDC-3 Production Flowline (CRA Clad), 6-inch Jansz DC-3 MEG Pipeline and 6-inch Jansz DC-3 Utility Pipeline.
  4. New infield control umbilicals for Gorgon M4, and Jansz DC-3. Installation of all interconnecting flying leads to allow control of the Facility.


The Subsea Installation Work includes the following:

  1. Tie-in of Gorgon M1 production wells
  2. Subsea Tie-back of Gorgon M4 Drill Centre
  3. Subsea Tie-back of Jansz DC-3 Drill Centre

 

The Work includes the following activities:

  • Installation of subsea structures
  • Fabrication of spools, jumpers and well jumpers
  • Installation of spools, jumpers, umbilicals and flying leads
  • Pipeline Systems Pre-commissioning



SHOW LESS

Associated Opportunities


SHOW MORE

Project Documents


TechnipFMC Information

  ▲ CONTRACT
Contact Details.doc
SHOW LESS

Work Packages


There are currently no open work packages for this project.
Note: The closing date/s for expressions of interest shown below are subject to change.

OPEN LISTINGS    AWARDED    CLOSED LISTINGS    OTHER
OPEN FOR EOI    INCOMPLETE EOI    EOI COMPLETED
STATUS   MISCELLANEOUS    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
Offshore Spreader Bars and Seafastening Fabrication 

Full scope has been awarded to:

Contact

Tony Marraffa- Project Manager
tony.marraffa@civmec.com.au
T+61 8 9437 6288
M 0418 949 724

CIVMEC CONSTRUCTION & ENGINEERING PTY LTD

16 Nautical Drive
HENDERSON, WA
Australia 6166
Phone: +61 8 9437 6288
Fax: +61 8 9437 6388
Email: civmec@civmec.com.au
Web: www.civmec.com.au

Fabrication includes all supply of materials and welding of support structures for offshore transport of the subsea spools.
Subsea Rigid Spool Fabrication 

Full scope has been awarded to:

Contact

Tony Marraffa- Project Manager
tony.marraffa@civmec.com.au
T+61 8 9437 6288
M 0418 949 724

CIVMEC CONSTRUCTION & ENGINEERING PTY LTD

16 Nautical Drive
HENDERSON, WA
Australia 6166
Phone: +61 8 9437 6288
Fax: +61 8 9437 6388
Email: civmec@civmec.com.au
Web: www.civmec.com.au

Fabrication of 24 diverless spools and jumpers. All spools utilise SEV's horizontal diverless connection system
Freight Forwarding 

Full scope has been awarded to:

Schenker Australia Pty Ltd

Contact Details:-
Shailesh Sequeira
Business Development Manager - Oil & Gas / Mining, WA.

Schenker Australia Pty Ltd
919 Abernethy Road, High Wycombe, WA 6058, Australia
Phone + 61 8 6188 1941, Fax + 61 8 9454 4344
Mobile + 61 481 004 194

Please refer to scope of works document for details of the package
Subsea Pre-commissioning24 May 201921 Jun 201921 Jun 2019
Please refer to scope of works document for details of the package
Subsea Survey25 Oct 201922 Nov 201922 Nov 2019
See Scope for full details
Concrete Mattresses and Grout Bags17 Jan 202020 Mar 202030 Mar 2020
See full scope for details
Tugs Barges Assist Tugs and Supply Vessels17 Jan 202020 Mar 202030 Mar 2020
See Scope for Details