Osborne Naval Shipbuilding Precinct (Future Subs Program) Infrastructure Development



Contact Details


Jeff Camburn, ICN SA
+61 8 8303 2054
 CONTACT EMAIL

Eddie Ivar
Supply Consultant, ICN SA
+61 8 8226 3011
 CONTACT EMAIL

  Locations: SA Australia
  Project Value: TBC
  Project Status: Design Phase
  Project Owner Laing O'Rourke Australia Construction Pty Ltd

Project Details


The Osborne Naval Shipbuilding Precinct (Future Submarine Program) (ONSP(FSP)) Infrastructure Development will provide the necessary build, test, and integration facilities (BTIFI) to design, produce and accept into service a fleet of future submarines (FSM). The project is part of the Commonwealth Government's Naval Shipbuilding Plan announced in May 2017 which sets out the strategic approach to building a long-term, sustainable naval shipbuilding and ship sustainment capability in Australia.


Laing O’Rourke has been awarded the Managing Contractor role for this large scale project and is now requesting Registrations of Interest (ROI) from trade subcontractors interested in participating in this exciting South Australian Project. Delivery Phase works are scheduled to commence in Q1 2019 and be completed in 2026.


The proposed scope of works includes the following:


New building works include:

•    Production Workshops

•    Platform Land Based Test Facility (PLBTF)

•    Combat System Physical Integration Facility (CSPIF)

•    Paint workshops

•    Raft workshop

•    Warehousing

•    Wharf support buildings

•    Shipyard maintenance and utility building

•    Canteen and amenities

•    FSP building

•    On-grade car park and pedestrian bridge over rail


Civil and marine infrastructure includes:

•    Piling, bulk earthworks, roads, aprons and hardstands

•    Wharf upgrades/extensions

•    Power, water, electrical, security and communications infrastructure.


Building refurbishment includes:

Refurbishment of existing buildings


PROJECT UPDATE

Following the development of the Phase 1 design, the Osborne North Development Project is continuing to progress well towards construction.  In August 2019 will be starting our site establishment activities and by the end of 2019 we will have commenced our first permanent works.


Within the next two months we will be issuing expressions of interest for the Phase 1 Delivery Packages, which will commence on site in Q1 2020.  Please continue to review the ICN portal for sight of these opportunities.


Procurement of the Phase 2 scope is also in our sights, and we are focusing upon the services that we require during the planning (design) phase for those works, including early supply chain engagement for key trade works where input into the design process is required.  We will provide more detail on Phase 2 requirements in a further Industry Briefing later this year.


We will hold a series of Supply Chain Safety Forums as we progress, to share the Laing O’Rourke safety ethos and behaviours, as well as some of our project objectives with potential supply chain partners on the project.  These Forums will target trades due to be procured and mobilised at that time.  The first will target earthworks, civils and structural trades, and will take place on 29 August 2019. More information will be issued through the ICN Portal in due course.   


We look forward to engaging with you on the Osborne North Future Submarine Project.  If you require any further information please continue to view the ICN portal or contact us on FSPID.Osborne@laingorourke.com.au

SHOW LESS

Associated Opportunities


  • Osborne Naval Shipyard
    •  Osborne Naval Shipbuilding Precinct (Future Subs Program) Infrastructure Development
SHOW MORE

Work Packages


To edit or submit an expression of interest, select the icon next to the package you are interested in.
Note: The closing date/s for expressions of interest shown below are subject to change.

OPEN LISTINGS    AWARDED    CLOSED LISTINGS    OTHER
OPEN    INCOMPLETE    COMPLETE

STANDARD LISTINGS        ▲ CONTRACT
STATUS   01 PHASE 1 EXPRESSION OF INTEREST    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
WP-P1DP-0115 Carpentry16 Sep 202023 Oct 2020 
 
General carpentry works. This also includes internal doors, fire doors, metal clad security doors, installation only of sundry hardware and architectural hardware such as handles, closers, door stops, locks and hinges.
WP-P1DP-0122 Washroom Partitioning Systems13 Oct 202026 Oct 2020 
 
Supply and install of toilet and shower partitioning systems including urinal dividers.
WP-P1D-0057 Mechanical Installations 
  
EOI for the Osborne North Infrastructure project for Mechanical Installations
WP-P1DP-0030 Security Systems 
  
The Security Systems will include for the supply and installation of permanent security systems to multiple buildings. The recipient should be capable of providing the security works from a Type 1A Security Alarm Panel Manufacturer's approved installer
WP-P1DP-0044 Sliding Roof 
  
The project requires an engineering Subcontractor to carry out the detailed design, manufacture, install, test and commissioning of the mechanically operated roof including motors, rails and controls.
WP-P1DP-0046 Roller Shutters Industrial Doors Supply and Installation 
  
The manufacture, supply and installation of 20-25 roller shutter industrial doors of various sizes.
WP-P1DP-0060 Wet and Dry Fire 
  
Wet and dry fire protection systems installation to 3 buildings within Phase 1 of the Project.
WP-P1DP-0097 Plumbing and Hydraulics 
  
Supply and installation of all sanitary plumbing and drainage, metering, potable cold water, potable hot water, rainwater, and natural gas supply for building within Phase 1.
In completing the scope of works, the Contractor shall be responsible for but not limited to:
- All labour
- Design (where required)
- Material
- Transport
- Cranage
- Submissions to authorities prior to commencement of the works
- The supply and fixing of all necessary equipment and components for the complete installation
Phase 1 Overhead Cranes (Including crane rails) and Knuckle Boom Crane 
  

Full scope has been awarded to:

Overhead Crane (Including Rails) Awarded

Eilbeck Cranes

Unit 2, 23-25 Clovelly Ave, ROYAL PARK
SA, Australia 5014
Ph: +61 8 8162 5150
Email: adelaide@eilbeckcranes.com
Web: www.eilbeckcranes.com

The design, manufacture, supply, installation and commissioning of varied overhead and knuckle boom cranes.
WP76 Formwork Reinforcement and Pour 
  

Full scope has been awarded to:

Ballestrin Construction Services Pty Ltd

26 Duncan Road
Gepps Cross, SA
Australia 5094
Phone: +61 8 8359 0899
Email: info@ballestrin.com.au
Web: www.ballestrin.com.au

Expression of Interest for FRP requirement for Phase 1.
WP-P1D-0027 Passenger and Goods Lift 
  

Full scope has been awarded to:

KONE ELEVATORS PTY LTD

205 Euston Road
ALEXANDRIA, NSW
Australia 2015
Phone: +61 2 9577 7000
Fax: +61 2 9577 7100
Web: www.kone.com.au

Design, manufacture, install, test and commissioning of up to 5no. passenger and goods lifts for Phase 1 of the Project.
WP-P1D-0043 Cladding Supply and Install (inc Louvres) 
  

Full scope has been awarded to:

CLADDING & ROOFING CONTRACTORS PTY LTD

10-14 Toogood Avenue
Beverley, SA
Australia 5009
Phone: +61 8 8347 3999
Email: andrew@claddingandroofing.com.au
Web: www.claddingandroofing.com.au

The supply and installation of cladding, roofing and louvres and relevant components for three buildings included within Phase 1 of the ONDP Project.

.
WP-P1D-0045 Precast Concrete Supply and Install 
  

Full scope has been awarded to:

RAMCO PRECAST

20 Waddikee Road
Lonsdale, SA
Australia 5160
Phone: +61 08 8326 8877
Email: paul@tiltupsa.com.au
Web: www.tiltupsa.com.au

Expression of Interest for Precast Concrete Supply and Install requirements for Phase 1 of the build.
WP-P1D-0047 Glazing Supply and Install 
  

Full scope has been awarded to:

ABS FACADE ADELAIDE PTY LTD

47 Byre Avenue
Somerton Park, SA
Australia 5044
Email: nathan.smith@absfacade.com.au
Web: www.absfacade.com.au

Glazing Supply and Install EOI
WP-P1D-0081 HV Switchgear 
  

Full scope has been awarded to:

NILSEN (SA) PTY LTD

100 Regency Road
FERRYDEN PARK, SA
Australia 5010
Phone: +61 08 8440 5300
Fax: +61 08 8347 0347
Email: nilsensa@nilsen.com.au
Web: www.nilsen.com.au

EOI for HV Switchgear for Phase 1 of the Osborne Infrastructure project.
WP-P1DP-0040 Structural Steel 
  

Full scope has been awarded to:

SA STRUCTURAL PTY LTD

40-54 Kaurna Avenue
Edinburgh, SA
Australia 5111
Phone: +61 08 8285 5111
Fax: +61 08 8285 5122
Email: sastructural@sastructural.com.au
Web: www.sastructural.com.au

Expression of Interest for Structural Steel requirements for Phase 1 of the build.
Phase 1 Civil and Infrastructure Package27 Nov 201913 Dec 2019 
  
Works include heavy duty pavements, service roads, permanent car parks, footpaths, installation of external services (various), and hard landscape including bollards, bike racks and similar.

Package Information Brief available by clicking the Full Scope EOI icon.
Phase 1 Site Logistics Package27 Nov 201920 Dec 2019 
  
The scope of this package includes the delivery of onsite logistics services for Phase 1 of the Project.
The scope of services will include the provision of labour and supervision, small tools & plant, and materials to co-ordinate and manage access, materials movement, waste clearance, temporary site services.

Package Information Brief available by clicking the Full Scope EOI icon.
WP-P1D-002 Labour Hire24 Apr 202008 May 2020 
  
The scope of this package includes general construction labour for the project.
An initial award will be made for Phase 1, with an option to extend for Phase 2.
The scope of services will include the provision of labour and supervision, predominantly for
site support and logistics, but skilled tradespersons may also be required from time to time.
WP-P1D-02 Logistics-Electrical Temporary Services18 Feb 202013 Mar 2020 
  
Subcontract for Temporary power supply for Construction Site and distribution of mains
power for trades.
WP-P1DP-0052 Ceilings and Partitions14 Apr 202005 Jun 2020 
  
Ceilings, partitions, dry lining and fit out to 3 no. buildings within Phase 1 of the Project.
WP-P1DP-0053 Access Floors07 Aug 202008 Sep 2020 
  
ASP Extra heavy duty industrial grade anti-static access floor system (Type Icon Data + Vinyl System) - ACS005, ASC006 (or similar).
Other access floor systems subject to design development
WP-P1DP-0056 Electrical21 Feb 202028 Apr 2020 
  
Electrical installation including communication systems, to 3no buildings within Phase 1 of the Project.
WP-P1DP-0062 Tiles Including Water Proofing14 Aug 202009 Oct 2020 
  
Subcontract for various specification porcelain and ceramic wall and floor tiling to wet areas, stairs, landing including waterproofing and associated works.
Other tiling works subject to design development
WP-P1DP-0063 Floor Finishes13 Aug 202009 Oct 2020 
  
Subcontract for various specification carpet tiles, vinyl flooring, tactiles, floor treads and nosings, matwells and mats.
Other floor finishes works subject to design development.
WP-P1DP-0064 Epoxy Flooring01 May 202001 Jul 2020 
  
Supply, installation, and certification of epoxy floor system to 3no. industrial buildings within Phase 1 of the Project.
WP-P1DP-0066 General Metalwork11 Aug 202009 Sep 2020 
  
Various specification ballustrade, access stairs, access ladders, guardrails and access walkways and general metalwork subject to design development.
This invitation relates to supply and installation of general metalwork.
WP-P1DP-0083 Signage (Permanent)08 Sep 202016 Oct 2020 
  
Subcontract for various Permanent Signage, including directional, building, external and statutory permanent signage.
WP-P1DP-0106 Minor Civil Works20 Mar 202014 Sep 2020 
  
The scope of this package shall include minor civil works for non-permanent work for the project. (This may be in the form of a 'call off' agreement or a panel contract).
The works may include small to medium earth or material transfer and removal, trenching for drainage and services, service and grading of unsurfaced roads, temporary footpaths and access routes.
WP-P1DP-0109 Security Fencing07 Aug 202009 Sep 2020 
  
Subcontract for various specification security fencing, including chain wire mesh, gates, razor wire. Including installation of anti-dig plinths.
WP-P1DP-0110 Joinery24 Aug 202008 Sep 2020 
  
The extent of the works includes items such as reception counters, benchtops, lockers, overhead cupboards, kitchen island benches, all joinery hardware and toilet and shower partitioning systems
WP-P1DP-0114 Furniture Fixture and Equipment21 Aug 202009 Sep 2020 
  
The scope of works comprises supply, delivery, installation, certification and general trade works associated with Furniture, Fixtures and Equipment (FF&E).
The extent of the Works shall include but not limited to the following Furniture, Fixtures and Equipment (FF&E) items:
. Loose Furniture - Supply & Install
. System Furniture - Supply & Install
. Equipment - Supply & Install
. Workstations - Supply & Install
WP-P1DP-0116 Operable Walls07 Sep 202025 Sep 2020 
  
The scope of works comprises supply, delivery, installation, certification and general trade works associated with the Operable Wall trade package.
The operable wall shall be of type Lotus 100 Series or equivalent.
WP-P1DP-055 Painting and Decorating12 Aug 202010 Sep 2020 
  
Subcontract for various specification painting and decorating to walls and ceilings.
Other painting and decorating works subject to design development.
STATUS   01 PHASE 2 EXPRESSION OF INTEREST    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
WP-P2DP-00013 Cladding11 Sep 202024 Sep 2020 
  
Expressions of interest are invited for Phase 2 cladding and roofing packages. Please login download and review the package brief for further details.
WP-P2ISW-0007 Formwork Reinforcement and Pour (FRP)11 Mar 202007 Oct 2020 
  
The subcontract is for FRP works included in the Phase 2 Initial Site Works scope.
WP-P2ISW-0010 Site Accommodation06 Apr 202021 Apr 2020 
  
Additional site accommodation to connect onto already installed buildings to facilitate an increase in site personnel.
Tender lists for Phase 2 will be produced from the assessment of responses to this EOI.
WP-P2ISW-0018 Structural Steel20 Apr 202004 May 2020 
  
Structural Steel frames for industrial buildings.
STATUS   02 REGISTRATION OF INTEREST    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
01 Access Floors - ROI19 Nov 201831 Jan 2021 
 
Access Floors
02 Acoustic Insulation - ROI19 Nov 201831 Jan 2021 
 
Acoustic Insulation
03 Asbestos Removal - ROI19 Nov 201831 Jan 2021 
 
Asbestos Removal
04 Blinds - ROI19 Nov 201831 Jan 2021 
 
Blinds
05 Building Materials - ROI19 Nov 201831 Jan 2021 
 
Building Materials
06 Carpentry (Doors/Frames/Hardware) - ROI19 Nov 201831 Jan 2021 
 
Carpentry (Doors/Frames/Hardware)
07 Civil and Infrastructure Works - ROI19 Nov 201831 Jan 2021 
 
Civil & Infrastructure Works
08 Cleaning - ROI19 Nov 201831 Jan 2021 
 
Cleaning
09 Communications and Data - ROI19 Nov 201831 Jan 2021 
 
Communications and Data
10 Concrete Supply - ROI19 Nov 201831 Jan 2021 
 
Concrete Supply
11 Concrete Place - ROI19 Nov 201831 Jan 2021 
 
Concrete Place
12 Crane Hire - ROI19 Nov 201831 Jan 2021 
 
Crane Hire
13 Demolition - ROI19 Nov 201831 Jan 2021 
 
Demolition
14 Electrical (HV) - ROI19 Nov 201831 Jan 2021 
 
Electrical (HV)
15 Electrical Services (LV) - ROI19 Nov 201831 Jan 2021 
 
Electrical Services (LV)
16 Epoxy Floor Coatings - ROI19 Nov 201831 Jan 2021 
 
Epoxy Floor Coatings
17 External Facade Cladding - ROI19 Nov 201831 Jan 2021 
 
External Facade Cladding
18 Fencing - ROI19 Nov 201831 Jan 2021 
 
Fencing
19 Fire Doors - ROI19 Nov 201831 Jan 2021 
 
Fire Doors
20 Fire Services - ROI19 Nov 201831 Jan 2021 
 
Fire Services
21 Floor Coverings - ROI19 Nov 201831 Jan 2021 
 
Floor Coverings
22 Formwork - ROI19 Nov 201831 Jan 2021 
 
Formwork
23 Furniture Fittings and Equipment - ROI19 Nov 201831 Jan 2021 
 
Furniture, Fittings and Equipment
24 Gantry Cranes - ROI19 Nov 201831 Jan 2021 
 
Gantry Cranes
25 Hydraulic Services - ROI19 Nov 201831 Jan 2021 
 
Hydraulic Services
26 Joinery - ROI19 Nov 201831 Jan 2021 
 
Joinery
27 Kitchen Equipment - ROI19 Nov 201831 Jan 2021 
 
Kitchen Equipment
28 Labour Hire - ROI19 Nov 201831 Jan 2021 
 
Labour Hire
29 Landscaping (Hard) - ROI19 Nov 201831 Jan 2021 
 
Landscaping (Hard)
30 Landscaping (Soft) - ROI19 Nov 201831 Jan 2021 
 
Landscaping (Soft)
31 Lifts - ROI19 Nov 201831 Jan 2021 
 
Lifts
32 Linemarking - ROI19 Nov 201831 Jan 2021 
 
Linemarking
33 Louvres - ROI19 Nov 201831 Jan 2021 
 
Louvres
34 Masonry - ROI19 Nov 201831 Jan 2021 
 
Masonry
35 Masterkeying - ROI19 Nov 201831 Jan 2021 
 
Masterkeying
36 Mechanical Services - ROI19 Nov 201831 Jan 2021 
 
Mechanical Services
37 Metal Wall Cladding - ROI19 Nov 201831 Jan 2021 
 
Metal Wall Cladding
38 Metalwork - ROI19 Nov 201831 Jan 2021 
 
Metalwork
39 Operable Walls - ROI19 Nov 201831 Jan 2021 
 
Operable Walls
40 Painting - ROI19 Nov 201831 Jan 2021 
 
Painting
41 Paint Booth (Industrial) - ROI19 Nov 201831 Jan 2021 
 
Paint Booth (Industrial)
42 Panel Lift Doors (Industrial) - ROI19 Nov 201831 Jan 2021 
 
Panel Lift Doors (Industrial)
43 Partitions and Ceilings - ROI19 Nov 201831 Jan 2021 
 
Partitions and Ceilings
44 Piling - ROI19 Nov 201831 Jan 2021 
 
Piling
45 Plant hire - ROI19 Nov 201831 Jan 2021 
 
Plant Hire
46 Plastering - ROI19 Nov 201831 Jan 2021 
 
Plastering
47 Precast Concrete - ROI19 Nov 201831 Jan 2021 
 
Precast Concrete
48 Reinforcement (Fixing) - ROI19 Nov 201831 Jan 2021 
 
Reinforcement (Fixing)
49 Reinforcement (Supply) - ROI19 Nov 201831 Jan 2021 
 
Reinforcement (Supply)
50 Roads and Carparks - ROI19 Nov 201831 Jan 2021 
 
Roads & Carparks
51 Roller Doors and Shutters - ROI19 Nov 201831 Jan 2021 
 
Roller Doors and Shutters
52 Roofing (Including Roof Safety Systems) - ROI19 Nov 201831 Jan 2021 
 
Roofing (Including Roof Safety Systems)
53 Scaffolding - ROI19 Nov 201831 Jan 2021 
 
Scaffolding
54 Security Services (Guards) - ROI19 Nov 201831 Jan 2021 
 
Security Services (Guards)
55 Security Systems - ROI19 Nov 201831 Jan 2021 
 
Security Systems
56 Services Identification - ROI19 Nov 201831 Jan 2021 
 
Services Identification
57 Sheet Piling - ROI19 Nov 201831 Jan 2021 
 
Sheet Piling
58 Signage - ROI19 Nov 201831 Jan 2021 
 
Signage
59 Small Tools - ROI19 Nov 201831 Jan 2021 
 
Small Tools
60 Stainless Steel - ROI19 Nov 201831 Jan 2021 
 
Stainless Steel
61 Structural Steel - ROI19 Nov 201831 Jan 2021 
 
Structural Steel
62 Survey - ROI19 Nov 201831 Jan 2021 
 
Survey
63 Temporary Fencing - ROI19 Nov 201831 Jan 2021 
 
Temporary Fencing
64 Temporary Buildings - ROI19 Nov 201831 Jan 2021 
 
Temporary Buildings
65 Temporary Electrical / Data - ROI19 Nov 201831 Jan 2021 
 
Temporary Electrical / Data
66 Temporary Hydraulics - ROI19 Nov 201831 Jan 2021 
 
Temporary Hydraulics
67 Tiling - ROI19 Nov 201831 Jan 2021 
 
Tiling
68 Waste Management (bins) - ROI19 Nov 201831 Jan 2021 
 
Waste Management (bins)
69 Waterproofing - ROI19 Nov 201831 Jan 2021 
 
Waterproofing
70 Windows and Glazing - ROI19 Nov 201831 Jan 2021 
 
Windows & Glazing
71 Workstations - ROI19 Nov 201831 Jan 2021 
 
Workstations
72 Modular Buildings (Complete Package) - ROI19 Nov 201831 Jan 2021 
 
Modular Buildings (Complete Package)
73 Long Span Pedestrian Bridge (Complete Package) - ROI19 Nov 201831 Jan 2021 
 
Long Span Pedestrian Bridge (Complete Package)
74 Wharf and Marine Works (Complete Package) - ROI19 Nov 201831 Jan 2021 
 
Wharf & Marine Works (Complete Package)
75 Building Refurbishment (Complete Package) - ROI19 Nov 201831 Jan 2021 
 
Building Refurbishment (Complete Package)
STATUS   03 INITIAL SITE WORKS EOI    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
WP-P1PP-0013 Site Survey 
  

Full scope has been awarded to:

FYFE PTY LTD

Darwin Corporate Park, Tenancy 412, Building 4, Level 1
631 Stuart Highway
BERRIMAH, NT
Australia 0828
Phone: +61 8 8944 7888
Fax: +61 8 8944 7820
Email: info@fyfe.com.au
Web: www.fyfe.com.au

Expression of Interest for early works Site Surveying services, including Site Survey, Site Boundary and Set out points.
WP-P1PP-0017 Earthworks and Civils 
  

Full scope has been awarded to:

Shamrock Civil Engineering Pty Ltd

306 Saint Vincent Street
Port Adelaide, South Australia 5015
estimating@shamrockcivil.com.au
www.shamrockcivil.com.au

Expression of Interest for early works Earthworks and Civil's including Demolition and Grubbing, Earthworks, Service Diversions,Structural Fill, Dust Suppression and Utility Diversions and Capping.
WP-P1PP-0019 Precast Pilling 
  

Full scope has been awarded to:

KELLER PTY LTD

Suite G01-02, Ground Floor
2-4 Lyonpark Road
MACQUARIE PARK, NSW
Australia 2113
Phone: +61 02 8866 1155
Email: info@keller.com.au
Web: www.keller.com.au

Expression of Interest for Precast Pilling, including Precast yard, Casting of Precast Piles, Pile Testing and Piling to CSPIF building.
WP-P1PP-0020 Site Security 
  

Full scope has been awarded to:

AMA CORPORATE SERVICES PTY LTD

76 Unley Road
Unley, SA
Australia 5061
Email: courtney@amasecurity.com.au
Web: http://www.amasecurity.com.au/

Expression of Interest for Site Security including EIFY Turnstile access system, Security Guards and Gate Personnel.
WP-P1PP-0023 Construction Fencing 
  

Full scope has been awarded to:

FIELDQUIP

2 Mons Ave
EDWARDSTOWN, SA
Australia 5039
Phone: (008) 8293 2299
Fax: (008) 8293 2260
Email: sales@fieldquip.net
Web: www.fieldquip.net

Expression of Interest for Construction Fencing including Perimeter fencing to Phase 1 site, Access Gates and Shade Cloth.
WP-P1PP-0024 Waste Management 
  

Full scope has been awarded to:

Suez Recycling & Recovery

133 Cormack Road, Wingfield
SA, Australia 5013
Ph: +61 8 8345 7800
Email: david.muncaster@suez.com
Web: www.sita.com.au

Expressions of Interest for Waste Management, including Skips, Removal of Construction Waste, Removal of Office Waste and Contaminated Waste.
WP-P1PP-0021 Cleaning18 Apr 201903 May 201903 May 2019
  
Expression of Interest for Cleaning services including Office cleaning and Crib and Ablutions cleaning.