Osborne Naval Shipbuilding Precinct (Future Subs Program) Infrastructure Development



Contact Details


  Jeff Camburn, ICN SA
  (08) 8429 3268
 CONTACT EMAIL

  Jeremy Satchell
  (08) 8429 2990
 CONTACT EMAIL

  Eddie Ivar, ICN SA
  (08) 8429 3376
 CONTACT EMAIL

  Locations: SA Australia
  Project Value: TBC
  Project Status: Design Phase
  Project Owner Laing O'Rourke Australia Construction Pty Ltd

Project Details


The Osborne Naval Shipbuilding Precinct (Future Submarine Program) (ONSP(FSP)) Infrastructure Development will provide the necessary build, test, and integration facilities (BTIFI) to design, produce and accept into service a fleet of future submarines (FSM). The project is part of the Commonwealth Government's Naval Shipbuilding Plan announced in May 2017 which sets out the strategic approach to building a long-term, sustainable naval shipbuilding and ship sustainment capability in Australia.


Laing O’Rourke has been awarded the Managing Contractor role for this large scale project and is now requesting Registrations of Interest (ROI) from trade subcontractors interested in participating in this exciting South Australian Project. Delivery Phase works are scheduled to commence in Q1 2019 and be completed in 2026.


The proposed scope of works includes the following:


New building works include:

•    Production Workshops

•    Platform Land Based Test Facility (PLBTF)

•    Combat System Physical Integration Facility (CSPIF)

•    Paint workshops

•    Raft workshop

•    Warehousing

•    Wharf support buildings

•    Shipyard maintenance and utility building

•    Canteen and amenities

•    FSP building

•    On-grade car park and pedestrian bridge over rail


Civil and marine infrastructure includes:

•    Piling, bulk earthworks, roads, aprons and hardstands

•    Wharf upgrades/extensions

•    Power, water, electrical, security and communications infrastructure.


Building refurbishment includes:

Refurbishment of existing buildings

SHOW LESS

Work Packages


To submit an expression of interest, select the icon next to the work package scope you are interested in.
Note: The closing date/s for expressions of interest shown below are subject to change.

OPEN LISTINGS    AWARDED    CLOSED LISTINGS    OTHER
OPEN FOR EOI    INCOMPLETE EOI    EOI COMPLETED
STATUS   01 REGISTRATION OF INTEREST    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
01 Access Floors - ROI19 Nov 1831 Dec 19 
Access Floors
02 Acoustic Insulation - ROI19 Nov 1831 Dec 19 
Acoustic Insulation
03 Asbestos Removal - ROI19 Nov 1831 Dec 19 
Asbestos Removal
04 Blinds - ROI19 Nov 1831 Dec 19 
Blinds
05 Building Materials - ROI19 Nov 1831 Dec 19 
Building Materials
06 Carpentry (Doors/Frames/Hardware) - ROI19 Nov 1831 Dec 19 
Carpentry (Doors/Frames/Hardware)
07 Civil and Infrastructure Works - ROI19 Nov 1831 Dec 19 
Civil & Infrastructure Works
08 Cleaning - ROI19 Nov 1831 Dec 19 
Cleaning
09 Communications and Data - ROI19 Nov 1831 Dec 19 
Communications and Data
10 Concrete Supply - ROI19 Nov 1831 Dec 19 
Concrete Supply
11 Concrete Place - ROI19 Nov 1831 Dec 19 
Concrete Place
12 Crane Hire - ROI19 Nov 1831 Dec 19 
Crane Hire
13 Demolition - ROI19 Nov 1831 Dec 19 
Demolition
14 Electrical (HV) - ROI19 Nov 1831 Dec 19 
Electrical (HV)
15 Electrical Services (LV) - ROI19 Nov 1831 Dec 19 
Electrical Services (LV)
16 Epoxy Floor Coatings - ROI19 Nov 1831 Dec 19 
Epoxy Floor Coatings
17 External Facade Cladding - ROI19 Nov 1831 Dec 19 
External Facade Cladding
18 Fencing - ROI19 Nov 1831 Dec 19 
Fencing
19 Fire Doors - ROI19 Nov 1831 Dec 19 
Fire Doors
20 Fire Services - ROI19 Nov 1831 Dec 19 
Fire Services
21 Floor Coverings - ROI19 Nov 1831 Dec 19 
Floor Coverings
22 Formwork - ROI19 Nov 1831 Dec 19 
Formwork
23 Furniture Fittings and Equipment - ROI19 Nov 1831 Dec 19 
Furniture, Fittings and Equipment
24 Gantry Cranes - ROI19 Nov 1831 Dec 19 
Gantry Cranes
25 Hydraulic Services - ROI19 Nov 1831 Dec 19 
Hydraulic Services
26 Joinery - ROI19 Nov 1831 Dec 19 
Joinery
27 Kitchen Equipment - ROI19 Nov 1831 Dec 19 
Kitchen Equipment
28 Labour Hire - ROI19 Nov 1831 Dec 19 
Labour Hire
29 Landscaping (Hard) - ROI19 Nov 1831 Dec 19 
Landscaping (Hard)
30 Landscaping (Soft) - ROI19 Nov 1831 Dec 19 
Landscaping (Soft)
31 Lifts - ROI19 Nov 1831 Dec 19 
Lifts
32 Linemarking - ROI19 Nov 1831 Dec 19 
Linemarking
33 Louvres - ROI19 Nov 1831 Dec 19 
Louvres
34 Masonry - ROI19 Nov 1831 Dec 19 
Masonry
35 Masterkeying - ROI19 Nov 1831 Dec 19 
Masterkeying
36 Mechanical Services - ROI19 Nov 1831 Dec 19 
Mechanical Services
37 Metal Wall Cladding - ROI19 Nov 1831 Dec 19 
Metal Wall Cladding
38 Metalwork - ROI19 Nov 1831 Dec 19 
Metalwork
39 Operable Walls - ROI19 Nov 1831 Dec 19 
Operable Walls
40 Painting - ROI19 Nov 1831 Dec 19 
Painting
41 Paint Booth (Industrial) - ROI19 Nov 1831 Dec 19 
Paint Booth (Industrial)
42 Panel Lift Doors (Industrial) - ROI19 Nov 1831 Dec 19 
Panel Lift Doors (Industrial)
43 Partitions and Ceilings - ROI19 Nov 1831 Dec 19 
Partitions and Ceilings
44 Piling - ROI19 Nov 1831 Dec 19 
Piling
45 Plant hire - ROI19 Nov 1831 Dec 19 
Plant Hire
46 Plastering - ROI19 Nov 1831 Dec 19 
Plastering
47 Precast Concrete - ROI19 Nov 1831 Dec 19 
Precast Concrete
48 Reinforcement (Fixing) - ROI19 Nov 1831 Dec 19 
Reinforcement (Fixing)
49 Reinforcement (Supply) - ROI19 Nov 1831 Dec 19 
Reinforcement (Supply)
50 Roads and Carparks - ROI19 Nov 1831 Dec 19 
Roads & Carparks
51 Roller Doors and Shutters - ROI19 Nov 1831 Dec 19 
Roller Doors and Shutters
52 Roofing (Including Roof Safety Systems) - ROI19 Nov 1831 Dec 19 
Roofing (Including Roof Safety Systems)
53 Scaffolding - ROI19 Nov 1831 Dec 19 
Scaffolding
54 Security Services (Guards) - ROI19 Nov 1831 Dec 19 
Security Services (Guards)
55 Security Systems - ROI19 Nov 1831 Dec 19 
Security Systems
56 Services Identification - ROI19 Nov 1831 Dec 19 
Services Identification
57 Sheet Piling - ROI19 Nov 1831 Dec 19 
Sheet Piling
58 Signage - ROI19 Nov 1831 Dec 19 
Signage
59 Small Tools - ROI19 Nov 1831 Dec 19 
Small Tools
60 Stainless Steel - ROI19 Nov 1831 Dec 19 
Stainless Steel
61 Structural Steel - ROI19 Nov 1831 Dec 19 
Structural Steel
62 Survey - ROI19 Nov 1831 Dec 19 
Survey
63 Temporary Fencing - ROI19 Nov 1831 Dec 19 
Temporary Fencing
64 Temporary Buildings - ROI19 Nov 1831 Dec 19 
Temporary Buildings
65 Temporary Electrical / Data - ROI19 Nov 1831 Dec 19 
Temporary Electrical / Data
66 Temporary Hydraulics - ROI19 Nov 1831 Dec 19 
Temporary Hydraulics
67 Tiling - ROI19 Nov 1831 Dec 19 
Tiling
68 Waste Management (bins) - ROI19 Nov 1831 Dec 19 
Waste Management (bins)
69 Waterproofing - ROI19 Nov 1831 Dec 19 
Waterproofing
70 Windows and Glazing - ROI19 Nov 1831 Dec 19 
Windows & Glazing
71 Workstations - ROI19 Nov 1831 Dec 19 
Workstations
72 Modular Buildings (Complete Package) - ROI19 Nov 1831 Dec 19 
Modular Buildings (Complete Package)
73 Long Span Pedestrian Bridge (Complete Package) - ROI19 Nov 1831 Dec 19 
Long Span Pedestrian Bridge (Complete Package)
74 Wharf and Marine Works (Complete Package) - ROI19 Nov 1831 Dec 19 
Wharf & Marine Works (Complete Package)
75 Building Refurbishment (Complete Package) - ROI19 Nov 1831 Dec 19 
Building Refurbishment (Complete Package)
STATUS   INITIAL SITE WORKS EOI    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
WP-P1PP-0013 Site Survey18 Apr 193 May 193 May 19
Expression of Interest for early works Site Surveying services, including Site Survey, Site Boundary and Set out points.
WP-P1PP-0017 Earthworks and Civils18 Apr 193 May 193 May 19
Expression of Interest for early works Earthworks and Civil's including Demolition and Grubbing, Earthworks, Service Diversions,Structural Fill, Dust Suppression and Utility Diversions and Capping.
WP-P1PP-0019 Precast Pilling18 Apr 193 May 193 May 19
Expression of Interest for Precast Pilling, including Precast yard, Casting of Precast Piles, Pile Testing and Piling to CSPIF building.
WP-P1PP-0020 Site Security18 Apr 193 May 193 May 19
Expression of Interest for Site Security including EIFY Turnstile access system, Security Guards and Gate Personnel.
WP-P1PP-0021 Cleaning18 Apr 193 May 193 May 19
Expression of Interest for Cleaning services including Office cleaning and Crib and Ablutions cleaning.
WP-P1PP-0023 Construction Fencing18 Apr 193 May 193 May 19
Expression of Interest for Construction Fencing including Perimeter fencing to Phase 1 site, Access Gates and Shade Cloth.
WP-P1PP-0024 Waste Management18 Apr 193 May 193 May 19
Expressions of Interest for Waste Management, including Skips, Removal of Construction Waste, Removal of Office Waste and Contaminated Waste.
STATUS   MISCELLANEOUS    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
Osborne Naval Shipbuilding Precinct (Future Submarines Program) Infrastructure Development - Any Opportunities19 Nov 1831 Dec 19 
Express interest for any opportunities that may arise for this project.