West Angelas Deposits C&D



Contact Details


  Linus O'Brien
  (08) 9365 7556
 CONTACT EMAIL

  Locations: WA Australia (Onshore)
  Project Status: Feasibility Study(subject to approval)
  Project Owner RIO TINTO LIMITED

Project Details


EPCM: Rio Tinto has appointed Jacobs Group Australia Pty Ltd as the projects Engineering, Procurement, Construction Manager (EPCM). All major agreements will be with Rio Tinto directly.  

 

Project Details  

 

The expansion of the existing West Angelas iron ore mine site to provide a replacement source of iron ore to sustain current capacity and enable the continued operation of the existing processing plant, stockyards and rail loop that link the mine to the Rio Tinto Pilbara network.  

 

The Project includes;   

• Rom pad; 

• New primary crushing facility and discharge conveyor; 

• Modifications to existing processing infrastructure; 

• HV re-fuelling facility (including overland diesel pipeline); 

• Secondary crushing facility upgrade; 

• New surge bin facility; 

• Overland conveyor to existing processing plant (approx. 10km); 

• Power supply upgrades; 

• Dewatering and water infrastructure; 

• Gas pipeline realignment (approx. 10km); 

• New non-process infrastructure; 

• Diversion drains and levees; 

• Heavy and light vehicle road networks; 

• Extending existing communications infrastructure; and 

• Temporary construction accommodation.  

 

It is a Rio Tinto requirement that standards utilised are either Australian or internationally recognised equivalents, unless otherwise justified due to specific technological, commercial, intellectual property or similar requirements. All requests for proposal (RFP), tender and contract document references will stipulate any standards requirements. In certain circumstances, materials specifications in RTPs may be met by using either Australian or internationally recognised standards. Otherwise it is the project’s intent that standards specified in RTPs do not seek to exclude Australian business from participating in Tier 1 supply opportunities.  

 

Delivery Schedule:  Subject to approval, construction will take approximately two years and provide employment for over 600 personnel (at peak).  


Project Documents 

SHOW LESS

Work Packages


To submit an expression of interest, select the icon next to the work package scope you are interested in.

OPEN LISTINGS    AWARDED    CLOSED LISTINGS    OTHER
OPEN FOR EOI    INCOMPLETE EOI    EOI COMPLETED
STATUS       ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
33kV Powerline14 Nov 1828 Nov 1828 Nov 18
Please refer to the scope of works documents for package details
33kV Switchboards14 Nov 1828 Nov 1828 Nov 18
Please refer to scope of works document for package details
Switchrooms and LV Switchgear14 Nov 1828 Nov 1828 Nov 18
Specific Scope Requirements: Suppliers wishing to be considered must be able to demonstrate their ability to complete the following tasks:
The Contractor must supply complete switchroom assemblies including:
a) installation of Company supplied 6.6 kV and 33kV switchgear;
b) Installation of Company supplied 6.6kV VVVFs;
c) Supply and installation of LV VVVFs; and
d) Supply and installation of air conditioning, fire detection and suppression, landings, stairs, floor penetrations, lighting, socket outlets and other auxiliary equipment.
Transformers14 Nov 1828 Nov 1828 Nov 18
The Contractor shall design, supply,
manufacture and deliver to Site 33/0.433 kV, 33/6.6 kV and 6.6/0.433 kV
transformers for the West Angelas Deposits C and D Project.
Conveyor Idlers21 Aug 1831 Aug 1831 Aug 18
The Contractor shall design, supply and deliver to site the conveyor
idlers required for the West Angelas Deposits C and D Project.
Mine Communications Systems21 Sep 189 Oct 189 Oct 18
Design, delivery and commissioning of complex turnkey analogue UHF voice mobile radio systems
Conveyor Belting21 Sep 1818 Oct 1818 Oct 18
The Contractor shall supply and deliver to Site the conveyor belting required for the West Angelas Deposits C and D Project
Bulk Earthworks and Civils Works18 Oct 188 Nov 188 Nov 18
New and modified Earthworks and Civil works, including processing hubs and vehicle roads, with overpasses and necessary infrastructure to support the project.
Structural Mechanical Piping Electrical and Instrumentation Works SMPEI22 Oct 189 Nov 189 Nov 18
Please refer to scope of works doc. for a full description of the package.