Koodaideri Project



Contact Details


  Linus O'Brien
  (08) 9365 7556
 CONTACT EMAIL

  Locations: WA Australia (Onshore)
  Project Status: Feasibility Study(subject to approval)
  Project Owner RIO TINTO LIMITED

Project Details


EPCM: Rio Tinto has appointed WorleyParsons Services Pty Ltd as the projects Engineering, Procurement, Construction Manager (EPCM). All major agreements will be with Rio Tinto directly.  

 

Project Details  

 

The development of a new iron ore mine and associated rail infrastructure extending from the Koodaideri mine to Rio Tinto’s existing rail network. The project will include the following components;  

 

• A stockyard with associated stackers and reclaimer; 

• Train load-out facility; 

• A 220kV transmission line connecting to the Yandicoogina transmission line; 

• A 220/33kV switchyard; 

• Site control systems and communications, fire detection and security; 

• A bore field for water supply; 

• Non-process infrastructure (administration buildings, workshops, warehouse, explosive storage facility, vehicle wash and fuelling facilities); 

• A new airport; 

• Bridges;

•Access roads; 

• Accommodation village and temporary construction camps; 

• 170km of new railway including rail sidings and junctions; 

• Level crossings; 

• Rail maintenance track; radio base stations and fibre optic cabling; 

• Signalling, communications and asset protection system upgrades; and 

• Construction facilities such as laydown areas, haul roads, borrow pits, site offices and construction and potable water sources.   

 

It is a Rio Tinto requirement that standards utilised are either Australian or internationally recognised equivalents, unless otherwise justified due to specific technological, commercial, intellectual property or similar requirements. All requests for proposal (RFP), tender and contract document references will stipulate any standards requirements. In certain circumstances, materials specifications in RTPs may be met by using either Australian or internationally recognised standards. Otherwise it is the project’s intent that standards specified in RTPs do not seek to exclude Australian business from participating in Tier 1 supply opportunities.  

 

Delivery Schedule:  Subject to approval, construction of the Project will take approximately three years and provide employment for over 1,600 personnel (at peak). 


Project Documents 

 

SHOW LESS

Work Packages


To submit an expression of interest, select the icon next to the work package scope you are interested in.

OPEN LISTINGS    AWARDED    CLOSED LISTINGS    OTHER
OPEN FOR EOI    INCOMPLETE EOI    EOI COMPLETED
STATUS       ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
6/6 kV Switchgear25 Oct 1822 Nov 1822 Nov 18
Please refer to scope of works document for details of the package
Conveyor Drives 25 Oct 1822 Nov 1822 Nov 18
Please refer to scope of works document for package details
Conveyor Idlers 25 Oct 1822 Nov 1822 Nov 18
please refer to scope of works document for package details
Conveyor Pulleys25 Oct 1822 Nov 1822 Nov 18
Please refer to scope of works document for package details
Laboratory including Building and Equipment25 Oct 1822 Nov 1822 Nov 18
please refer to scope of works document for package details
Mine - Shop Detailing25 Oct 1822 Nov 1822 Nov 18
please refer to scope of works document of details of the package
Camp Crossing Rail Camp (rapid deployment camp)21 Aug 1831 Aug 1831 Aug 18
Design, supply, moblise, install, test. commission and demobilse the 400 Room Crossing Rail Construction camp
Mine Plant Bulk Earthworks6 Sep 1820 Sep 1820 Sep 18
Construction of the Mine Plant Bulk Earthworks contract
Optical Fibre Cable System 21 Sep 186 Oct 186 Oct 18
Supply, install, test and commission 200km of Koodaideri Fibre optic cable mainly through ploughing as an installation method across a greenfield area.
Rail Communications - RBS Construction and Integration 21 Sep 186 Oct 186 Oct 18
Supply, design detailing, procure, install, integrate, test and commission:
seven (7) Rail Base Stations (RBS) site including earthworks required to construct the RBS civil pads, earthing system, RBS tower design, construction and erection.
Chillers28 Sep 1815 Oct 1815 Oct 18
Three (3) identical capacity Chiller Assemblies (one for primary crusher and two for the secondary crushers
Isolation Gates 28 Sep 1815 Oct 1815 Oct 18
The scope of work is to design, manufacture, shop test, pre-assemble, pack and transport isolation gates
Track Weigh Scales28 Sep 1815 Oct 1815 Oct 18
. One (1) track weigh scale assembly
Ballast Supply11 Oct 1825 Oct 1825 Oct 18
Please refer to Scope of Works document
Concrete Sleepers11 Oct 1825 Oct 1825 Oct 18
Please refer to Scope of Works
Accommodation Camps 5 Oct 1826 Oct 1826 Oct 18
Package consists of 470 new rooms and 346 rooms relocated from other RTIO camps, new kitchen facility, gymnasium, swimming pool, sporting and recreational facilities within the Koodaideri Village
Survey Services Mine and Rail19 Oct 181 Nov 181 Nov 18
The Scope of Services covers the provision of labour, plant and equipment, materials, management, supervision and other things necessary to carry out the EPCM survey services to facilitate construction of the Mine and Rail Scope of Work.
33kV Switchgear9 Oct 186 Nov 186 Nov 18
The Scope of Works document details the package requirements
Mine Prestrip26 Oct 1816 Nov 1816 Nov 18
Please refer to scope of works document for package details