Lendlease - HMAS Cerberus Redevelopment Project



Contact Details


  Chris Reilly
  +61 439 616 759
 CONTACT EMAIL

  Locations: VIC Australia
  Project Value: $463 million
  Project Status: Invitation to Register
  Project Owner LENDLEASE BUILDING CONTRACTORS PTY LIMITED

Project Details


About Lendlease

Lendlease has been appointed as the Managing Contractor for the Planning Phase of Project N2197, HMAS Cerberus Redevelopment Project.  The proposed redevelopment will deliver key infrastructure and buildings at the HMAS Cerberus Navy Base in Western Port Bay, Victoria.


About the Project

HMAS Cerberus is located approximately 75km South of Melbourne. The proposed redevelopment will upgrade and refurbish the existing infrastructure and facilities on the Base to meet current and future training and support requirements. The Base is proposed to remain operational during the redevelopment works.


The proposed redevelopment will deliver:

  • The upgrade of key base services including power, water, stormwater, sewerage, gas, fuel systems and information and communications technology to modern standards and to develop spare capacity,

  • Working, training and living accommodations upgraded to contemporary and functional standards and; 

  • Synergistic functions such as messing, logistics support and retail areas are to be consolidated with a view to achieving efficiencies and redundant buildings that are surplus are to be demolished.


Works are being undertaken within two phases.  Phase 1 is underway and Phase 2 is to commence in early 2020.


Lendlease is seeking Invitation to Register (ITRs) from suppliers and contractors for a wide range of work packages that will be required to construct the project. A list of work packages is available on this ICN Gateway project page.


Project Pre-Qualification

  • By submitting an Expression of Interest in, or tender for, this project, you will become subject to the Code for the Tendering and Performance of Building Work 2016
  • The Australian Government Fair Work Principles apply
  • Lendlease Global Minimum Requirements (GMRs) and Environmental, Health and Safety Requirements apply
  • Compliance with Lendlease Quality Systems to meet ISO 9001
  • Previous experience and current workload
  • Employment and training
  • Quality management systems


How to Register an Invitation to Register (ITR)

The ITR is the first of a two stage tender process. Lendlease will select tenderers for particular work packages from those that register interest.


How to register interest:

  • To submit an ITR, companies must have an ICN Gateway company profile. Information on how to register your company on ICN Gateway is detailed below.
  • These are trade specific ITR submissions. All companies who submit an ITR will be included in information presented to Lendlease for this project.
  • Lendlease will be provided with your detailed company profile outlining your capabilities.


Full Scope EOI Registrants:

  • Download and complete the ITR documents attached under the 'Docs' column of the work packages listed below.
  • Submit ITR and all required documentation by clicking on the 'Full Scope' EOI checkbox below.


Partial Scope EOI Registrants:

  • Submit your EOI by clicking on the 'Partial Scope' EOI checkbox below.
  • Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.
     

Important Notes

  • Registrations of Interest received after the closing date and time may not be considered. 
  • Applicants should carefully consider their work packages nominations.
  • Applicants must be able to demonstrate relevant package experience.
  • Subcontract type will be based on Defence MASC-2004.


ICN Gateway Company Registration

  • Click here to register your company profile on ICN Gateway.
  • Support and assistance is available through the web links listed below.
  • An ICN Gateway company profile that accurately and effectively summarises your company is critical to using the services of the ICN Group - please ensure that your company invests the time and energy required to represent your company in the most effective manner possible.
  • Companies should ensure that the email notification functionality within their ICN Gateway company profile is activated to include an appropriate level of coverage to ICN News and Updates, Major Projects and Regional Opportunities.

    (1) ICN Gateway Setup Wizard
    (2) ICN Gateway User Guide
SHOW LESS

Work Packages


To submit an expression of interest, select the icon next to the work package scope you are interested in.
Note: The closing date/s for expressions of interest shown below are subject to change.

OPEN LISTINGS    AWARDED    CLOSED LISTINGS    OTHER
OPEN FOR EOI    INCOMPLETE EOI    EOI COMPLETED
STATUS   A. MAIN WORK PACKAGES - STRUCTURE AND DEMOLITION    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
TP02.32131-01 Scaffolding28 Nov 1915 Dec 1915 Dec 19
Builders Scaffolding required for demolition works for existing building facade replacement on base. Scaffold Loading bay platforms and perimeter handrail included also.

Package Estimate: $1.0 million - $1.5 million

Anticipated Tender Open Date: 29/01/2020

Anticipated Tender Close Date: 26/02/2020

Anticipated Subcontractor Recommendation: 09/04/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.40011-01 Demolition28 Nov 1915 Dec 1915 Dec 19
Demolition package works consists of all Demolition Works including:
- Demolition of the existing buildings
- Strip out existing buildings to be refurbished
- Hazardous Material Removal (Hygienest advise by others)
- Movement of large equipment on Base
- Lead Paint Removal


Package Estimate: $3.2 million - $4.8 million

Anticipated Tender Open Date: 17/01/2020

Anticipated Tender Close Date: 14/02/2019

Anticipated Subcontractor Recommendation: 28/03/2019

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.41012-01 Concrete Structure28 Nov 1915 Dec 1915 Dec 19
Concrete Structure package works consists of all in-situ Concrete Structure Works including:
- Detailed excavation
- Ground prep
- Form work and reinforcement
- Post tensioning
- Concrete supply place and finish
- All plant and equipment to complete works
- Termite protection

Package Estimate: $6.3 million - $9.5 million

Anticipated Tender Open Date: 13/01/2020

Anticipated Tender Close Date: 10/02/2020

Anticipated Subcontractor Recommendation: 24/03/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.41023-01 Concrete Precast Panel28 Nov 1915 Dec 1915 Dec 19
Concrete Precast Panel package works consists of all Concrete Precast Panel works including:
- Shop Drawing and Design Development
- Supply & Installation of Precast Panels and associated components
- All plant and equipment including craneage for Precast Panel Erection


Package Estimate: $2.1 million - $3.1 million

Anticipated Tender Open Date: 24/01/2020

Anticipated Tender Close Date: 21/02/2020

Anticipated Subcontractor Recommendation: 04/04/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.41131-01 Structural Steel28 Nov 1915 Dec 1915 Dec 19
Structural Steel package works consists of all Structural Steel Works including:
- Shop Drawing and Design Development
- Supply & Installation of Structural Steel
- All plant and equipment including craneage for Steel Erection
- Gantry Crane ET/TT Fcaility
-Ship doors - MT building


Package Estimate: $4.6 million - $6.9 million

Anticipated Tender Open Date: 22/01/2020

Anticipated Tender Close Date: 19/02/2020

Anticipated Subcontractor Recommendation: 02/04/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.42034-01 Timber Structure - Refurbishment28 Nov 1915 Dec 1915 Dec 19
Timber Structure - Refurbishment package works consists of all Timber Structure - Refurbishment works including:

Existing Timber Structure upgrade is required to Heritage Listed Buildings on Base. Works will require removal of existing flooring, supply and Installation of replacement Timber Structure (including all plant and equipment).

Package Estimate: $0.7 million - $1.1 million

Anticipated Tender Open Date: 16/02/2020

Anticipated Tender Close Date: 12/03/2020

Anticipated Subcontractor Recommendation: 24/04/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.43071-01 Lift - Block A. B and C28 Nov 1915 Dec 1915 Dec 19
Lift - Block A, B & C package works consists of all Lift Works including:
-Supply and Install of personnel lifts to buildings


Package Estimate: $0.4 million - $0.6 million

Anticipated Tender Open Date: 02/02/2020

Anticipated Tender Close Date: 27/02/2020

Anticipated Subcontractor Recommendation: 10/04/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
STATUS   B. FACADE WORK PACKAGES    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
TP02.41091-01 Masonry and Blockwork and Bricks28 Nov 1915 Dec 1915 Dec 19
Masonry , Blockwork & Bricks package works consists of all Masonry, Blockwork & Brick works including:
- external brickwork
- internal Blockwork walls
- door frame install (only) (to brickwork, blockwork, and concrete door openings)
- blockwork stiffener supply and install
- reo and core filling as required
- refurbishment of existing brickwork walls


Package Estimate: $0.8 million - $1.2 million

Anticipated Tender Open Date: 07/03/2020

Anticipated Tender Close Date: 01/04/2020

Anticipated Subcontractor Recommendation: 14/05/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.41154-01 Internal Glazing and External Glazing28 Nov 1915 Dec 1915 Dec 19
Scope include the supply and installation of:
- glazed partitions & aluminium suites for all external and internal windows
- aluminium Door Frames, and Aluminium / Glazed doors along with associated Door Hardware


Package Estimate: $1.2 million - $1.8 million

Anticipated Tender Open Date: 21/03/2020

Anticipated Tender Close Date: 15/04/2020

Anticipated Subcontractor Recommendation: 28/05/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.41154-02 Heritage Windows - Block A28 Nov 1915 Dec 1915 Dec 19
Heritage Windows - Block A package works consists of all Heritage Window works including:
- Heritage window refurbishment for Building 187


Package Estimate: $0.2 million - $0.3 million

Anticipated Tender Open Date: 29/02/2020

Anticipated Tender Close Date: 25/03/2020

Anticipated Subcontractor Recommendation: 07/05/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.41171-01 Ext Wall Claddings28 Nov 1915 Dec 1915 Dec 19
Ext Wall Cladding package works consists of all Ext Wall Cladding works
- External Metal wall cladding to all facilities.

Package Estimate: $1.3 million - $1.9 million

Anticipated Tender Open Date: 08/02/2020

Anticipated Tender Close Date: 04/03/2020

Anticipated Subcontractor Recommendation: 16/04/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.41171.02 Louvres28 Nov 1915 Dec 1915 Dec 19
Louvres package works consists of all External Louvres works including:
- grilles
- plant enclosures


Package Estimate: $0.8 million - $1.1 million

Anticipated Tender Open Date: 15/02/2020

Anticipated Tender Close Date: 11/03/2020

Anticipated Subcontractor Recommendation: 23/04/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.41172-01 Roofing28 Nov 1915 Dec 1915 Dec 19
The Metal roofing and roof plumbing scope consists of roofing to new buildings across the base as well as refurbishment and make good of existing buildings. This Package will also include the design, and certification of Roof access system


Package Estimate: $2.7 million - $4.1 million

Anticipated Tender Open Date: 22/02/2020

Anticipated Tender Close Date: 18/03/2020

Anticipated Subcontractor Recommendation: 30/04/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.42113-01 Waterproofing and Epoxy28 Nov 1915 Dec 1915 Dec 19
Waterproofing and Epoxy Scope works include Supply and Installation of the following:
- surface preparation and Treatment fo concrete floors
- exposed Waterproofing membranes
- epoxy
- concrete sealants


Package Estimate: $0.1 million - $0.2 million

Anticipated Tender Open Date: 14/03/2020

Anticipated Tender Close Date: 08/04/2020

Anticipated Subcontractor Recommendation: 21/05/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
STATUS   C. SHELLWORK WORK PACKAGES    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
TP02.42038-02 Carpentry/ Doors/ Frames/ Hardware and Skirtings28 Nov 1915 Dec 1915 Dec 19
The Carpentry Scope includes Supply & installation of:
- supply of Pressed Metal Door frames to Partition Contractor and Blockwork Contractor
- hardware
- skirting
- operable Walls
- door frame supply
- sanitary Hardware
- supply of Fixtures and Fittings


Package Estimate: $2.3 million - $3.5 million

Anticipated Tender Open Date: 11/04/2020

Anticipated Tender Close Date: 06/05/2020

Anticipated Subcontractor Recommendation: 18/06/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.42057-01 Joinery28 Nov 1915 Dec 1915 Dec 19
Scope includes all fixed joinery across the site including:
- desks
- shelving
- brew rooms
- overheads
- bedroom joinery


Package Estimate: $1.0 million - $1.5 million

Anticipated Tender Open Date: 04/04/2020

Anticipated Tender Close Date: 29/04/2020

Anticipated Subcontractor Recommendation: 11/06/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.42073-01 Plasterboard Partitions and Ceiling28 Nov 1915 Dec 1915 Dec 19
Partitions and Ceilings Package Includes the supply and installation of:
- all framed walls and ceilings
- linings such as plasterboard, compressed fibre cement, plywood partitions and wall linings, thermal insulation
- door frame install within framed walls only (Doors and door frame supply are excluded from this package)



Package Estimate: $6.5 million - $9.7 million

Anticipated Tender Open Date: 18/04/2020

Anticipated Tender Close Date: 13/05/2020

Anticipated Subcontractor Recommendation: 25/06/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.42092-01 Floor Coverings (Carpet and Vinyl)28 Nov 1915 Dec 1915 Dec 19
Floor coverings Scope includes the Supply and Installation of:
- all carpet and vinyl floor coverings
- timber flooring
- nosing strips & tactiles (All sites)
- entry mats
- floor preparation


Package Estimate: $1.3 million - $2 million

Anticipated Tender Open Date: 02/05/2020

Anticipated Tender Close Date: 27/05/2020

Anticipated Subcontractor Recommendation: 09/07/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.42111-01 Tiling28 Nov 1915 Dec 1915 Dec 19
Floor and wall tiling (including stone) is required to all buildings throughout:
- hallways
- external areas
- wet areas
- stairs

Floor prep, subgrade & floating will be required to below tiled areas. Waterproof membrane under floor finishes.


Package Estimate: $2.1 million - $3.2 million

Anticipated Tender Open Date: 23/05/2020

Anticipated Tender Close Date: 17/06/2020

Anticipated Subcontractor Recommendation: 30/07/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.43177-01 Kitchen Fitout/Stainless Steel28 Nov 1915 Dec 1915 Dec 19
Kitchen fitout works include the supply and installation of:
- cool rooms
- removal and installation of existing and new Kitchen Equipment
- new kitchen plant and equipment
- stainless steel project wide (including laundries through Living in Accommodation)



Package Estimate: $2.7 million - $4.1 million

Anticipated Tender Open Date: 28/03/2020

Anticipated Tender Close Date: 22/04/2020

Anticipated Subcontractor Recommendation: 04/06/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
STATUS   D. FINISHING WORK PACKAGES    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
TP02.42011-01 Metalwork28 Nov 1915 Dec 1915 Dec 19
Floor covering scope includes the Supply and Installation of:
- balustrade & handrail
- bike racks etc.
- corner guards
- ladders platforms (where not installed by roof access).


Package Estimate: $1.1 million - $1.6 million

Anticipated Tender Open Date: 16/05/2020

Anticipated Tender Close Date: 10/06/2020

Anticipated Subcontractor Recommendation: 23/07/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.42015-01 Roller Shutters28 Nov 1915 Dec 1915 Dec 19
Supply and installation for all roller shutters project wide.

Package Estimate: $0.1 million - $0.1 million

Anticipated Tender Open Date: 13/06/2020

Anticipated Tender Close Date: 08/07/2020

Anticipated Subcontractor Recommendation: 20/08/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.42031-01 Toilet Partitions / Shower Partitions / Shower Screens28 Nov 1915 Dec 1915 Dec 19
Supply and installation of:
- toilet partitions
- shower partitions
- shower screens

Package Estimate: $0.3 million - $0.4 million

Anticipated Tender Open Date: 30/05/2020

Anticipated Tender Close Date: 24/06/2020

Anticipated Subcontractor Recommendation: 06/08/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.42054-01 Workstations28 Nov 1915 Dec 1915 Dec 19
Supply and placement of all office workstations to buildings including overhead shelving.

Package Estimate: $0.5 million - $0.7 million

Anticipated Tender Open Date: 09/05/2020

Anticipated Tender Close Date: 03/06/2020

Anticipated Subcontractor Recommendation: 16/07/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.42171-01 Painting28 Nov 1915 Dec 1915 Dec 19
Scope includes for all site applied painting finishes to internal and external areas.

Package Estimate: $1.3 million - $1.9 million

Anticipated Tender Open Date: 06/06/2020

Anticipated Tender Close Date: 01/07/2020

Anticipated Subcontractor Recommendation: 13/08/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.44011-01 External Fences (Hard Landscaping)28 Nov 1915 Dec 1915 Dec 19
The external fencing scope includes:
- Chain link fencing
- Palisade fencing
- Gates

Package Estimate: $0.2 million - $0.3 million

Anticipated Tender Open Date: 11/07/2020

Anticipated Tender Close Date: 05/08/2020

Anticipated Subcontractor Recommendation: 17/09/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.44012-01 Soft Landscaping28 Nov 1915 Dec 1915 Dec 19
Soft landscaping Package includes the supply and installation of:
- soils
- spray seed
- irrigation
- mulch
- plants and trees


Package Estimate: $0.5 million - $0.7 million

Anticipated Tender Open Date: 25/04/2020

Anticipated Tender Close Date: 20/05/2020

Anticipated Subcontractor Recommendation: 02/07/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
STATUS   E. FURNITURE, FIXTURES & EQUIPMENT WORK PACKAGES    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
TP02.32116-01 Final Cleaning28 Nov 1915 Dec 1915 Dec 19
Scope includes for builders clean and final clean project wide.

Package Estimate: $0.4 million - $0.6 million

Anticipated Tender Open Date: 25/07/2020

Anticipated Tender Close Date: 19/08/2020

Anticipated Subcontractor Recommendation: 01/10/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.40031-02 Removal of Contaminated Material28 Nov 1915 Dec 1915 Dec 19
Scope includes removal of contaminated material offsite to a licensed waste facility if friable asbestos or lead containing material is found.

Package Estimate: To be based on m3 rates

Anticipated Tender Open Date: 18/07/2020

Anticipated Tender Close Date: 12/08/2020

Anticipated Subcontractor Recommendation: 24/09/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.42052-01 Blinds28 Nov 1915 Dec 1915 Dec 19
Supply and installation of blinds project wide.

Package Estimate: $0.1 million - $0.1 million

Anticipated Tender Open Date: 04/07/2020

Anticipated Tender Close Date: 29/07/2020

Anticipated Subcontractor Recommendation: 10/09/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.42153-01 Furniture Fixtures and Equipment Package - Lockers28 Nov 1915 Dec 1915 Dec 19
The FF&E Package includes the supply and placement of all Loose Furniture - Lockers.

Package Estimate: $0.1 million - $0.1 million

Anticipated Tender Open Date: 20/06/2020

Anticipated Tender Close Date: 15/07/2020

Anticipated Subcontractor Recommendation: 27/08/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.42153-02 Furniture Fixtures and Equipment Package - Appliances28 Nov 1915 Dec 1915 Dec 19
The FF&E Package includes the supply and placement of all Loose Furniture:
- Fridges
- Dishwashers
- Ovens
- Dryers
- Washing machines

Package Estimate: $1.8 million - $2.6 million

Anticipated Tender Open Date: 01/08/2020

Anticipated Tender Close Date: 26/08/2020

Anticipated Subcontractor Recommendation: 08/10/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.42153-03 Furniture Fixtures and Equipment Package - Chairs and Tables28 Nov 1915 Dec 1915 Dec 19
The FF&E Package includes the supply and placement of all Loose Furniture - Chairs and Tables.

Package Estimate: $1.1 million - $1.7 million

Anticipated Tender Open Date: 08/08/2020

Anticipated Tender Close Date: 02/09/2020

Anticipated Subcontractor Recommendation: 15/10/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.42153-04 Furniture Fixtures and Equipment Package - Storage28 Nov 1915 Dec 1915 Dec 19
The FF&E Package includes the supply and placement of all Loose Furniture:
- Compactus
- Cabinets
- Basketball nets and other sporting equipment

Package Estimate: $0.5 million - $0.7 million

Anticipated Tender Open Date: 15/08/2020

Anticipated Tender Close Date: 09/09/2020

Anticipated Subcontractor Recommendation: 22/10/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.
TP02.42158-01 Signage28 Nov 1915 Dec 1915 Dec 19
Project wide signage including directional signage, graphics, and statutory signage.

Package Estimate: $0.2 million - $0.3 million

Anticipated Tender Open Date: 27/06/2020

Anticipated Tender Close Date: 22/07/2020

Anticipated Subcontractor Recommendation: 03/09/2020

Full Scope EOI Registrants:
- Download and complete the ITR documents under the 'Docs' column.
- Submit the required ITR documentation by clicking on the 'Full Scope' EOI checkbox.

Partial Scope EOI Registrants:
- Submit your EOI by clicking on the 'Partial Scope' EOI checkbox.
- Partial Scope registrant details will be provided to successful Full Scope tenderers, at time of tender, for their review and consideration in their tender offers/proposals.

Important Notes:
- All enquiries must be raised at least 5 business days prior to the work package (ITR) close date.
- All ITR submissions must be uploaded onto this ICN Gateway page by 11.59pm AEST on 15 December 2019.