|
STATUS
|
|
A. CONSTRUCTION & TRADES ▲ CONTRACT
|
OPENS
|
FULL SCOPE CLOSES
|
PARTIAL SCOPE CLOSES
|
DOCS
|
FULL SCOPE EOI
|
PARTIAL SCOPE EOI
|
| | Access Ladders and Platforms | 24 Jul 2019 | 01 Sep 2020 | 01 Sep 2020 | 
| | |
| Scope of Works: Supply and/or installation of Caged Ladders, Walkways and Access Platforms
Work Zone: East
Approx Tonnage: 450
Approx Installation Date: January 2021 |
| | Bridge Rail | 24 Jul 2019 | 01 Nov 2020 | 01 Nov 2020 | 
| | |
| Scope of Works: Supply and/or Installation of Bridge Rails to Bridge 60,61,62,71 and Parapet Rails
Work Zone: East
Approx Tonnage: 940
Approx Installation Date: Q3 2020 |
| | Gantries - ITS Structures | 24 Jul 2019 | 01 Dec 2020 | 01 Dec 2020 | 
| | |
| Scope of Work: Supply and Installation of Gantries for ITS Structures
Work Zone: East
Approx Tonnage: 407
Statue: Concept Designs Stage |
| | Light Poles | 24 Jul 2019 | 01 Dec 2020 | 01 Dec 2020 | 
| | |
| Scope of Works: Supply and/or Installation of Light Poles
Work Zone: East
Installation: Approx Q1 2020 to Q3 2021 |
| | Mast | 24 Jul 2019 | 01 Dec 2020 | 01 Dec 2020 | 
| | |
| Scope of Works: Supply and/or Installation of Mast
Work Zone: East
Approx Tonnage: 176
Installation: Approx Q4 2020 to Q3 2021 |
| | V81107-0104 Supply and Installation of Noise Walls and Retaining Walls - Package CLOSES 16 JULY 2018 | 12 Jul 2018 | 26 Jul 2018 | 26 Jul 2018 | 
| |
| (A) Supply & Install Retaining Walls, Noise Wall Piles, Pile Capping Beams, Gantry Piles, Training Wall Posts, Cast insitu Pile Caps, Cast Insitu Spread Footings, Shotcrete Walls and Reinforcement including trimming and strip drains, Cast insitu Strip Footings, steel fixings, ragbolts, grout, panel clips, acrylic channels and similar, Acrylic Noise Wall Panels.
(B) Install only Pre-cast Concrete Fascia Panels, Retaining Wall Panels and Concrete Noise Wall Panels.
(C) Remove and disposal of existing Noise Walls.
PLEASE NOTE THIS PACKAGE WILL CLOSE 16 JULY 2018. |
| | Bearing and Retainer Plates | 06 Aug 2019 | 31 Oct 2019 | 31 Oct 2019 | 
| |
| Scope of Works: Supply and/or Installation of Bearing Plates
Work Zone: East
Approx Tonnage: 336
Approx Installation Date: November 2019
Scope of Works: Supply and/or Installation of Retainer Plates
Work Zone: East
Approx Tonnage: 1344
Approx Installation Date: November 2019 |
| | Architectural Cladding | 24 Jul 2019 | 01 Nov 2019 | 01 Nov 2019 | 
| |
| Scope of Works: Supply and/or Installation of Architectural Cladding
Work Zone: East
Approx Tonnage: 190
Approx Tender Date: August 2019 |
| | Northern Portal Structural Steel | 06 Aug 2019 | 30 Nov 2019 | 30 Nov 2019 | 
| |
| Scope of Works: Supply and/or Installation of Structural Steel for the Northern Portal
Work Zone: Building
Approx Tonnage: 700
Approx Installation Date: Early 2020 |
| | Southern Portal Structural Steel | 06 Aug 2019 | 30 Nov 2019 | 30 Nov 2019 | 
| |
| Scope of Works: Supply and/or installation of Structural Steel for the Southern Portal
Work Zone: Building
Approx Tonnage: 650
Approx Installation Date: Early 2020 |
| | Handrails | 24 Jul 2019 | 01 Dec 2019 | 01 Dec 2019 | 
| |
| Scope of Works: Supply and/or Installation of Handrails
Work Zone: East
Approx Tonnage: 186
Installation: approx 2020 |
| | Structural Steel | 24 Jul 2019 | 01 Dec 2019 | 01 Dec 2019 | 
| |
| Scope of Works: Supply and/or Installation of Structural Steel
Work Zone: East
Approx Tonnage: 9453
Status: Designs range from Conceptual to Detailed IFC
Installation: approx Q1 2020 to Q1 2021 |
| | Temporary Steel | 24 Jul 2019 | 01 Dec 2019 | 01 Dec 2019 | 
| |
| Scope of Works: Supply and/or Installation of Temporary Steel
Work Zone: East
Approx Tonnage: 968
Installation: approx from Q3 2020 |
| | V81102-0710 Bored Piling - Hyde Street Bridges | 18 Sep 2018 | 31 Oct 2018 | | 
| |
| This scope is for the bored piling which will establish Hyde Street Bridges in area 203 of the West Zone. There will be two separable portions. |
| | V81103-0186 Tunnel Service Pipes and Fittings Etc | 20 Jul 2018 | 10 Aug 2018 | | 
| |
| Supply & Delivery of Tunnel Service Pipes, Couplings ,Valves & Manifolds |
| | V81103-0281 Temporary Access Towers | 17 Jul 2018 | 31 Jul 2018 | | 
| |
| Supply, delivery, erection and dismantling of temporary access towers to existing CityLink ramp viaducts, and other scaffolding works as required. |
| | V81104-0447 Steel Pile Liner Supply | 17 Jul 2018 | 31 Jul 2018 | | 
| |
| Fabrication, surface coating, supply and delivery to site of compliant steel pile liners for bored piles (1600mm diameter) and driven piles (1600mm/2000mm/2200mm diameter) at bridge locations in the east zone. |
| | V81104-0451 Bridge Cladding | 17 Jul 2018 | 31 Jul 2018 | | 
| |
| The design, supply of material, fabrication, surface treatment and complete installation of all bridge cladding, architectural screens including acrylic panels and/or fins on bridges BR50, BR51, BR52 & BR53 in the east zone. |
| | V81104-0559 Jetty Fabrication Package CLOSES 23 JULY 2018 | 17 Jul 2018 | 31 Jul 2018 | | 
| |
| Jetty Fabrication - East Zone Package 0559 |
| | V81104-0573 Sheet Pile Supply | 17 Jul 2018 | 30 Jul 2018 | | 
| |
| Fabrication, supply and delivery to site of approx. 1000t of sheet piles. (Interest in the availability of a buy back option of sheet piles.) |
| | V81104-0577 Bridge Bearings and Expansion Joints | 17 Jul 2018 | 31 Jul 2018 | | 
| |
| The design, supply of material, fabrication, surface treatment for the bearing plates, complete supply and delivery of all bridge bearings for bridges in the east zone. Scope also includes fabrication, supply and delivery of expansion joints for bridges |
| | V81104-0675 Fabricated Steel Girders | 25 Sep 2018 | 22 Oct 2018 | | 
| |
| The works associated with the fabrication and delivery of steel girders to the Maribyrnong Bridge Steel Superstructures including but not limited to:
- Design, detailing, drawing development and software modelling;
- Perform all necessary temporary works inclusive of design;
- Fabrication of steel plates, beams/girders to the quality standards specified by CPBJH JV (including VicRoads);
- Handling and storage of all fabricated goods; and
- Logistics associated with the transport and delivery of all fabricated goods to the site locations nominated by CPBJH JV.
|
| | V81104-XXXX Crawler Crane Hire PACKAGE CLOSES 17 AUG 2018 | 13 Aug 2018 | 27 Aug 2018 | | 
| |
| Works to be undertaken at the East Zone of the West Gate Tunnel Project (Project) include the construction of overhead structures with components weighing up to 280T.
To ensure the safe and efficient performance of these works, the Project requires the supply of crawler crane plant ranging from 100-700T capacity with some configurations expected to require super lifts. It is anticipated that the preferred vendor shall have the resource capacity to meet demanding Project requirements.
Interested participants shall note that the supply is dry hire only and the period of hire shall range from 6 months to 2 years in duration. |
| | V81104-XXXX Rigging Gear PACKAGE CLOSES 4 SEP 2018 | 30 Aug 2018 | 14 Sep 2018 | | 
| |
| Works to be undertaken at the East Zone of the West Gate Tunnel Project (Project) include the lifting of equipment and structures.
The Project seeks expression of interest from providers with regard to the supply, tag and inspection of rigging gear. This includes, but is not limited to chains, slings, hooks, material cages, FSWR and other rigging materials utilised for lifting purposes.
Interested participants shall note that the period of engagement shall range from 6 months to 3-4 years in duration.
|
| | V81105-0213 Lifts - Egress Out and Under | 01 Dec 2018 | 14 Dec 2018 | | 
| |
| This scope of work covers the design, supply and installation of one number low-rise non-automatically controlled, fully enclosed platform lifts in each of the 9 Egress Out & Under (EOU) areas. |
| | V81105-0430-1 Low Voltage Distribution Boards | 09 Jul 2018 | 21 Sep 2018 | | 
| |
| Low Voltage Equipment (above ground) Fabrication and Delivery:
1. 415v & 690v switchboards(41 Unit)
2. Distribution Boards (28 Unit)
3. 415v & 690v Switchboards - Maintenance Invert - (12 Unit)
4. Low Voltage Equipment, UPS System - Maintenance Invert - (5 Unit)
5. Distribution Boards - Maintenance Invert - (72 Unit)
6. Sump Pump / Water Treatment Equipment & Switchboard Motor Control Centre (5 Unit) |
| | V81105-XXXX High Voltage Equipment - Transformers | 09 Jul 2018 | 24 Aug 2018 | | 
| |
| Fabricate & Supply:
1. 1000KVA Dry Type 22/0.4kV
2. 1500KVA Dry Type 22/0.69kV
3. 2000KVA Type 22/0.69kV |
| | V81107-0300 Calibration and Test Equipment | 04 Aug 2018 | 18 Aug 2018 | | 
| |
| Supply of Calibration Equipment at Benalla for Concrete Distribution and Batch Plant Laboratory. |
| | V81107-0306 Lifting Spreader Beams PACKAGE CLOSES 6 AUGUST 2018 | 01 Aug 2018 | 14 Aug 2018 | | 
| |
| Design, Manufacture and delivery of LiftingSpreader Bems to lift Precast Concrete Elements and Cages.
Concrete T Beams 90 M long and approx 23 Tonnes
Cages & Strand 100M long approx 16.8 tonnes |
| | V81107-0313 Electrical Reticulation and Commissioning | 06 Aug 2018 | 20 Aug 2018 | | 
| |
| Supply of Electrical Reticulation and Commissioning at new Precast Concrete Plant at Benalla in Regional Victoria. |
| | V81107-0337 Supply and Install Crane Rails | 09 Jul 2018 | 23 Jul 2018 | | 
| |
| Overhead crane rail supply and installation inside of the sheds. Must be supplied in accordance to the shed support capabilities. |
| | V81107-0351 Steel Stressing Strand | 04 Aug 2018 | 18 Aug 2018 | | 
| |
| Supply of Steel Stressing Strand. Seven Wire Ordinary Strand of Normal Diameter 15.2 mm. Minimum Strength of 1750mpa with Low Relaxation Stress Relieved. Minimum Breaking Load of 250KN |
| | V81107-0566 Lamps and Poles | 04 Aug 2018 | 18 Aug 2018 | | 
| |
| Supply of Electric Lamps and Poles for the New Precast Concrete facility in Benalla Victoria |
| | V81107-0622 Mechanical Services and Maintenance | 06 Aug 2018 | 20 Aug 2018 | | 
| |
| Supply of Mechanical Services and Maintenance at Precast Concrete Plant being built at Benalla in Regional Victoria. |
| | V81107-0623 Electrical Maintenance and Services | 06 Aug 2018 | 20 Aug 2018 | | 
| |
| Supply of Maintenance and Electrical Services at Precast Concrete Plant being built at Benalla in Regional Victoria. |
| | V81107-XXXX Crane Maintenance Services | 04 Aug 2018 | 18 Aug 2018 | | 
| |
| Supply of Crane Maintenance Services at new Precast Facility in Benalla Victoria |
| | V81107-XXXX LPG Supply PACKAGE CLOSES 21 SEP 2018 | 14 Sep 2018 | 28 Sep 2018 | | 
| |
| Supply of LPG gas for Benalla Precast Plant.
Estimated usage of 10,000 kg per week for around 2 years |
| | V81107-XXXX Mould Stripping Oil | 04 Aug 2018 | 18 Aug 2018 | | 
| |
| Supply of Mould Stripping Oil for Precast Concrete Plant |
| | V81107-XXXX Septic Tanks | 04 Aug 2018 | 18 Aug 2018 | | 
| |
| Supply of Septic Tanks |
| | V81107-XXXX Silo 100 Tonne Capacity For Cement Storage | 04 Aug 2018 | 18 Aug 2018 | | 
| |
| Supply of Cement Storage Silo 100 Tonne Capacity Complete With Jet Pulse Filter and Overfill Protection System |
| | V81107-XXXX Switchboards | 06 Aug 2018 | 20 Aug 2018 | | 
| |
| Supply of Electrical Switchboards |
| | V81107-XXXX Truck Unloader | 04 Aug 2018 | 18 Aug 2018 | | 
| |
| Supply of Drive Over Style Truck Unloader |
|
STATUS
|
|
B. MISCELLANEOUS ▲ CONTRACT
|
OPENS
|
FULL SCOPE CLOSES
|
PARTIAL SCOPE CLOSES
|
DOCS
|
FULL SCOPE EOI
|
PARTIAL SCOPE EOI
|
| | CPBJH JV - West Gate Tunnel Project - Any Opportunities | 03 Jul 2017 | 30 Jun 2020 | 30 Jun 2020 | 
| | |
| Express interest for Any Opportunities that may arise for this project. |
| | Local and Small Business Opportunities to Support the Delivery of the WGTP | 12 Jul 2018 | 30 Jun 2020 | | 
| | |
| The West Gate Tunnel Project is committed to supporting local businesses across Melbourne's Western Suburbs. We would like to connect with local suppliers and businesses who are able to assist with the day to day procurement opportunities that might arise from a Project of this size and nature.
We are also actively encouraging our workforce to shop local, supporting businesses the length of the project from Docklands to Laverton.
The types of goods and services we are potentially looking to procure include, but are not limited to the following:
Workforce Support
Construction support
Health & Fitness
Advisory Services
Office Set-up/Running
Work-life Balance
Event Hosting
Educational programs
Catering
Automotive Repairs
Laundry Services
and many more.
If you believe you have something to offer our Project and/or our Workforce, please complete an EOI against this Work Package. |