The Eagle Downs Coal Project is located in the Bowen Basin in Central Queensland.

The Project involves construction, development and operation of an underground longwall hard coking coal mine, Coal Handling and Preparation Plant (CHPP) and associated infrastructure. Eagle Downs Coal Management Pty Ltd (EDCM) is delivering the project under a joint venture of Aquila Coal Pty Ltd and South32 Eagle Downs Pty Ltd, the Eagle Downs Coal Joint Venture  .

It is estimated that the mine will produce an average of 4.5Mtpa of product coking coal in the first ten years of full production from one underground longwall. The later years will utilise longwall top coal caving. The mine life is expected to be 45 years. The coal from our mine is a low volatile, hard coking coal that is highly sought in global markets.

The Coal Handling and Preparation Plant (CHPP) will have a throughput of 1,100tpa Run of Mine (ROM).

Coal will be transported by conveyor from the mine to a CHPP where it will be crushed, sized and washed before being transported to a export coal facility.

Project location

The Project is located within the Bowen Basin of Central Queensland near the BMA Peak Downs mine, approximately 25km south of the centre of Moranbah.

The mining lease (ML 70389) covers an area of approximately 4,550 hectares (ha). The BMA Peak Downs mine is located approximately two kilometres (km) to the west, while the Norwich Park Branch railway line is located in the south-east corner of the Project area.

The site is owned by a single landowner. The majority of the land has been used for grazing and is within the jurisdiction of the Belyando Shire. A smaller portion of the land is subject to the jurisdiction of the Broadsound Shire. 

Project Timelines

The project is currently in the study phase and will be seeking final investment decision mid 2020.


The Expression of Interest Process:

All potential subcontractors and suppliers are encouraged to register their interest via the ICN Gateway website in order to be considered.


The Expression of Interest Process is summarised in the steps below:

  1. Companies complete ICN Gateway EOI 
  2. ICN assess & provide initial shortlist recommendations
  3. Eagle Downs Coal Management validates ICN shortlist.
  4. Eagle Downs Coal Management prequalifies the shortlisted companies
  5. Issue RFT to final shortlisted tenderers.

If not registered with ICN, Companies must create a profile on the ICN web page - Click here

Please note- An EOI does not guarantee that you will receive request for quotation documentation. Eagle Downs Coal will only invite prequalification and/or tender from suppliers with demonstrated capability and capacity. It is essential that your company profile on ICN Gateway is complete, up-to-date and accurate.

SHOW LESS

Work Packages


To submit an expression of interest, select the icon next to the work package scope you are interested in.
Note: The closing date/s for expressions of interest shown below are subject to change.

OPEN LISTINGS    AWARDED    CLOSED LISTINGS    OTHER
OPEN FOR EOI    INCOMPLETE EOI    EOI COMPLETED
STATUS       ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
Eagle Downs Coal- General Expression of Interest18 Jun 1912 Jun 20 
This is general EOI for any opportunities that may arise for this project. The project is expecting to do work package specific EOI after the Final Investment Decision (FID) made in mid 2020. The companies expressing interest for this package along with other companies with appropriate notification preference on ICN gateway will be notified when the detailed work packages are listed.