Gosford Hospital Redevelopment



Contact Details


  Ken Raymond
  ICN - NSW
CONTACT EMAIL

  Locations: NSW Australia
  Project Value: $385M
  Project Status: Active
  Project Owner LENDLEASE BUILDING CONTRACTORS PTY LIMITED

Project Details


Gosford Hospital $368M  Redevelopment.

 Once complete, Gosford Hospital will be a totally transformed facility, featuring a new main entrance, a new and expanded emergency department, intensive care and high dependency unit, cardiovascular, maternity and paediatric services, a coronary care unit, medical imaging facilities, psychiatric care ...
SHOW MORE


Work Packages


To submit an expressions of interest, select the icon next to the work package scope you are interested in.

OPEN LISTINGS    AWARDED    CLOSED LISTINGS    OTHER
OPEN FOR EOI    INCOMPLETE EOI    EOI COMPLETED
STATUS       ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
Artworks - Internal 1 Jan 171 Mar 17n/a
Artworks - Internal as required
Balustrading & Handrails 1 Dec 161 Mar 17n/a
Balustrading & Handrails as required
Blockwork 1 Dec 161 Mar 17n/a
Blockwork as required
Curtains & Blinds 1 Dec 161 Mar 17n/a
Curtains & Blinds as required
Door Hardware 1 Dec 161 Mar 17n/a
Door Hardware as required
Doors & Frames 1 Dec 161 Mar 17n/a
Doors & Frames as required
External Features 1 Jan 171 Mar 17n/a
External Features as required
External Works Jan-171 Jan 171 Mar 17n/a
External Works as required
Fencing 1 Jan 171 Mar 17n/a
Fencing as required
Furniture 1 Jan 171 Mar 17n/a
Furniture as required
Glazed Balustrades 1 Dec 161 Mar 17n/a
Glazed Balustrades as required
Hard Landscaping 1 Jan 171 Mar 17n/a
Hard Landscaping as required
Metal Roofing 1 Jan 171 Mar 17n/a
Metal Roofing as required
Roadworks 1 Jan 171 Mar 17n/a
Roadworks as required
Signage 1 Jan 171 Mar 17n/a
Signage as required
Soft Landscaping 1 Jan 171 Mar 17n/a
Soft Landscaping as required
Vinyl / Carpet Install1 Jan 171 Mar 17n/a
Vinyl / Carpet Install as required
Workstations & Screens 1 Dec 161 Mar 17n/a
Workstations & Screens
Shielding Systems Oct-16 1 Oct 161 Dec 17n/a
Shielding Systems as required
Internal Windows1 Oct 161 Dec 16n/a
Internal Windows as required
Membrane Roofing1 Nov 161 Feb 17n/a
Membrane Roofing as required
Metalwork 1 Dec 161 Feb 17n/a
Metalwork as required
Mirrors 1 Oct 161 Dec 16n/a
Mirrors as required
Painting Works 1 Nov 161 Jan 17n/a
Painting Works as required
Racking & Storage 1 Oct 161 Dec 16n/a
Racking & Storage as required
Speedpanel/Plasterboard/Glass Partions /Ceilings1 Oct 161 Dec 16n/a
Speedpanel/Plasterboard/Glass Partions /Ceilings as required
Stone Finishes1 Nov 1615 Jan 17n/a
Stone Finishes as required
Tiling/Screed/Membrane 1 Nov 161 Jan 17n/a
Tiling/Screed/Membrane
Timber Wall Panel/Cladding 1 Oct 161 Dec 16n/a
Timber Wall Panel/Cladding as required

Vinyl/Carpet Supply 1 Oct 161 Dec 16n/a
Vinyl/Carpet Supply as required