KEPCO Bylong Coal Project



Contact Details


  Jerone Bodiam - ICN
  +61 2 9927 3110
 CONTACT EMAIL

  Industry Capability Network
  +61 2 9927 3100
  +61 2 8920 1856
 CONTACT EMAIL

  Locations: NSW Australia
  Project Status: Seeking approvals
  Project Owner KEPCO BYLONG AUSTRALIA PTY LTD

Project Details


KEPCO proposes to develop the Bylong Coal Project, located approximately 55 km north-east of Mudgee and 53 km from Denman in New South Wales, Australia. The purpose is to extract, wash and export coal. The Bylong Coal Project proposes to supply 6.5 million tonnes (ROM) of thermal coal per annum to the export market. The mine will cover an area of approximately 3,000 ha and will include two open-cut mining areas and an underground mining area.

The mine is likely to employ up to 665 people during construction and maintain a workforce of approximately 290 people during operations.

The life of mine is expected to be approximately 25 years, with open-cut operations commencing around year 4 and operation of an underground mine commencing afterwards at around year 7. Coal will be transported from the Project site to the Port of Newcastle via rail, which will require the construction of a dedicated rail loop connecting to the existing Sandy Hollow-Gulgong Line.

SHOW LESS

Work Packages


There are currently no open work packages for this project.
Note: The closing date/s for expressions of interest shown below are subject to change.

OPEN LISTINGS    AWARDED    CLOSED LISTINGS    OTHER
OPEN FOR EOI    INCOMPLETE EOI    EOI COMPLETED
STATUS   EQUIPMENT - OPERATIONS    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
Coal Bins29 Sep 1530 Sep 1930 Sep 19
Loading coal trains.
Load coal waste to trucks.
CPP feed surge bin
Coal Prep Plant (CPP) Excluding Dewatering29 Sep 1530 Sep 1930 Sep 19
Complete CPP Plant, Including CPP primary washing equipment (Mechanical, Electrical, Instrumentation, CPP Surge Bin)
Coal Preparation - Dewatering29 Sep 1530 Sep 1930 Sep 19
Centrifuges, Thickener and Belt Filter Press
Communications equipment20 Jun 1730 Sep 1930 Sep 19
Communications equipment
Continuous miners and bolters29 Sep 1530 Sep 1930 Sep 19
Supply of continuous miners & roof bolters
Conveyor system ( including belt drives motors motor starter panels brakes and structural steel)29 Sep 1530 Sep 1930 Sep 19
Complete surface conveyor systems
including drives, belting,motors and starters brakes and structural steel
Feeder/breakers29 Sep 1530 Sep 1930 Sep 19
Underground coal feeder breakers
Hydraulic and air-complete systems29 Sep 1530 Sep 1930 Sep 19
Complete underground hydraulic and air systems
including pumps and sumps
Load/haul/dumps (LHDs)29 Sep 1530 Sep 1930 Sep 19
Underground Load Haul Dumps
Man transporters29 Sep 1530 Sep 1930 Sep 19
Underground Coal man transporters
Rail Track System29 Sep 1530 Sep 1930 Sep 19
Rail Switching and Signalling Systems.for balloon loop
Raw Coal Feed System29 Sep 1530 Sep 1930 Sep 19
Feed and Crushing Plant.
Shuttle cars29 Sep 1530 Sep 1930 Sep 19
Underground Coal shuttle cars
Stockpile and Reclaim System - Stacker reclaimers29 Sep 1530 Sep 1930 Sep 19
Includes product stockpile structures, coal flow activators and feeders.
Includes dust and fire management.
Substations - Switchgear and Cabling (Underground)29 Sep 1530 Sep 1930 Sep 19
Underground Power - up to 11kv - and Control systems
Substations Switchgear Cables29 Sep 1530 Sep 1930 Sep 19
Supply of HV and LV power to site,including transmission towers and reticulation around site
Underground Coal Longwall Mining System10 Sep 1530 Sep 1930 Sep 19
One (1) only longwall mining system comprising roof supports, shearers, armoured face conveyor, beam stage loader, crusher, bootend, monorail, hydraulic power pack, underground electrical supply
Ventilation facility (Surface fans-Underground fans)29 Sep 1530 Sep 1930 Sep 19
As described
Water reticulation equipment20 Jun 1730 Sep 1930 Sep 19
Water reticulation equipment
STATUS   MISCELLANEOUS    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
Professional services and labour hire23 May 1730 Sep 19 
e.g. environmental services, surveying, security, logistics, labourers
Services or goods not included elsewhere23 May 1730 Sep 19 
Goods and services not included in any other work package
Above-ground Mine Infrastructure23 May 1730 Sep 1930 Sep 19
e.g. concreting, road works, office accommodation, fencing, water reticulation
Civils - Bulk earthworks20 Jun 1730 Sep 1930 Sep 19
Civils - Bulk earthworks
Civils - Dams20 Jun 1730 Sep 1930 Sep 19
Civils - Dams
Civils - Roads20 Jun 1730 Sep 1930 Sep 19
Civils - Bulk earthworks