Pluto LNG Train 2


Project at a glance


WA Australia (Onshore)
FEED
Woodside Energy Ltd

Contact Details


Andie Pfaff
Project Officer
+61 8 9365 7442

On 1 January 2022, Woodside Energy issued Full Notice to Proceed (FNTP) to Bechtel (Western Australia) Pty Ltd and Bechtel International, Inc (Bechtel) for the Pluto Train 2 Project Engineering, Procurement and Construction (EPC) scope of work.


Woodside Energy is Australia's leading natural gas producer, and Bechtel is excited to be working with this key customer to help meet the increasing global demand for LNG as a transitional energy source.


Pluto Train 2 is the expansion of a second LNG train at the existing Pluto LNG onshore facility. Pluto Train 2 will process Scarborough gas and have an LNG capacity of ~5 million tonnes per annum. As part of the construction of Pluto Train 2, additional domestic gas infrastructure will be installed to increase capacity to ~ 225 Terajoules per day.


Bechtel has commenced the full engineering, procurement, construction and commissioning scope to support delivery of the Pluto Train 2 Project, building on the ongoing construction of the temporary Construction Accommodation Village to accommodate the non-local construction workforce at the Gap Ridge Village site in Karratha.


The EPC scope of work for Bechtel includes the construction and commissioning of the second LNG train, domestic gas facilities as well as common utilities, and general facilities at the Pluto LNG Park.

Share this project on:

FB Twitter LinkedIn

Work Package
Documents
Full Scope EOI
Partial Scope EOI
Status
Accordian collapse

Bechtel Australia

Full Scope EOI

Create EOI
Closes: 
29 Apr 2024 (AWST)

Partial Scope EOI

Create EOI
Closes: 
29 Apr 2024 (AWST)
  Open

Full Scope EOI

Create EOI
Closes: 
29 Apr 2024 (AWST)

Partial Scope EOI

Create EOI
Closes: 
29 Apr 2024 (AWST)
  Open

Full Scope EOI

Create EOI
Closes: 
09 May 2024 (AWST)

Partial Scope EOI

Create EOI
Closes: 
09 May 2024 (AWST)
  Open

Full Scope EOI

Partial Scope EOI

  No longer required
AccordianPlus CO2 Absorber

Full Scope EOI

Closed: 
03 Apr 2019 (AWST)

Partial Scope EOI

Closed: 
03 Apr 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
03 Apr 2019 (AWST)

Partial Scope EOI

Closed: 
03 Apr 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
04 Apr 2019 (AWST)

Partial Scope EOI

Closed: 
04 Apr 2019 (AWST)
  Awarded
AccordianPlus Internals for Columns

Full Scope EOI

Closed: 
04 Apr 2019 (AWST)

Partial Scope EOI

Closed: 
04 Apr 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
05 Apr 2019 (AWST)

Partial Scope EOI

Closed: 
05 Apr 2019 (AWST)
  Awarded
AccordianPlus Power Transformers

Full Scope EOI

Closed: 
05 Apr 2019 (AWST)

Partial Scope EOI

Closed: 
05 Apr 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
08 Apr 2019 (AWST)

Partial Scope EOI

Closed: 
08 Apr 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
08 Apr 2019 (AWST)

Partial Scope EOI

Closed: 
08 Apr 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
09 Apr 2019 (AWST)

Partial Scope EOI

Closed: 
09 Apr 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
09 Apr 2019 (AWST)

Partial Scope EOI

Closed: 
09 Apr 2019 (AWST)
  Awarded
AccordianPlus Coalescers

Full Scope EOI

Closed: 
10 Apr 2019 (AWST)

Partial Scope EOI

Closed: 
10 Apr 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
10 Apr 2019 (AWST)

Partial Scope EOI

Closed: 
10 Apr 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
11 Apr 2019 (AWST)

Partial Scope EOI

Closed: 
11 Apr 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
11 Apr 2019 (AWST)

Partial Scope EOI

Closed: 
11 Apr 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
12 Apr 2019 (AWST)

Partial Scope EOI

Closed: 
12 Apr 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
12 Apr 2019 (AWST)

Partial Scope EOI

Closed: 
12 Apr 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
26 Apr 2019 (AWST)

Partial Scope EOI

Closed: 
26 Apr 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
07 May 2019 (AWST)

Partial Scope EOI

Closed: 
07 May 2019 (AWST)
  Awarded
AccordianPlus Air Services

Full Scope EOI

Closed: 
13 Jun 2019 (AWST)

Partial Scope EOI

Closed: 
13 Jun 2019 (AWST)
  Awarded
AccordianPlus Bussing

Full Scope EOI

Closed: 
13 Jun 2019 (AWST)

Partial Scope EOI

Closed: 
13 Jun 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
13 Jun 2019 (AWST)

Partial Scope EOI

Closed: 
13 Jun 2019 (AWST)
  Awarded
AccordianPlus NDE Testing

Full Scope EOI

Closed: 
14 Jun 2019 (AWST)

Partial Scope EOI

Closed: 
14 Jun 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
25 Jun 2019 (AWST)

Partial Scope EOI

Closed: 
25 Jun 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
06 Jul 2019 (AWST)

Partial Scope EOI

Closed: 
06 Jul 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
06 Jul 2019 (AWST)

Partial Scope EOI

Closed: 
06 Jul 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
06 Jul 2019 (AWST)

Partial Scope EOI

Closed: 
06 Jul 2019 (AWST)
  Awarded
AccordianPlus Pump Vertical Sump

Full Scope EOI

Closed: 
06 Jul 2019 (AWST)

Partial Scope EOI

Closed: 
06 Jul 2019 (AWST)
  Awarded
AccordianPlus Electric Heater

Full Scope EOI

Closed: 
16 Jul 2019 (AWST)

Partial Scope EOI

Closed: 
16 Jul 2019 (AWST)
  Awarded
AccordianPlus Ethylene Storage Drums

Full Scope EOI

Closed: 
16 Jul 2019 (AWST)

Partial Scope EOI

Closed: 
16 Jul 2019 (AWST)
  Awarded
AccordianPlus Pig Receiver

Full Scope EOI

Closed: 
16 Jul 2019 (AWST)

Partial Scope EOI

Closed: 
16 Jul 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
16 Jul 2019 (AWST)

Partial Scope EOI

Closed: 
16 Jul 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
16 Jul 2019 (AWST)

Partial Scope EOI

Closed: 
16 Jul 2019 (AWST)
  Awarded
AccordianPlus Tank Shop Fabricated

Full Scope EOI

Closed: 
16 Jul 2019 (AWST)

Partial Scope EOI

Closed: 
16 Jul 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
21 Jul 2019 (AWST)

Partial Scope EOI

Closed: 
21 Jul 2019 (AWST)
  Awarded
AccordianPlus Pressure Relief Valves

Full Scope EOI

Closed: 
21 Jul 2019 (AWST)

Partial Scope EOI

Closed: 
21 Jul 2019 (AWST)
  Awarded
AccordianPlus Pump Centrifugal API

Full Scope EOI

Closed: 
21 Jul 2019 (AWST)

Partial Scope EOI

Closed: 
21 Jul 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
21 Jul 2019 (AWST)

Partial Scope EOI

Closed: 
21 Jul 2019 (AWST)
  Awarded
AccordianPlus Rupture Disks

Full Scope EOI

Closed: 
21 Jul 2019 (AWST)

Partial Scope EOI

Closed: 
21 Jul 2019 (AWST)
  Awarded
AccordianPlus T-Strainers

Full Scope EOI

Closed: 
21 Jul 2019 (AWST)

Partial Scope EOI

Closed: 
21 Jul 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
21 Jul 2019 (AWST)

Partial Scope EOI

Closed: 
21 Jul 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
26 Aug 2019 (AWST)

Partial Scope EOI

Closed: 
26 Aug 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
23 Sep 2019 (AWST)

Partial Scope EOI

Closed: 
23 Sep 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
23 Sep 2019 (AWST)

Partial Scope EOI

Closed: 
23 Sep 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
23 Sep 2019 (AWST)

Partial Scope EOI

Closed: 
23 Sep 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
23 Sep 2019 (AWST)

Partial Scope EOI

Closed: 
23 Sep 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
04 Oct 2019 (AWST)

Partial Scope EOI

Closed: 
04 Oct 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
04 Oct 2019 (AWST)

Partial Scope EOI

Closed: 
04 Oct 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
04 Oct 2019 (AWST)

Partial Scope EOI

Closed: 
04 Oct 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
21 Oct 2019 (AWST)

Partial Scope EOI

Closed: 
21 Oct 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
22 Oct 2019 (AWST)

Partial Scope EOI

Closed: 
22 Oct 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
22 Oct 2019 (AWST)

Partial Scope EOI

Closed: 
22 Oct 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
22 Oct 2019 (AWST)

Partial Scope EOI

Closed: 
22 Oct 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
04 Nov 2019 (AWST)

Partial Scope EOI

Closed: 
04 Nov 2019 (AWST)
  Awarded
AccordianPlus Custody Metering Skid

Full Scope EOI

Closed: 
04 Nov 2019 (AWST)

Partial Scope EOI

Closed: 
04 Nov 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
05 Nov 2019 (AWST)

Partial Scope EOI

Closed: 
05 Nov 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
05 Nov 2019 (AWST)

Partial Scope EOI

Closed: 
05 Nov 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
06 Nov 2019 (AWST)

Partial Scope EOI

Closed: 
06 Nov 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
06 Nov 2019 (AWST)

Partial Scope EOI

Closed: 
06 Nov 2019 (AWST)
  Awarded
AccordianPlus Key Interlock Valves

Full Scope EOI

Closed: 
07 Nov 2019 (AWST)

Partial Scope EOI

Closed: 
07 Nov 2019 (AWST)
  Awarded
AccordianPlus Pipe Support Standard

Full Scope EOI

Closed: 
07 Nov 2019 (AWST)

Partial Scope EOI

Closed: 
07 Nov 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
08 Nov 2019 (AWST)

Partial Scope EOI

Closed: 
08 Nov 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
08 Nov 2019 (AWST)

Partial Scope EOI

Closed: 
08 Nov 2019 (AWST)
  Awarded
AccordianPlus Structural Bolts

Full Scope EOI

Closed: 
11 Nov 2019 (AWST)

Partial Scope EOI

Closed: 
11 Nov 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
12 Nov 2019 (AWST)

Partial Scope EOI

Closed: 
12 Nov 2019 (AWST)
  Awarded
AccordianPlus Instrument Cable

Full Scope EOI

Closed: 
12 Nov 2019 (AWST)

Partial Scope EOI

Closed: 
12 Nov 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
12 Nov 2019 (AWST)

Partial Scope EOI

Closed: 
12 Nov 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
12 Nov 2019 (AWST)

Partial Scope EOI

Closed: 
12 Nov 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
03 Dec 2019 (AWST)

Partial Scope EOI

Closed: 
03 Dec 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
10 Feb 2020 (AWST)

Partial Scope EOI

Closed: 
10 Feb 2020 (AWST)
  Awarded
AccordianPlus Gaskets

Full Scope EOI

Closed: 
06 Apr 2020 (AWST)

Partial Scope EOI

Closed: 
06 Apr 2020 (AWST)
  Awarded
AccordianPlus Monoflange Valves

Full Scope EOI

Closed: 
10 Jun 2021 (AWST)

Partial Scope EOI

Closed: 
10 Jun 2021 (AWST)
  Awarded
AccordianPlus Fire and Gas Detectors

Full Scope EOI

Closed: 
13 Oct 2021 (AWST)

Partial Scope EOI

Closed: 
13 Oct 2021 (AWST)
  Awarded
AccordianPlus Precast Trenches

Full Scope EOI

Closed: 
13 Oct 2021 (AWST)

Partial Scope EOI

Closed: 
13 Oct 2021 (AWST)
  Awarded
AccordianPlus Sample Coolers

Full Scope EOI

Closed: 
13 Oct 2021 (AWST)

Partial Scope EOI

Closed: 
13 Oct 2021 (AWST)
  Awarded

Full Scope EOI

Closed: 
13 Dec 2021 (AWST)

Partial Scope EOI

Closed: 
13 Dec 2021 (AWST)
  Awarded

Full Scope EOI

Closed: 
22 Dec 2021 (AWST)

Partial Scope EOI

Closed: 
22 Dec 2021 (AWST)
  Awarded

Full Scope EOI

Closed: 
17 Jan 2022 (AWST)

Partial Scope EOI

Closed: 
17 Jan 2022 (AWST)
  Awarded

Full Scope EOI

Closed: 
24 Jan 2022 (AWST)

Partial Scope EOI

Closed: 
24 Jan 2022 (AWST)
  Awarded
AccordianPlus Crane Rental

Full Scope EOI

Closed: 
11 Mar 2022 (AWST)

Partial Scope EOI

Closed: 
11 Mar 2022 (AWST)
  Awarded

Full Scope EOI

Closed: 
11 Mar 2022 (AWST)

Partial Scope EOI

Closed: 
11 Mar 2022 (AWST)
  Awarded

Full Scope EOI

Closed: 
11 Mar 2022 (AWST)

Partial Scope EOI

Closed: 
11 Mar 2022 (AWST)
  Awarded

Full Scope EOI

Closed: 
08 Aug 2022 (AWST)

Partial Scope EOI

Closed: 
08 Aug 2022 (AWST)
  Awarded

Full Scope EOI

Closed: 
28 Sep 2022 (AWST)

Partial Scope EOI

Closed: 
28 Sep 2022 (AWST)
  Awarded
AccordianPlus Temporary Telecoms

Full Scope EOI

Closed: 
13 Jun 2019 (AWST)

Partial Scope EOI

Closed: 
13 Jun 2019 (AWST)
  Closed
AccordianPlus Concrete Pumping

Full Scope EOI

Closed: 
14 Jun 2019 (AWST)

Partial Scope EOI

Closed: 
14 Jun 2019 (AWST)
  Closed

Full Scope EOI

Closed: 
14 Jun 2019 (AWST)

Partial Scope EOI

Closed: 
14 Jun 2019 (AWST)
  Closed

Full Scope EOI

Closed: 
14 Jun 2019 (AWST)

Partial Scope EOI

Closed: 
14 Jun 2019 (AWST)
  Closed
AccordianPlus Road Paving

Full Scope EOI

Closed: 
25 Jun 2019 (AWST)

Partial Scope EOI

Closed: 
25 Jun 2019 (AWST)
  Closed

Full Scope EOI

Closed: 
21 Jul 2019 (AWST)

Partial Scope EOI

Closed: 
21 Jul 2019 (AWST)
  Closed

Full Scope EOI

Closed: 
02 Aug 2019 (AWST)

Partial Scope EOI

Closed: 
02 Aug 2019 (AWST)
  Closed

Full Scope EOI

Closed: 
02 Aug 2019 (AWST)

Partial Scope EOI

Closed: 
02 Aug 2019 (AWST)
  Closed

Full Scope EOI

Closed: 
04 Oct 2019 (AWST)

Partial Scope EOI

Closed: 
04 Oct 2019 (AWST)
  Closed

Full Scope EOI

Closed: 
11 Nov 2019 (AWST)

Partial Scope EOI

Closed: 
11 Nov 2019 (AWST)
  Closed

Full Scope EOI

Closed: 
06 Dec 2019 (AWST)

Partial Scope EOI

Closed: 
06 Dec 2019 (AWST)
  Closed

Full Scope EOI

Closed: 
18 Mar 2021 (AWST)

Partial Scope EOI

Closed: 
18 Mar 2021 (AWST)
  Closed

Full Scope EOI

Closed: 
13 Oct 2021 (AWST)

Partial Scope EOI

Closed: 
13 Oct 2021 (AWST)
  Closed
AccordianPlus Bellville Washers

Full Scope EOI

Closed: 
13 Oct 2021 (AWST)

Partial Scope EOI

Closed: 
13 Oct 2021 (AWST)
  Closed
AccordianPlus Supply of Diesel Fuel

Full Scope EOI

Closed: 
07 Jan 2022 (AWST)

Partial Scope EOI

Closed: 
07 Jan 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
17 Jan 2022 (AWST)

Partial Scope EOI

Closed: 
17 Jan 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
17 Jan 2022 (AWST)

Partial Scope EOI

Closed: 
17 Jan 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
17 Jan 2022 (AWST)

Partial Scope EOI

Closed: 
17 Jan 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
24 Jan 2022 (AWST)

Partial Scope EOI

Closed: 
24 Jan 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
24 Jan 2022 (AWST)

Partial Scope EOI

Closed: 
24 Jan 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
24 Jan 2022 (AWST)

Partial Scope EOI

Closed: 
24 Jan 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
31 Jan 2022 (AWST)

Partial Scope EOI

Closed: 
31 Jan 2022 (AWST)
  Closed
AccordianPlus Crane Purchase

Full Scope EOI

Closed: 
31 Jan 2022 (AWST)

Partial Scope EOI

Closed: 
31 Jan 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
31 Jan 2022 (AWST)

Partial Scope EOI

Closed: 
31 Jan 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
31 Jan 2022 (AWST)

Partial Scope EOI

Closed: 
31 Jan 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
31 Jan 2022 (AWST)

Partial Scope EOI

Closed: 
31 Jan 2022 (AWST)
  Closed
AccordianPlus Scaffold

Full Scope EOI

Closed: 
31 Jan 2022 (AWST)

Partial Scope EOI

Closed: 
31 Jan 2022 (AWST)
  Closed
AccordianPlus Shoring and Formwork

Full Scope EOI

Closed: 
31 Jan 2022 (AWST)

Partial Scope EOI

Closed: 
31 Jan 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
31 Jan 2022 (AWST)

Partial Scope EOI

Closed: 
31 Jan 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
31 Jan 2022 (AWST)

Partial Scope EOI

Closed: 
31 Jan 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
01 Mar 2022 (AWST)

Partial Scope EOI

Closed: 
01 Mar 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
11 Mar 2022 (AWST)

Partial Scope EOI

Closed: 
11 Mar 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
11 Mar 2022 (AWST)

Partial Scope EOI

Closed: 
11 Mar 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
15 Apr 2022 (AWST)

Partial Scope EOI

Closed: 
15 Apr 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
17 Jun 2022 (AWST)

Partial Scope EOI

Closed: 
17 Jun 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
25 Jul 2022 (AWST)

Partial Scope EOI

Closed: 
25 Jul 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
02 Aug 2022 (AWST)

Partial Scope EOI

Closed: 
02 Aug 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
03 Aug 2022 (AWST)

Partial Scope EOI

Closed: 
03 Aug 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
26 Aug 2022 (AWST)

Partial Scope EOI

Closed: 
26 Aug 2022 (AWST)
  Closed
AccordianPlus Janitorial Supplies

Full Scope EOI

Closed: 
12 Oct 2022 (AWST)

Partial Scope EOI

Closed: 
12 Oct 2022 (AWST)
  Closed
AccordianPlus Supply of Bottled Gas

Full Scope EOI

Closed: 
26 Oct 2022 (AWST)

Partial Scope EOI

Closed: 
26 Oct 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
26 Oct 2022 (AWST)

Partial Scope EOI

Closed: 
26 Oct 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
26 Oct 2022 (AWST)

Partial Scope EOI

Closed: 
26 Oct 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
25 Nov 2022 (AWST)

Partial Scope EOI

Closed: 
25 Nov 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
23 Jan 2023 (AWST)

Partial Scope EOI

Closed: 
23 Jan 2023 (AWST)
  Closed
AccordianPlus Earth Rod Installation

Full Scope EOI

Closed: 
12 May 2023 (AWST)

Partial Scope EOI

Closed: 
12 May 2023 (AWST)
  Closed

Full Scope EOI

Closed: 
31 May 2023 (AWST)

Partial Scope EOI

Closed: 
31 May 2023 (AWST)
  Closed

Full Scope EOI

Closed: 
06 Sep 2023 (AWST)

Partial Scope EOI

Closed: 
06 Sep 2023 (AWST)
  Closed

Full Scope EOI

Closed: 
30 Nov 2023 (AWST)

Partial Scope EOI

Closed: 
30 Nov 2023 (AWST)
  Closed
AccordianPlus Removable Jacket

Full Scope EOI

Closed: 
14 Mar 2024 (AWST)

Partial Scope EOI

Closed: 
14 Mar 2024 (AWST)
  Closed

Full Scope EOI

Closed: 
02 Apr 2024 (AWST)

Partial Scope EOI

Closed: 
02 Apr 2024 (AWST)
  Closed

Full Scope EOI

Closed: 
12 Apr 2024 (AWST)

Partial Scope EOI

Closed: 
12 Apr 2024 (AWST)
  Closed
Accordian collapse

Woodside

Full Scope EOI

Closed: 
15 Aug 2022 (AWST)

Partial Scope EOI

Closed: 
15 Aug 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
19 Aug 2022 (AWST)

Partial Scope EOI

Closed: 
19 Aug 2022 (AWST)
  Closed
Accordian collapse

DBNGP (WA)

Full Scope EOI

Closed: 
12 Sep 2023 (AWST)

Partial Scope EOI

Closed: 
12 Sep 2023 (AWST)
  Closed
Note: The closing date/s for expressions of interest are subject to change.
PROJECT
WA AUSTRALIA

The North West Shelf (NWS) subsea tieback (SSTB) program is focused on using existing infrastructure to develop reserves from existing and undeveloped NWS Project fields. 

View Project
PROJECT
WA AUSTRALIA

This is the home page for Woodside covering all projects.

View Project
PROJECT
WA AUSTRALIA

Woodside will develop the Scarborough gas resource through new offshore facilities connected by an approximately 430 km pipeline to a brownfield expansion of the existing Pluto LNG onshore facility (Pluto Train 2).


The proposal is to initially develop the gas field with eight subsea, high-rate gas wells, and thirteen wells drilled over the life of the Scarborough field, with all wells tied back to a semi-submersible floating production unit (FPU) moored in 950 m of water close to the Scarborough field.

View Project
PROJECT
WA AUSTRALIA

Woodside is pursuing an opportunity to process up to 3 Mtpa of Scarborough gas via the existing Pluto Train 1. This project is known as the Pluto Train 1 Scarborough Modifications Project and involves modifying the existing Pluto Train 1 facility to enable it to process Scarborough gas.

View Project