Scarborough Project


Project at a glance


WA Australia (Offshore)
Front-end engineering design activities
Woodside Energy Ltd

Contact Details


Raymond Loh
Manager
+61 8 9365 7499

Woodside will develop the Scarborough gas resource through new offshore facilities connected by an approximately 430 km pipeline to a brownfield expansion of the existing Pluto LNG onshore facility (Pluto Train 2).


The proposal is to initially develop the gas field with eight subsea, high-rate gas wells, and thirteen wells drilled over the life of the Scarborough field, with all wells tied back to a semi-submersible floating production unit (FPU) moored in 950 m of water close to the Scarborough field.


The development of Scarborough will provide a boost to Western Australia, growing jobs and bringing work through the supply chain. Woodside is working closely with its key contractors to maximise opportunities for local, regional and WA businesses across the supply chain for Scarborough.


Woodside has engaged with a range of specialist contractors in the offshore, subsea and pipeline sectors to deliver the Scarborough Project, including Subsea Integrated Alliance for the engineering, manufacture, supply and installation of the subsea hardware, umbilicals, risers and flowlines scope, McDermott for the engineering, procurement, construction and delivery of the FPU, Saipem for the coating and installation of the export pipeline and Boskalis for the seabed intervention and shore crossing scope.


In Q4 2021, Woodside announced a final investment decision for the Scarborough Project. Woodside has issued Full Notice to Proceed to key Scarborough contractors.


Contractor Details

McDermott Australia Pty Ltd https://www.mcdermott.com/Suppliers

Subsea Integration Alliance https://www.subseaintegrationalliance.com/contact-us\

Saipem Australia Pty Ltd SaipemProc.Au@saipem.com

Intecsea Pty Ltd http://www.intecsea.com/contact/

Boskalis Australia Pty Ltd https://australia.boskalis.com/contact/head-office-contact-details.html

Share this project on:

FB Twitter LinkedIn

Work Package
Documents
Full Scope EOI
Partial Scope EOI
Status
Accordian collapse

Boskalis

Full Scope EOI

Closed: 
17 Feb 2022 (AWST)

Partial Scope EOI

Closed: 
17 Feb 2022 (AWST)
  Awarded

Full Scope EOI

Closed: 
25 Apr 2022 (AWST)

Partial Scope EOI

Closed: 
25 Apr 2022 (AWST)
  Awarded
AccordianPlus Crane Hire

Full Scope EOI

Closed: 
25 Apr 2022 (AWST)

Partial Scope EOI

Closed: 
25 Apr 2022 (AWST)
  Awarded

Full Scope EOI

Closed: 
30 Apr 2022 (AWST)

Partial Scope EOI

Closed: 
30 Apr 2022 (AWST)
  Awarded

Full Scope EOI

Closed: 
02 May 2022 (AWST)

Partial Scope EOI

Closed: 
02 May 2022 (AWST)
  Awarded

Full Scope EOI

Closed: 
09 May 2022 (AWST)

Partial Scope EOI

Closed: 
09 May 2022 (AWST)
  Awarded
Accordian collapse

McDermott

Full Scope EOI

Closed: 
17 Apr 2019 (AWST)

Partial Scope EOI

Closed: 
17 Apr 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
17 Apr 2019 (AWST)

Partial Scope EOI

Closed: 
17 Apr 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
24 Apr 2019 (AWST)

Partial Scope EOI

Closed: 
24 Apr 2019 (AWST)
  Awarded
AccordianPlus Living Quarters FPU

Full Scope EOI

Closed: 
06 Jun 2019 (AWST)

Partial Scope EOI

Closed: 
06 Jun 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
11 Jun 2019 (AWST)

Partial Scope EOI

Closed: 
11 Jun 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
11 Jun 2019 (AWST)

Partial Scope EOI

Closed: 
11 Jun 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
11 Jun 2019 (AWST)

Partial Scope EOI

Closed: 
11 Jun 2019 (AWST)
  Awarded
AccordianPlus Centrifugal Pumps

Full Scope EOI

Closed: 
10 Jan 2020 (AWST)

Partial Scope EOI

Closed: 
10 Jan 2020 (AWST)
  Awarded
AccordianPlus RO Water Maker

Full Scope EOI

Closed: 
10 Jan 2020 (AWST)

Partial Scope EOI

Closed: 
10 Jan 2020 (AWST)
  Awarded

Full Scope EOI

Closed: 
03 Feb 2020 (AWST)

Partial Scope EOI

Closed: 
03 Feb 2020 (AWST)
  Awarded

Full Scope EOI

Closed: 
03 Feb 2020 (AWST)

Partial Scope EOI

Closed: 
03 Feb 2020 (AWST)
  Awarded
AccordianPlus Flare

Full Scope EOI

Closed: 
13 Feb 2020 (AWST)

Partial Scope EOI

Closed: 
13 Feb 2020 (AWST)
  Awarded
AccordianPlus HV Switchgear

Full Scope EOI

Closed: 
13 Feb 2020 (AWST)

Partial Scope EOI

Closed: 
13 Feb 2020 (AWST)
  Awarded
AccordianPlus Inlet Pig Receiver

Full Scope EOI

Closed: 
13 Feb 2020 (AWST)

Partial Scope EOI

Closed: 
13 Feb 2020 (AWST)
  Awarded
AccordianPlus LV Switchboards

Full Scope EOI

Closed: 
13 Feb 2020 (AWST)

Partial Scope EOI

Closed: 
13 Feb 2020 (AWST)
  Awarded
AccordianPlus Pressure Vessels

Full Scope EOI

Closed: 
13 Feb 2020 (AWST)

Partial Scope EOI

Closed: 
13 Feb 2020 (AWST)
  Awarded

Full Scope EOI

Closed: 
13 Feb 2020 (AWST)

Partial Scope EOI

Closed: 
13 Feb 2020 (AWST)
  Awarded
AccordianPlus Transformers

Full Scope EOI

Closed: 
13 Feb 2020 (AWST)

Partial Scope EOI

Closed: 
13 Feb 2020 (AWST)
  Awarded

Full Scope EOI

Closed: 
27 Feb 2020 (AWST)

Partial Scope EOI

Closed: 
27 Feb 2020 (AWST)
  Awarded

Full Scope EOI

Closed: 
28 Feb 2020 (AWST)

Partial Scope EOI

Closed: 
28 Feb 2020 (AWST)
  Awarded
AccordianPlus Cooling Unit

Full Scope EOI

Closed: 
28 Feb 2020 (AWST)

Partial Scope EOI

Closed: 
28 Feb 2020 (AWST)
  Awarded

Full Scope EOI

Closed: 
01 Mar 2020 (AWST)

Partial Scope EOI

Closed: 
01 Mar 2020 (AWST)
  Awarded

Full Scope EOI

Closed: 
01 Mar 2020 (AWST)

Partial Scope EOI

Closed: 
01 Mar 2020 (AWST)
  Awarded
AccordianPlus Waste Drums

Full Scope EOI

Closed: 
05 Mar 2020 (AWST)

Partial Scope EOI

Closed: 
05 Mar 2020 (AWST)
  Awarded

Full Scope EOI

Closed: 
05 Mar 2020 (AWST)

Partial Scope EOI

Closed: 
05 Mar 2020 (AWST)
  Awarded

Full Scope EOI

Closed: 
06 Mar 2020 (AWST)

Partial Scope EOI

Closed: 
06 Mar 2020 (AWST)
  Awarded
AccordianPlus API 6D Ball Valves

Full Scope EOI

Closed: 
09 Mar 2020 (AWST)

Partial Scope EOI

Closed: 
09 Mar 2020 (AWST)
  Awarded
AccordianPlus Free Fall Life Boats

Full Scope EOI

Closed: 
09 Mar 2020 (AWST)

Partial Scope EOI

Closed: 
09 Mar 2020 (AWST)
  Awarded
AccordianPlus Control Valves

Full Scope EOI

Closed: 
20 Apr 2020 (AWST)

Partial Scope EOI

Closed: 
20 Apr 2020 (AWST)
  Awarded

Full Scope EOI

Closed: 
20 Apr 2020 (AWST)

Partial Scope EOI

Closed: 
20 Apr 2020 (AWST)
  Awarded

Full Scope EOI

Closed: 
20 Apr 2020 (AWST)

Partial Scope EOI

Closed: 
20 Apr 2020 (AWST)
  Awarded

Full Scope EOI

Closed: 
04 May 2020 (AWST)

Partial Scope EOI

Closed: 
04 May 2020 (AWST)
  Awarded

Full Scope EOI

Closed: 
04 May 2020 (AWST)

Partial Scope EOI

Closed: 
04 May 2020 (AWST)
  Awarded
AccordianPlus Mooring Chain

Full Scope EOI

Closed: 
04 May 2020 (AWST)

Partial Scope EOI

Closed: 
04 May 2020 (AWST)
  Awarded
AccordianPlus Leg Mating Unit (LMU)

Full Scope EOI

Closed: 
23 Feb 2021 (AWST)

Partial Scope EOI

Closed: 
23 Feb 2021 (AWST)
  Awarded
AccordianPlus AC UPS

Full Scope EOI

Closed: 
18 Aug 2021 (AWST)

Partial Scope EOI

Closed: 
18 Aug 2021 (AWST)
  Awarded

Full Scope EOI

Closed: 
05 Oct 2021 (AWST)

Partial Scope EOI

Closed: 
05 Oct 2021 (AWST)
  Awarded

Full Scope EOI

Closed: 
05 Oct 2021 (AWST)

Partial Scope EOI

Closed: 
05 Oct 2021 (AWST)
  Awarded

Full Scope EOI

Closed: 
05 Oct 2021 (AWST)

Partial Scope EOI

Closed: 
05 Oct 2021 (AWST)
  Awarded

Full Scope EOI

Closed: 
05 Oct 2021 (AWST)

Partial Scope EOI

Closed: 
05 Oct 2021 (AWST)
  Awarded
AccordianPlus Fire and Gas Devices

Full Scope EOI

Closed: 
12 Oct 2021 (AWST)

Partial Scope EOI

Closed: 
12 Oct 2021 (AWST)
  Awarded

Full Scope EOI

Closed: 
29 Oct 2021 (AWST)

Partial Scope EOI

Closed: 
29 Oct 2021 (AWST)
  Awarded

Full Scope EOI

Closed: 
29 Oct 2021 (AWST)

Partial Scope EOI

Closed: 
29 Oct 2021 (AWST)
  Awarded
AccordianPlus Monoblock Valves

Full Scope EOI

Closed: 
29 Oct 2021 (AWST)

Partial Scope EOI

Closed: 
29 Oct 2021 (AWST)
  Awarded
AccordianPlus VESDA System

Full Scope EOI

Closed: 
29 Oct 2021 (AWST)

Partial Scope EOI

Closed: 
29 Oct 2021 (AWST)
  Awarded
AccordianPlus Modular Ball Valves

Full Scope EOI

Closed: 
09 Mar 2020 (AWST)

Partial Scope EOI

Closed: 
09 Mar 2020 (AWST)
  Closed

Full Scope EOI

Closed: 
13 Mar 2020 (AWST)

Partial Scope EOI

Closed: 
13 Mar 2020 (AWST)
  Closed
AccordianPlus Sewage Treatment Unit

Full Scope EOI

Closed: 
01 May 2020 (AWST)

Partial Scope EOI

Closed: 
01 May 2020 (AWST)
  Closed

Full Scope EOI

Closed: 
05 Oct 2021 (AWST)

Partial Scope EOI

Closed: 
05 Oct 2021 (AWST)
  Closed
Accordian collapse

Saipem

Full Scope EOI

Closed: 
01 Jul 2021 (AWST)

Partial Scope EOI

Closed: 
01 Jul 2021 (AWST)
  Awarded

Full Scope EOI

Closed: 
13 Oct 2022 (AWST)

Partial Scope EOI

Closed: 
13 Oct 2022 (AWST)
  Awarded

Full Scope EOI

Closed: 
09 Dec 2022 (AWST)

Partial Scope EOI

Closed: 
09 Dec 2022 (AWST)
  Awarded

Full Scope EOI

Closed: 
11 Apr 2023 (AWST)

Partial Scope EOI

Closed: 
11 Apr 2023 (AWST)
  Awarded

Full Scope EOI

Closed: 
14 Apr 2023 (AWST)

Partial Scope EOI

Closed: 
14 Apr 2023 (AWST)
  Awarded

Full Scope EOI

Closed: 
19 Apr 2023 (AWST)

Partial Scope EOI

Closed: 
19 Apr 2023 (AWST)
  Awarded
AccordianPlus Bunker Fuel Supply

Full Scope EOI

Closed: 
24 Apr 2023 (AWST)

Partial Scope EOI

Closed: 
24 Apr 2023 (AWST)
  Awarded

Full Scope EOI

Closed: 
24 Apr 2023 (AWST)

Partial Scope EOI

Closed: 
24 Apr 2023 (AWST)
  Awarded

Full Scope EOI

Closed: 
26 Apr 2023 (AWST)

Partial Scope EOI

Closed: 
26 Apr 2023 (AWST)
  Awarded

Full Scope EOI

Closed: 
26 Apr 2023 (AWST)

Partial Scope EOI

Closed: 
26 Apr 2023 (AWST)
  Awarded

Full Scope EOI

Closed: 
27 Apr 2023 (AWST)

Partial Scope EOI

Closed: 
27 Apr 2023 (AWST)
  Awarded

Full Scope EOI

Closed: 
15 May 2023 (AWST)

Partial Scope EOI

Closed: 
15 May 2023 (AWST)
  Awarded

Full Scope EOI

Closed: 
22 May 2023 (AWST)

Partial Scope EOI

Closed: 
22 May 2023 (AWST)
  Awarded

Full Scope EOI

Closed: 
22 May 2023 (AWST)

Partial Scope EOI

Closed: 
22 May 2023 (AWST)
  Awarded

Full Scope EOI

Closed: 
05 Jun 2023 (AWST)

Partial Scope EOI

Closed: 
05 Jun 2023 (AWST)
  Awarded

Full Scope EOI

Closed: 
10 Jul 2023 (AWST)

Partial Scope EOI

Closed: 
10 Jul 2023 (AWST)
  Awarded
Accordian collapse

Subsea Integration Alliance

Full Scope EOI

Closed: 
22 Nov 2019 (AWST)

Partial Scope EOI

Closed: 
22 Nov 2019 (AWST)
  Awarded

Full Scope EOI

Closed: 
09 Jun 2021 (AWST)

Partial Scope EOI

Closed: 
09 Jun 2021 (AWST)
  Awarded

Full Scope EOI

Closed: 
16 Jun 2021 (AWST)

Partial Scope EOI

Closed: 
16 Jun 2021 (AWST)
  Awarded

Full Scope EOI

Closed: 
16 Jun 2021 (AWST)

Partial Scope EOI

Closed: 
16 Jun 2021 (AWST)
  Awarded
AccordianPlus Line Pipe Coating

Full Scope EOI

Closed: 
22 Jun 2021 (AWST)

Partial Scope EOI

Closed: 
22 Jun 2021 (AWST)
  Awarded
AccordianPlus Line Pipe Supply

Full Scope EOI

Closed: 
22 Jun 2021 (AWST)

Partial Scope EOI

Closed: 
22 Jun 2021 (AWST)
  Awarded
AccordianPlus Pull-In System

Full Scope EOI

Closed: 
18 Oct 2021 (AWST)

Partial Scope EOI

Closed: 
18 Oct 2021 (AWST)
  Awarded

Full Scope EOI

Closed: 
16 Dec 2021 (AWST)

Partial Scope EOI

Closed: 
16 Dec 2021 (AWST)
  Awarded
AccordianPlus X Trees Installation

Full Scope EOI

Closed: 
27 Dec 2019 (AWST)

Partial Scope EOI

Closed: 
27 Dec 2019 (AWST)
  Closed

Full Scope EOI

Closed: 
09 Jun 2021 (AWST)

Partial Scope EOI

Closed: 
09 Jun 2021 (AWST)
  Closed
AccordianPlus Precommissioning

Full Scope EOI

Closed: 
16 Aug 2022 (AWST)

Partial Scope EOI

Closed: 
16 Aug 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
16 Dec 2022 (AWST)

Partial Scope EOI

Closed: 
16 Dec 2022 (AWST)
  Closed
AccordianPlus Chartered Vessels

Full Scope EOI

Closed: 
27 Jul 2023 (AWST)

Partial Scope EOI

Closed: 
27 Jul 2023 (AWST)
  Closed

Full Scope EOI

Closed: 
14 Sep 2023 (AWST)

Partial Scope EOI

Closed: 
14 Sep 2023 (AWST)
  Closed

Full Scope EOI

Closed: 
25 Sep 2023 (AWST)

Partial Scope EOI

Closed: 
25 Sep 2023 (AWST)
  Closed
AccordianPlus Tugs and Barges

Full Scope EOI

Closed: 
25 Mar 2024 (AWST)

Partial Scope EOI

Closed: 
25 Mar 2024 (AWST)
  Closed
Accordian collapse

Woodside

Full Scope EOI

Closed: 
01 Dec 2021 (AWST)

Partial Scope EOI

Closed: 
01 Dec 2021 (AWST)
  Awarded
AccordianPlus Subsea Flowlines

Full Scope EOI

Closed: 
19 May 2022 (AWST)

Partial Scope EOI

Closed: 
19 May 2022 (AWST)
  Awarded

Full Scope EOI

Closed: 
01 Aug 2022 (AWST)

Partial Scope EOI

Closed: 
01 Aug 2022 (AWST)
  Awarded

Full Scope EOI

Closed: 
02 Aug 2021 (AWST)

Partial Scope EOI

Closed: 
02 Aug 2021 (AWST)
  Closed

Full Scope EOI

Closed: 
06 May 2022 (AWST)

Partial Scope EOI

Closed: 
06 May 2022 (AWST)
  Closed
AccordianPlus Xmas Tree Installation

Full Scope EOI

Closed: 
25 Jul 2022 (AWST)

Partial Scope EOI

Closed: 
25 Jul 2022 (AWST)
  Closed

Full Scope EOI

Closed: 
16 Nov 2023 (AWST)

Partial Scope EOI

Closed: 
16 Nov 2023 (AWST)
  Closed
Note: The closing date/s for expressions of interest are subject to change.
PROJECT
WA AUSTRALIA

The North West Shelf (NWS) subsea tieback (SSTB) program is focused on using existing infrastructure to develop reserves from existing and undeveloped NWS Project fields. 

View Project
PROJECT
WA AUSTRALIA

This is the home page for Woodside covering all projects.

View Project
PROJECT
WA AUSTRALIA

On 1 January 2022, Woodside Energy issued Full Notice to Proceed (FNTP) to Bechtel (Western Australia) Pty Ltd and Bechtel International, Inc (Bechtel) for the Pluto Train 2 Project Engineering, Procurement and Construction (EPC) scope of work.

View Project
PROJECT
WA AUSTRALIA

Woodside is pursuing an opportunity to process up to 3 Mtpa of Scarborough gas via the existing Pluto Train 1. This project is known as the Pluto Train 1 Scarborough Modifications Project and involves modifying the existing Pluto Train 1 facility to enable it to process Scarborough gas.

View Project