State Square Underground Carpark



Contact Details


  David Royle
  (08) 8922 9422
 CONTACT EMAIL

  Locations: NT Australia
  Project Value: $19 Million
  Project Status: Construction commenced August 2018, completion in August 2019
  Project Owner TOMAZOS GROUP PTY LTD

Project Details


Tomazos Group has been awarded the Northern Territory Government's design, development and construction of State Square Underground Carpark. Tomazos Group have engaged DTA Contractors to provide project management services for this project. 

The key features of the project include:

  • Three storeys underground carpark
  • 450 spaces car park including 6 electric car charging stations
  • Cyclone shelter for 600 people including amenities
  • Automated parking system 
  • Bike Store and End of Trip Facilities

All Subcontractors and Suppliers wishing to provide an Expression of Interest (EOI) for any of the available packages for the State Square Underground Carpark Project must comply with the Work Health & Safety (National Uniform Legislation) Act 2011 and the Work Health & Safety (National Uniform Legislation) Regulations and the Building Code 2016. 

In addition, Subcontractors must be Contractor Accreditation Limited (CAL) accredited for works priced at $100,000 + GST and above.

Finally, all Subcontractors must provide copies of their current workers compensation and public liability insurance certificates of currency, with the EOI.

You will be prompted to provide this information during the EOI process for relevant packages. To be kept up-to-date on project progressions, please register against the General Updates package below. 

SHOW LESS

Work Packages


To submit an expression of interest, select the icon next to the work package scope you are interested in.

OPEN LISTINGS    AWARDED    CLOSED LISTINGS    OTHER
OPEN FOR EOI    INCOMPLETE EOI    EOI COMPLETED
STATUS   GENERAL    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
State Square Underground Carpark - General updates31 Aug 181 Aug 19 
Express interest to receive updates on project progression
STATUS   PACKAGES    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
Concrete Place and finish31 Aug 1829 Sep 18 
Concrete Place and finish
Concrete Pumping31 Aug 1829 Sep 18 
Concrete Pumping
Concrete Supply31 Aug 1829 Sep 18 
Concrete Supply
Electrical Services31 Aug 1829 Sep 18 
Electrical Services
Fire protection Services31 Aug 1829 Sep 18 
Fire protection Services
Formwork3 Sep 1829 Sep 18 
Formwork
Hydraulics Services31 Aug 1829 Sep 18 
Hydraulics Services
Mechanical services31 Aug 1829 Sep 18 
Mechanical services
Mobile Crane31 Aug 1829 Sep 18 
Mobile Crane
Precast concrete31 Aug 1829 Sep 18 
Precast concrete
Reinforcing Fixing31 Aug 1829 Sep 18 
Reinforcing Fixing
Reinforcing Steel Supply31 Aug 1829 Sep 18 
Reinforcing Steel Supply
Shotcrete/Rock Anchors10 Sep 1829 Sep 18 
Shotcrete/Rock Anchors
Aluminium Louvre panels and Screening31 Aug 1831 Oct 18 
Aluminium Louvre panels and Screening
Bike Store31 Aug 1831 Oct 18 
Bike Store
CCTV installation31 Aug 1831 Oct 18 
CCTV installation
Cladding and Lining31 Aug 1831 Oct 18 
Cladding and Lining
Door Hardware supply and install31 Aug 1831 Oct 18 
Door Hardware supply and install
Doors and Frames31 Aug 1831 Oct 18 
Doors and Frames
Floor surface treatment31 Aug 1831 Oct 18 
Floor surface treatment
Generator supply and install 31 Aug 1831 Oct 18 
Generator supply and install
Glazing works31 Aug 1831 Oct 18 
Glazing works
Joinery and Fixtures31 Aug 1831 Oct 18 
Joinery and Fixtures
Landscaping31 Aug 1831 Oct 18 
Landscaping
Line Marking31 Aug 1831 Oct 18 
Line Marking
Metal Works31 Aug 1831 Oct 18 
Metal Works
Painting31 Aug 1831 Oct 18 
Painting
Roller Shutters31 Aug 1831 Oct 18 
Roller Shutters
Roofing31 Aug 1831 Oct 18 
Roofing
Structural Steel31 Aug 1831 Oct 18 
Structural Steel
Supply and Install of Solar Panels 13 Sep 1831 Oct 18 
Supply and Install of Solar Panels
Suspended Ceiling31 Aug 1831 Oct 18 
Suspended Ceiling
Tiling31 Aug 1831 Oct 18 
Tiling
Toilet Partitions31 Aug 1831 Oct 18 
Toilet Partitions
Water Proofing31 Aug 1831 Oct 18 
Water Proofing