Barossa Offshore Project FPSO EPCI (MODEC)



Contact Details


  David Royle
  +61 8 8922 9422
 CONTACT EMAIL

  Chan Lay Cheng
  +65 6496 4255
 CONTACT EMAIL

  Theophilus Tan
  +65 6496 2603
 CONTACT EMAIL

  Locations: NT Australia (Offshore)
  Project Value: > AUD $500 Million
  Project Status: FEED
  Project Owner CONOCOPHILLIPS AUSTRALIA BAROSSA PTY LTD

Project Details



About MODEC

MODEC provides complete solutions for the offshore Oil & Gas industry including Engineering, Construction and Operation Services for floating Oil & Gas production systems including FPSOs, FSOs, TLPs and Production Semisubmersibles.

MODEC is committed to supporting the ConocoPhillips’ Australian Industry Participation (AIP) Plan to ensure all Suppliers are given a Full, Fair and Reasonable  Opportunity to participate in the development of the ConocoPhillips’ Barossa Project.  

MODEC will comply with all the requirements as stated in the ConocoPhillips’ AIP Plan and the Australian Jobs Act 2013 throughout the project and for all future Projects in Australia.


About the Project

Barossa is an offshore gas and light condensate project being progressed by the Barossa Joint Venture comprising ConocoPhillips Australia Barossa Pty Ltd as Operator (ConocoPhillips Australia), Santos Offshore Pty Ltd and SK E&S Australia Pty Ltd.

MODEC was awarded a Front-End Engineering Design (FEED) contract of the Barossa FPSO in June 2018 and has now been selected as the turnkey contractor based upon its successful performance and deliverables of the FEED contract.

Further details on the Project and associated opportunities can be found at: BarossaOffshore.icn.org.au

For clarity, submission of an EoI through the ICN Gateway website does not place any obligation upon MODEC to accept or grant award of the Contract.

Further details of MODEC are available at http://www.modec.com


MODEC Pre-requisite Questionnaire for EOI

As part of submitting EOI on specific packages the supplier is to provide responses to a questionnaire found below which will provide a first pass screening of MODEC's general requirements.

This questionnaire is available below in the Project Documents section.


FPSO - Turret Mooring System (SOFEC)

MODEC has awarded to SOFEC, Inc. a subcontract to supply the Turret Mooring System for the Barossa FPSO project. Please refer to the packages listed below under the SOFEC – Turret Mooring System heading to register interest.


SOFEC Contact Details:

Mr James H Hayden

Project Contracts Manager

E: James.Hayden@sofec.com


FPSO – Hull (DSIC)

MODEC has awarded to Dalian Shipbuilding Industry Co., Ltd. (DSIC) a subcontract to supply the Hull for the Barossa FPSO project. Please refer to the packages listed below under the DSIC - FPSO Hull heading to register interest.


DSIC Contact Details:

Mr Chen Ke

Procurement Manager

E: chenke@dsic.cn


SHOW LESS

Associated Opportunities


SHOW MORE

Project Documents


Project Documents

  ▲ CONTRACT
General Terms and Conditions (P-1)
List of Banned Items (Q-3)
SHOW LESS

Work Packages


To submit an expression of interest, select the icon next to the work package scope you are interested in.
Note: The closing date/s for expressions of interest shown below are subject to change.

OPEN LISTINGS    AWARDED    CLOSED LISTINGS    OTHER
OPEN FOR EOI    INCOMPLETE EOI    EOI COMPLETED
STATUS   CURRENT OPPORTUNITIES    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
0482-MI20-44PO-9950 Deluge Valve Package24 Jan 202021 Feb 202030 Jun 2020
The deluge systems shall be activated automatically upon confirmed fire in the zone where the fire is detected as well as in the adjacent modules with common boundary.
Firewater deluge systems from fire water ring main shall be provided for the turret and topside process areas.
The use of foam from low expansion foam package, with the firewater deluge systems for the turret and topside process systems coverage are assessed based on the type of fire (pool fire or jet fire), process decks chosen (solid versus grated) and other consideration.
0482-MI20-50PO-6700 Metering System31 Jan 202028 Feb 202030 Sep 2020
Design, engineering, manufacture, supply, inspection testing, painting, packing forwarding, & spare parts for construction/ commissioning, mandatory spares, two years operational & maintenance spares, special tools & tackles, transportation & documentation of the Metering System and its accessories required for the Floating, Production, Storage and Offloading Units (FPSO)
0482-MI20-50PO-9920 Control Valves31 Jan 202028 Feb 202030 Jun 2020
The minimum requirements for the design, engineering, manufacture, supply, inspection testing, painting, packing forwarding, & spare parts for construction/ commissioning, mandatory spares, two years operational & maintenance spares, special tools & tackles, transportation & documentation of the Control valves and its accessories required for the Floating, Production, Storage and Offloading Units (FPSO) to be operating in the concession areas related to the Barossa Field.
0482-MI20-94PO-4230 Electrochlorinator Package05 Feb 202004 Mar 202030 Jun 2020
The purpose of Electro-chlorinator Package is to generate the Ionized chlorine and injected into the Seawater System and FWD fire pump sea chest to control microbial growth.
The Electrochlorinator uses an electrolytic cell to generate hypochlorite (NaOCl) from the NaCl contained within a small seawater stream. The hypochlorite shall be self-cleaning type. Hydrogen is generated as a byproduct of this reaction and is greatly diluted with air blowers and vented to a safe location. Hypochlorite generation and injection into the sea water stream shall be included with provision for redundancy.
0482-SC001 Sub-contract Scope for EEHA Verification and compliance11 Feb 202010 Mar 202030 Sep 2020
Management of all EEHA tasks in Compliance to the project EEHA Compliance Audit Plan.
Align with all the responsibilities and tasks from the EEHA Compliance Audit Plan.
Review Cable Gland Management Plan and implement at fabrication yards and ship yards.
0482-MI20-50PO-9900 Field Transmitters - PT PDT LT TT FT13 Feb 202012 Mar 202031 Mar 2020
The minimum requirements for the design, engineering, manufacture, supply, inspection testing, painting, packing forwarding, and spare parts for construction/ commissioning, mandatory spares, two years operational and maintenance spares, special tools and tackles, transportation and documentation of the FIELD TRANSMITTERS - PT/PDT/LT/TT/FT and its accessories required for the Floating, Production, Storage and Offloading Units (FPSO) to be operating in the concession areas related to the Barossa Field.
0482-MI20-50PO-9923 Pressure Safety Relief Valves13 Feb 202012 Mar 202030 Sep 2020
The minimum requirements for the design, engineering, manufacture, supply, inspection testing, painting, packing forwarding, and spare parts for construction/ commissioning, mandatory spares, two years operational and maintenance spares, special tools and tackles, transportation and documentation of the PRESSURE SAFETY RELIEF VALVES and its accessories required for the Floating, Production, Storage and Offloading Units (FPSO) to be operating in the concession areas related to the Barossa Field.
0482-MI20-50PO-9928 Shutdown Blowdown and On Off Valves13 Feb 202012 Mar 202030 Sep 2020
The minimum requirements for the design, engineering, manufacture, supply, inspection testing, painting, packing forwarding, & spare parts for construction/ commissioning, mandatory spares, two years operational & maintenance spares, special tools & tackles, transportation & documentation of the SHUTDOWN, BLOWDOWN & ON/OFF VALVES and its accessories required for the Floating, Production, Storage and Offloading Units (FPSO) to be operating in the concession areas related to the Barossa Field.
0482-MI20-50PO-9940 Flow Element (Orifice RO Venturi)13 Feb 202012 Mar 202030 Sep 2020
The minimum requirements for the design, engineering, manufacture, supply, inspection testing, painting, packing forwarding, and spare parts for construction and commissioning, mandatory spares, two years operational and maintenance spares, special tools and tackles, transportation and documentation of the FLOW ELEMENT (Orifice, RO, Venturi) and its accessories required for the Floating, Production, Storage and Offloading Units (FPSO) to be operating in the concession areas related to the Barossa Field.
0428-MI20-36PO-8205 Mechanical Ventilation Fans02 Jan 202030 Jan 202030 Jun 2020
The mechanical ventilation fans shall be designed to the following features but not limited to:
. All fans shall be suitable for offshore marine environment.
. Fan noise limits to be in accordance with good practice as per NOPSEMA guidance.
. All fans shall be provided suitable for duct connection, or constructed for direct bulkhead mounting with associated inlets, outlets, and dampers. All fans and motors shall be provided with earth bosses for earth bonding.
. Centrifugal fans are to be supported on anti-vibration mountings.
. Centrifugal fans not mounted on skids in run / standby arrangement shall have flexible connections on discharge outlets.
. Axial fans mounted on skids in run/ standby arrangement shall have flange connections on inlets and discharge outlets.
. Fans shall be designed and constructed in accordance with ISO 15138.
. Fan shaft and impeller critical speeds shall be at least 20% in excess of the recommended maximum operating speed. Fans shall be selected to give a margin for adjustment of +10% performances without reaching critical shaft or impeller speeds.
. Fans shall have non stall and non- overloading characteristics and operate without reverse flow.
0482-MI20-34PO-4205 Seawater Lift Hose and Handling System03 Jan 202030 Jan 202030 Jun 2020
The seawater for the water injection shall be lifted from at least 75 meters below the ship's base line using suction hoses. Seawater lift hoses shall be installed on the starboard side shell within reach of deck crane of the FPSO. The seawater lift hose system shall be designed with a full detailed global static, dynamic and localized analysis using either Flexcom-3D, Flexan-F, Orcaflex or Flex Riser. Due to the depths at which seawater shall be taken, it will be necessary for the hose to withstand drag forces and bending moments.
0482-MI20-34PO-5010 Fast Rescue/ Work Boat and Davit02 Jan 202030 Jan 202030 Jun 2020
One (1) set of fast rescue boat with launching and recovery davit system is to be provided and installed on the starboard side of FPSO main deck aft area. The fast rescue boat also shall be used for Man Overboard rescue.
0482-MI20-34PO-7100 Tandem Mooring and Floating System20 Jan 202007 Feb 202030 Jun 2020
Primary means of condensate offloading shall be via tandem mooring and floating hose system located on the stern of the FPSO using OCIMF Tandem Mooring and Offloading Guidelines ship to ship transfer methods. The transfer hose shall reach the midship manifold of a standard Aframax offloading tanker.
0482-MI20-36PO-8200 HVAC System for Accommodation13 Dec 201913 Jan 202030 Jun 2020
A central HVAC system shall be designed for the FPSO accommodation block which accommodates a permanent crew of 140 personnel. Dedicated package air conditioning units are to be provided for control rooms, muster area, galley, engine room workshop, battery rooms, etc.
0482-MI20-42PO-7400 Hydraulic Valve Remote Control System08 Jan 202005 Feb 202030 Jun 2020
Scope of supply for hydraulic valve remote control system shall include hydraulic
power unit (HPU), mimic panel, control boxes, solenoid valves deck boxes,
portable/stationary hand pumps, etc., suitable for approximately 150 sets of
hydraulic valves for continuous operation. The system consists of centralized and
remote operation of all marine system hydraulic valves installed on main deck,
and in tanks. The package shall be offered with ABS Class certification.
0482-MI20-44PO-4460 Fresh Water Generator13 Dec 201913 Jan 202030 Jun 2020
Freshwater generators are Vacuum Vapor Pressure type by Electric Heating, discharged head approx. 40 meters., and shall produce fresh water for hull part and topside users.
0482-MI20-44PO-7205 Inert Gas System04 Dec 201914 Dec 201930 Jun 2020
The package will consist of a scrubber with an outside venturi section equipped with an adjustable venturi ensuring an optimal soot extraction of all the different grades of soot particles during all running conditions.
0482-MI20-60PO-6030 Marine Switchboard Package11 Dec 201908 Jan 202030 Jun 2020
The Marine Switchboards Package shall include HV & LV switchboards which will be located in marine side of the FPSO. Ambient temperature for marine shall be considered as 40 Deg.C.
0482-MI20-60PO-6050 Power Transformer11 Dec 201908 Jan 202030 Jun 2020
The Power Transformer Package shall include oil type and dry-type transformers. The outdoor oil type transformers will be located in on the E-House roof top (safe area) of the FPSO and indoor dry type transformers shall be located in marine side TR room of the FPSO.
0482-MI20-60PO-9900 UPS System11 Dec 201908 Jan 202030 Jun 2020
Supply of UPS System
Please see scope of work for additional information.
0482-MI20-94PO-1400 Produced Water Treatment Package13 Dec 201913 Jan 202030 Jun 2020
Produced Water Treatment Equipment shall be designed to handle 20,000 bpd throughput of max. oily water content of 2000 mg/L and Hg content of 20 ppbw of incoming oily water stream.
See Scope of work for addational information
0482-MI20-94PO-1480 Produced Water Tertiary Treatment13 Dec 201913 Jan 202030 Jun 2020
Tertiary Produced Water Treatment System shall be designed to handle 20,000 bpd throughput of oily water content of 30 mg/L and Hg content of 10 ppbw from upstream Primary and Secondary Produced Water Treatment System.
See scope of work for addational information
0482-MI20-94PO-2900 Mercury Removal Solid Bed04 Dec 201914 Dec 201930 Jun 2020
The purpose of the Gas Mercury Removal System (or Gas Mercury Remove Unit, i.e., MRU) is to remove mercury from the gas stream to meet the export gas specification: Mercury Content to be less than 10 g/Nm3.
Please see scope of work for more information.
0482-MI20-94PO-4120 Sea Water Lift Pump Deepwell13 Dec 201913 Jan 202030 Jun 2020
The seawater is lifted from a water depth of about 70 meters below the surface. The Seawater System provides raw seawater with the required filtration to meet the FPSO heat reject demands including heating medium cooling and the cooling required for the Generator Steam Condenser. Ionized chlorine is injected at the inlet of the seawater lift pumps, to avoid marine growth.
0482-MI20-94PO-9960 Oil Production Separator and EOT05 Dec 201915 Dec 201930 Jun 2020
The well stream is routed to the FPSO via individual subsea manifolds and risers for the gas/condensate production. The inlet production stream from the Production Manifold is directed to the Production Separator. The Production Manifold and the Production Separator can be operated at High Pressure (HP) mode in early field life and Low Pressure (LP) Mode in late field life. The inlet production stream is separated in the Production Separator for bulk gas / liquid separation. The separated liquids from the Production Separator are further treated at lower operating pressures, enabling stabilization of the condensate before directing it to condensate storage in the hull.
0482-MI20-94PO-9966 Filters and Coalescers17 Dec 201915 Jan 202030 Jun 2020
The Filters and Coalescers of this package are components of the following systems of the FPSO:
. Gas Mercury Removal System
. CO2 Removal System and Permeate Compression System
. Condensate Separation System
. MEG Separation System
. Fuel Gas System
. Heating Medium System
. Cooling Medium System
. Steam Boiler System
0482-MI20-34PO-5000 Free-Fall Lifeboats and Davits13 Dec 201910 Jan 202030 Sep 2020
Three (3) sets of TEMPSC free-fall lifeboats with launching appliances are to be provided and installed on the starboard aft of the FPSO.
0482-MI20-34PO-7130 Offloading Hose13 Dec 201910 Jan 202030 Sep 2020
The offloading hose is the primary means of condensate offloading from the stern of the FPSO to the midship manifold of a standard Aframax offloading tanker.
0482-MI20-34PO-8540 MATERIAL HANDLING EQUIPMENT (Provision Crane)13 Dec 201910 Jan 202030 Sep 2020
The provision crane is for transferring of materials and equipment to / from the supply vessel. It is located at port aft of the FPSO, adjacent to the accommodation block.
0482-MI20-94PO-9975 Electric Heaters17 Dec 201915 Jan 202030 Sep 2020
The electric heaters are components of the Fuel Gas System which is part of the Utility Systems of the FPSO. There are three (3) units of electric heaters under this package.
0482-MI20-55PO-6315 Intrusion Detection and Security CCTV System10 Jan 202010 Feb 202031 Dec 2021
The FPSO shall have a IP based CCTV system installed to allow the remote monitoring of key areas of the facility, including but not limited to, community areas in accommodation, operational restricted areas, Heli Reception, muster points, offtake station, and helideck. Consideration shall be given to security aspects of the vessel such as; fore and aft; and critical pathways on deck towards the superstructure entries.
STATUS   DSIC - FPSO HULL    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
AIP-DSIC-009 Cable Package24 Jan 202021 Feb 202030 Jun 2020
All cables for marine part including HV cables, LV cables, LAN cable & data bus cable.
AIP-DSIC-002 Sacrificial Anodes08 Jan 202022 Jan 202031 Mar 2020
Sacrificial anodes are to be fitted in water ballast tanks, condensate tanks, slop tanks, produced water tanks, sea chests, shipside caissons and internal turret moonpool according to the following design condition and MODEC/COP's practice/standard.
AIP-DSIC-006 Cu-Ni Pipe Fittings and Flanges20 Jan 202018 Feb 202030 Jun 2020
The purpose of the Cu-Ni Pipe, Fittings and Flanges is used for Fire Water System, Low Expansion Foam System and Helideck Foam Fire Fighting System
AIP-DSIC-007 Piping Package (Carbon Steel)14 Jan 202007 Feb 202030 Jun 2020
The quantities and sizes of the piping package are indicative and preliminary and will be subjected to change as the project progresses.
AIP-DSIC-004 Aluminium Helideck Package14 Jan 202007 Feb 202031 Oct 2020
An aluminium helideck shall be provided suitable for Sikorsky S92 and Aerospatiale/Euro copter Super Puma AS-332/L1/L2 and EC-225 machines with additional area to park one helicopter.
AIP-DSIC-003 Prefabricated Cabin Unit14 Jan 202007 Feb 202031 May 2021
Requirement of 75 prefabricated cabin units.
STATUS   MISCELLANEOUS - ITT PHASE    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
0482-MI20-44PO-7108-01-C Submersible Deepwell Pump Requisition Specification 

Full scope has been awarded to:

Framo AS

Florvaagvegen 39 Florvag
Hordaland-5305 Norway
Contact: Eirik Solhaug
Ph: +47 55999022
Email: ESO@FRAMO.NO

The Submersible Deepwell Pump Specification Supply Scope
Please refer to attached scope of works.
0482-MI20-00C1-0011-01 Supply Base Management11 Dec 201808 Jan 201930 Jun 2019
Provide Warehousing services for the Barossa Project including Supply base facility, enclosed & bunded storage, climate controlled dehumidified storage area, offshore rated containers, freight services, lifting equipment, warehouse personnel, offices and waste management services.
please see scope of work for more information.
0482-MI20-00C1-0012-01 FPSO Barossa Catering14 Nov 201812 Dec 201830 Jun 2019
The scope of services of a complete CampBoss to cater offshore catering for the FPSO Crew
0482-MI20-34PO-8510-01-C Deck Crane Requisition Specification20 Nov 201818 Dec 201830 Jun 2019
The Deck Crane Requisition Specification Supply Scope.
Please refer to attached scope of works
0482-MI20-44PO-4029-01-C Essential Generator Requisition Specification20 Nov 201818 Dec 201830 Jun 2019
The Essential Generator Requisition Specification Supply Scope comprises of 2 units Please refer to attached scope of works.
0482-MI20-44PO-5109-01-C Fire Water Pump Requisition Specification20 Nov 201818 Dec 201830 Jun 2019
The Fire Water Pump Requisition Specification Supply Scope comprises of 3 units
Please refer to attached scope of works.
0482-MI20-50PO-9051-01 Integrated Control and Safety System (ICSS)21 Sep 201819 Oct 201830 Jun 2019
The Integrated Control and Safety System (ICSS) shall be a single database, distributed-type control system incorporating a robust, open and reliable architecture. Please refer to attached brief scope for further information
0482-MI20-55PO-6300 Telecommunication System19 Oct 201816 Nov 201830 Jun 2019
The telecommunication system is an essential system required for emergency and normal communication into the FPSO and to onshore/offshore facility. The systems shall comply with all relevant IEC standard, codes, flag state, class society rules, area classification. Please refer to attached scope of works.
0482-MI20-55PO-6305 Navigation System19 Oct 201816 Nov 201830 Jun 2019
The Navigation System is tie-in with telecommunication system, used for emergency and normal communication to FPSO. Please refer to the attached scope of works.
0482-MI20-55PO-6320 VSAT and INMARSAT System19 Oct 201816 Nov 201830 Jun 2019
The gyro-stabilized VSAT shall be back-up communication data transmission to FPSO. It will be used as primary communication link during onshore commissioning, transit voyage and offshore installation hock-up phase until the subsea fibre optic link is fully connected and commissioned. Minimum 10 Mbps transmission is required (uplink/downlink). Please refer to attached brief scope for further information.
0482-MI20-55PO-6330 IT/LAN Signal Distribution System19 Oct 201816 Nov 201830 Jun 2019
The IT/LAN Signal Distribution system shall be reliable and manageable cabling system to support the required telecom backbone network. The structured cabling system, should followed industry standard and high quality component to deliver best and stable telecom network. Please refer to the attached scope of works.
0482-MI20-55PO-6331 IT/LAN System19 Oct 201816 Nov 201830 Jun 2019
IT/LAN system shall cover the latest, compatible and reliable equipment used for offshore environment. The equipment shall include cables, CDs, licenses and supports. Please refer to the attached scope of works.
0482-MI20-55PO-6340 Satellite Entertainment System (IP-TVRO)19 Oct 201816 Nov 201830 Jun 2019
The entertainment system shall be capable of accepting satellite entertainment or streaming solutions and distribute TV and radio signals throughout the facility via modern IP streaming technology. Please refer to the attached scope of works.
0482-MI20-55PO-6350 Man Overboard System19 Oct 201816 Nov 201830 Jun 2019
The Man overboard system shall activate the life jacket sensor/tag automatically once immerse into water and/or distance between the FPSO and crew increase. The base station shall automatically sounds/alert the people onboard. Please refer to the attached scope of works.
0482-MI20-55PO-6360 Access Control/POB/E-Mustering and Tracking System19 Oct 201816 Nov 201830 Jun 2019
The access control shall be able to determine authorize/unauthorized personnel entering/leaving restricted area. The system shall be able to account POB on board and track personnel movement. It shall be able to facilitate the mastering of personnel on board in fast and accurate manner in compliance with company HSE procedure. Please refer to the attached scope of works.
0482-MI20-55PO-6380 Aeronautical Radio System19 Oct 201816 Nov 201830 Jun 2019
The aeronautical radio system shall be able to communicate with the pilot during Heli-operation. The frequency shall be assigned by Australian local regulation (ACMA), and able to program based on approved frequency. Please refer to the attached scope of works.
0482-MI20-55PO-6395 Electronic - Mustering and Tracking System19 Oct 201816 Nov 201830 Jun 2019
The Electronic- Mustering and Tracking, shall be able to facilitate the mastering of personnel on board in fast and accurate manner and in should comply with Company HSE procedure. The system should be able to determine track personnel on restricted areas and in the entire facility. Please refer to the attached scope of works.
0482-MI20-55PO-6400 Navigational Aid and Heli-Warning Light19 Oct 201816 Nov 201830 Jun 2019
The navigation aid shall comply with regulation and IALA recommendation. Please refer to the attached scope of works.
0482-MI20-55PO-6410 Tanker Berthing Aids System19 Oct 201816 Nov 201830 Jun 2019
The Tanker berthing Aids shall provide real time kinetic (RTK) differential GPS to determine the position of the antennas in centimetre value. It shall have portable units which allows determining FPSO heading and allows the system to draw in real time the position of the Tanker and tug boat. Thus, it can calculate automatically the distance, speed and bearing of approach, along with tanker position, speed and acceleration. Please refer to the attached scope of works.
0482-MI20-55PO-6500 Environment Motion Monitoring System (EMMS)19 Oct 201816 Nov 201830 Jun 2019
The Environment Motion Monitoring System (EMMS), shall complied with regulation and certification bodies, sensors integration shall be utilize for helideck operation, and interfaces to various systems. Please refer to the attached scope of works.
0482-MI20-55PO-6510 Position Reference System (PRS)19 Oct 201816 Nov 201830 Jun 2019
The Position and Reference System (PRS) system, shall have Differential Absolute and Relative Positioning System (DARPS) with dedicated GPS/GLONASS, correction signals, and receive ship heading from Gyro compasses. Please refer to attached scope of works.
0482-MI20-55PO-6530 Vessel Positioning and Excursion Monitoring System19 Oct 201816 Nov 201830 Jun 2019
The Vessel Positioning and Excursion Monitoring system, shall ensure the FPSO accurate position data via satellite with dual redundant position reference and fault tolerance combined with GPS/GLONASS. It shall monitor the turret position and heading with reference to dual gyro-compasses (MGC); in event of failure on mooring line and/or drift due to sea condition. Please refer to attached scope of works.
0482-MI20-55PO-6540 Hull Stress Monitoring System19 Oct 201816 Nov 201830 Jun 2019
The Hull Stress Monitoring System Equipment shall be type approved by Class. The system shall automatically re-start and run the software upon return of power source. The system shall have capacity to store at least one year of statistical data and 24 hours of time series from all sensors. Please refer to attached scope of works.
0482-MI20-94P0-3393-01 Process chemicals oversight01 Nov 201828 Nov 201830 Jun 2019
The scope of the services of a production chemistry consultant to assist with the selection process. This consultant is to act as an independent body to the shortlisted vendors. For further information refer to attached brief scope.
0482-MI20-94PO-2105 Flash Gas Compressor21 Sep 201819 Oct 201830 Jun 2019
Please refer to attached brief scope for further information
0482-MI20-94PO-2400 Export Gas Compressor21 Sep 201819 Oct 201830 Jun 2019
Please refer to attached brief scope for further information
0482-MI20-94PO-2720-01 CO2 Removal System21 Sep 201819 Oct 201830 Jun 2019
Please refer to attached brief scope for further information
0482-MI20-94PO-2720-0 MEG Regeneration System21 Sep 201819 Oct 201830 Jun 2019
Please refer to attached brief scope for further information
0482-MI20-94PO-2800 CO2 Permeate Compressor21 Sep 201819 Oct 201830 Jun 2019
Please refer to attached brief scope for further information
0482-MI20-94PO-2991-01 Mercury removal and disposal01 Nov 201828 Nov 201830 Jun 2019
The scope of mercury removal by non-regenerative adsorption to reduce the concentration in the FEED gas and disposal requirements are segregated under 3 categories, Pre-operations support - detail design phase, Pre-operations support - construction phase, Adsorbent change out - operations phase. For further information refer to attached brief scope
0482-MI20-94PO-3000 Flare Tip 21 Sep 201819 Oct 201830 Jun 2019
Please refer to attached brief scope for further information
0482-MI20-94PO-3300-01 Chemical Injection Skid21 Sep 201819 Oct 201830 Jun 2019
Please refer to attached brief scope for further information
0482-MI20-94PO-3391-01 boiler and closed loop chemicals 01 Nov 201828 Nov 201830 Jun 2019
The scope of supply for boiler and closed loop chemicals requirements are segregated under 4 main categories - Pre operations support (detail design phase) boiler and closed loop, Chemical supply (operations phase) boiler, Technical support (operations phase) boiler, Chemical supply (operations phase) closed loop systems. For further information refer to attached brief scope
0482-MI20-94PO-3392-01 Process chemicals and technical support01 Nov 201828 Nov 201830 Jun 2019
The scope of supply for process chemicals requirements are segregated under 4 main categories - Pre-operations support (detail design phase), Early operations technical support (HUC to steady Ops, Chemical supply (Operations phase, Technical support (steady operations phase). For further information refer to attached brief scope
0482-MI20-94PO-9962-01 Miscellaneous Pressure Vessels21 Sep 201819 Oct 201830 Jun 2019
Please refer to attached brief scope for further information
0482-MI20-94PO-9970-01 Shell and Tube Heat Exchangers21 Sep 201819 Oct 201830 Jun 2019
Please refer to attached brief scope for further information
0482-MI20-94PO-9972-01 Plate and Frame Heat Exchangers21 Sep 201819 Oct 201830 Jun 2019
Please refer to attached brief scope for further information
STATUS   SOFEC-TURRET MOORING SYSTEM    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
AIP-SOF-002 Turret Local Equipment Room (TLER)14 Feb 202013 Mar 202030 Sep 2020
The Turret Local Equipment Room (TLER) will be located on the Floating/Production/Storage/Offloading (FPSO), which is located in the Timor Sea approximately 300km North-Northwest of Darwin in Bonaparte Basin.

See scope of work for more information.
AIP-SOF-001 Anchor Leg and Riser Pull-In Equipment08 Jan 202022 Jan 202031 Mar 2020
Sacrificial anodes are to be fitted in water ballast tanks, condensate tanks, slop tanks, produced water tanks, sea chests, shipside caissons and internal turret moonpool according to the following design condition and MODEC/COP's practice/standard.