  Project Status: Selection Phase Study (SPS) currently. Definition Phase Study (DPS) or Feasibility Stage in 2019.
  Project Owner BHP Olympic Dam Corporation Pty Ltd (BHP)

Project Details


Project Details

BHP Olympic Dam (OD, the Company) is a fully-integrated mining and mineral processing operation, owned by the BHP Group through its wholly owned subsidiary BHP Billiton Olympic Dam Corporation Pty Ltd.

Productivity initiatives have been implemented over the last two years at Olympic Dam however further work is required to ensure it is a globally competitive, world-class operation.

In order to achieve this, a Brownfield Expansion (BFX) project is being evaluated to develop the mine and processing plant to increase production and lower operating cost.

OD has historically operated in the Northern Mine Area (NMA) since operations commenced in the 1980s.  The OD mine plan is now extending into the previously unexploited Southern Mine Area (SMA).

The proposed BFX Project (the Project) is to deliver a brownfield expansion of its underground and surface operations to deliver increased throughput of the existing plant and increasing overall copper production capacity.  The Project is currently finalising its pre-feasibility (or SPS) and is planned to transition into ‘feasibility’ (or DPS) later in 2019. 

Scope Overview

The scope as it is currently defined in ‘pre-feasibility’ (or SPS) includes the following:

  • Expanded footprint in the SMA to access more and higher grade ore
  • Expansion of the existing surface processing facilities including:

            -   Installation of an additional grinding mill

            -   Expanded smelting facility and supporting plant

            -   Expansion of existing refinery complex 

  • Installation of additional water supply and accommodation infrastructure
  • Provision of all associated:

            -   Project management (if required)

            -   Definition and detailed design required to deliver scope items (if required)

            -   Temporary/enabling works (if required)

            -   Installation

            -   Commissioning

The Project will complete definition and detailed design during the DPS, which will only commence after successful completion of the current SPS.

Indicative Timeline

Pre-feasibility or SPS completed FY2019

Feasibility or DPS design commencing FY2020

Final investment decision FY2021

Main construction and commissioning works FY2021 to FY2024.

Disclaimer

The proposed Project is currently completing a selection phase or ‘pre-feasibility’ study and is subject to a number of approvals. Accordingly, the scope descriptions, timelines and values stated in this project description are indicative only and subject to change.


SHOW LESS

Work Packages


To submit an expression of interest, select the icon next to the work package scope you are interested in.

OPEN LISTINGS    AWARDED    CLOSED LISTINGS    OTHER
OPEN FOR EOI    INCOMPLETE EOI    EOI COMPLETED
STATUS   GENERAL    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
BFX-SPS-078 Bismuth / Antimony Removal System8 Aug 1818 Aug 18 
BHP is seeking expressions of interest (EOI) from contractors capable of providing
the service of providing a full scale operating bismuth and antimony removal
system. This is an opportunity for such companies to operate a Bismuth Antimony
Removal system (BARS) pilot plant on the OD remote site, perform laboratory
testing (preferably using atomic absorption spectrophotometry), and the provision
of an interpretative report based on these results.
See attached document for further details.
BFX-SPS-081 Pastoral Water Infrastructure Survey10 Aug 1820 Aug 18 
BHP is seeking expressions of interest (EOI) for suitable qualified professionals to conduct a mapping survey on the pastoral stations surrounding the Wellfield B (in the Marree region of South Australia).
BFX-SPS-082 BFX Asset Management Program and Master Data 10 Aug 1820 Aug 18 
BHP is seeking expressions of interest (EOI) from qualified Companies to develop asset management programs and associated Master Data load sheets based on project Preliminary Equipment Lists.
See attached document for further details.
Engineering Services Combined Packages BFX085/BFX103/BFX08710 Aug 1820 Aug 18 
BHP is seeking expressions of interest (EOI) from contractors capable of completing detailed engineering and construction study works for the following scopes, on an individual or combined basis:
- BFX SPS 085 Precious Metal Refinery (Gold PMR) Capacity Assessment
- BFX SPS 103 Engineering Review of Surface Facilities (Updated Mine Plan)
- BFX SPS 087 Modularisation & Prefabrication Review

See attached document for further details.
BFX-SPS-127 Electro-Refinery Dynamic Model14 Aug 1824 Aug 18 
BHP is seeking expressions of interest (EOI) from contractors capable of providing modelling services to create a detailed (to individual machine movements level) dynamic model of the Electro-Refinery process. The dynamic model will be used to identify constraints within the process.
See attached document for further details.
BFX-SPS-099 Independent Peer Review of Power and Electrical Infrastructure Scope16 Aug 1826 Aug 18 
BHP is seeking expressions of interest (EOI) from contractors capable of providing a 'desk-top' Independent Peer Review (IPR) of the deliverables of a Brownfield Expansion Project (BFX), Engineering Contractor's (EC) 'Power and Electrical Infrastructure' scope of work. The IPR will review the technical compliance of the engineering and value-add through sharing of knowledge and experience.
See attached document for further detail.
BFX-SPS-028 Geotechnical Investigation24 Jul 185 Aug 18 
BHP is seeking expressions of interest (EOI) from contractors capable of providing
geotechnical engineering services including remote onsite drilling and coring,
laboratory testing of soil and rock samples and the provision of an interpretative
geotechnical report based on results from laboratory testing.
See attached document for further details.