Clean TeQ Sunrise Project



Contact Details


  Ian Hudson
  (02) 6360 8422
 CONTACT EMAIL

  Locations: NSW Australia
  Project Status: Pre-procurement
  Project Owner Clean TeQ Holdings Limited

Project Details


Clean Teq Sunrise Pty Ltd (ABN: 21 008 755 155) a wholly owned subsidiary of Clean Teq Holdings Limited (ABN: 34 127 457 916) is developing the Sunrise nickel, cobalt, scandium project in New South Wales utilising Clean-iX® technology. The project will be located approx. 350kms WNW of Sydney (Fifield District)


The Clean TeQ Sunrise process will see 2.5 MTPA of nickel laterite ore processed using the pressure acid leaching (PAL) process. The facility will produce three main products including nickel, cobalt, and scandium oxide. 


The Project’s Final Investment Decision (FID) is planned for first quarter 2019.  


Early Site construction works are planned to commence in late 2018 with start-up planned by the end of 2020.  Procurement for ‘Early Works’ will commence in July 2018.  


How to register an Expression of Interest

  • Work Packages currently available for submission of an EOI are listed below.
  • Partial scope registrations will be passed on to the contractor awarded the full scope contract.
  • To submit an initial EOI for a Work Package, companies must have an ICN Gateway company profile. Information on how to register your company on ICN Gateway is detailed below.
  • If you already have a company profile, please ensure it is up to date. For this particular project, please ensure that the Summary, Products/Services and Locations sections are current and complete.

            This is an initial, generic EOI submission only. After reviewing the information in your company profile, CleanTeq will contact you if they would like other information to be submitted.

 

ICN Gateway Company Registration

  • Click here to create your company profile on ICN Gateway.
  • Support and assistance is available through the web links listed below.
  • Your company summary and company description are used to assess your ability to complete projects when you lodge an EOI- please ensure that your company invests the time and energy required to represent your company in the most effective manner possible.


Intellectual Property

NOTICE - This website contains documents and attachments that may contain information or material that is confidential, privileged, and/or subject to copyright or other rights. Any unauthorized viewing, disclosure, retransmission, dissemination, or other use of or reliance on this website or anything contained therein is strictly prohibited and may be unlawful.

SHOW LESS

Associated Opportunities


SHOW MORE

Work Packages


To submit an expression of interest, select the icon next to the work package scope you are interested in.

OPEN LISTINGS    AWARDED    CLOSED LISTINGS    OTHER
OPEN FOR EOI    INCOMPLETE EOI    EOI COMPLETED
STATUS   SERVICES AND CONSTRUCTION SCOPES    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
9409 Charter Flights Services Package 15 Nov 1830 Nov 18 
Provision by the Contractor of all necessary supervision, labour,
expertise, materials, equipment and services required to provide the Air Charter and Regular
Passenger Transfer (RPT) Services for the Project
C9404 Site Waste Management Services 15 Nov 1830 Nov 18 
Provision by the Contractor of all necessary supervision, labour, expertise,
materials, equipment and services required to provide the Site Waste Management Services for the Project
30As Camp Management15 Aug 1831 Aug 18 
This Scope of Works includes the provision by the Contractor of all necessary supervision, labour, expertise, materials, foodstuffs, equipment and services required to provide the Camp Management Services
C1102 Gabbro Geotechnical Investigation18 Oct 1828 Oct 18 
Conducting drilling for further geotechnical investigation on the Project Site.
C1603 Construction Camp Access Road and Carpa21 Aug 187 Sep 18 
This work package covers the design and construction of the following:
. Upgrade Sunrise Lane from Wilmatha Road to the Site Access Road
. Upgrade the intersection of Wilmatha Road and Sunrise Lane
. New access road from Sunrise Lane to the Accommodation Camp; and
. Construction camp car park and bus turning circle.
C9401 Construction Camp Installation28 Aug 1811 Sep 18 
This scope of work is for the design, inspection and testing, preparation for shipment, transport to site, construction and commissioning of the Construction Camp.
P9406 Construction Camp Building Lease20 Aug 182 Sep 18 
Clean TeQ propose to install a 1300 person camp to enable the construction of the Sunrise Project. The camp will include administration and accommodation buildings that are owned by Clean TeQ and will be permanently installed. The remainder of the buildings with be leased or purchased as required.

This scope comprises of the supply of transportable accommodation and associated buildings on a leased basis for the remainder of the buildings. Buildings are to be in good working order and compliant with the relevant codes. The Contractor's scope is to include packing to make ready for transport, with transport provided by others.
S5916 Customs Brokerage7 Aug 1820 Aug 18 
Brokerage services shall support the importation of all Project permanent materials and temporary import and export of materials and equipment required for the installation of the Project facilities. These services will be required for the duration of the Project and shall include all modes of transport including ocean freight (Full Containers, Part Containers, Full Charter and Part Charters) and airfreight.
S5917 Domestic Transportation and Warehousing7 Aug 1820 Aug 18 
Project and Materials Management Services
Materials Consolidation and Laydown.
Transport Services (Regular In Gauge).
Transport Services (out of gauge non-escorted loads).
S5918 International Freight Forwarding7 Aug 1820 Aug 18 
International Freight Forwarding
Shipping Documentation Management
Reporting
STATUS   MATERIALS AND EQUIPMENT SUPPLY    ▲ CONTRACT OPENS FULL
SCOPE
CLOSES
PARTIAL
SCOPE
CLOSES
DOCS FULL
SCOPE
EOI
PARTIAL
SCOPE
EOI
2500 Romwall supply component2 Jul 1813 Jul 18 
The Scope includes design of complete Reinforced Earth Wall system and provision of design deliverables for Wall construction, including earthworks and wall drainage requirements. Supply, Site Delivery of all Materials for Reinforced Earth Wall inclusive of all facing panels, reinforcing strips, connection materials, geotextile
2801 Concrete - Batch Plant12 Jul 1827 Jul 18 
The design, supply, construction and operation of a concrete batch plant including ancillary plant, mixers, and infrastructure for the manufacture, testing and delivery of concrete to construction contractors. The batching plant will be within or adjacent to the main process plant site. Precise details of the batching plant location shall be nominated by the Contractor. Concrete delivery points shall include: Process Plant
Mine (mining infrastructure, load out facilities)
Construction Camp
2980 Concrete Protection12 Jul 1827 Jul 18 
The supply, application and testing of concrete protective coating systems. The Contractor shall supply all labour, supervision, OHSE support, personal protective equipment, materials/consumables, and all other items required to complete the concrete protection coating work on various plant facilities.
5102 Shop Fabricated Tanks (CS SS)2 Jul 1813 Jul 18 
\"The Scope includes engineering, detailed design and fabrication of the tanks listed below. The Principal will provide Design General Arrangement drawings with specifications and setout information. Tanks will be configured for a maximum transport envelope of 5.5m wide by 5.5m high. For tanks above 4.5 metres overall height, the tanks shall be fabricated as two cans with a trial fit-up in the workshop, for site assembly by others.\nThe Contractor shall provide all labour, materials, parts and services necessary to carry out the design, workshop detailing, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification and packaging, together with the provision of all necessary services\n\"\n
5103 Shop Fabricated Tanks FRP Tanks2 Jul 1830 Jul 18 
\\\"The scope includes tanks covering a wide range of dimensions. The smaller units are suitable for full shop fabrication, transportation and site installation. The largest tanks shall be field erected. Intermediate tanks may be transported as sub-assemblies and completed during site installation. The plan for fabrication location, the transportation of all material and sub-assemblies, and completed tank installation is the responsibility of the Contractor.\\n\\nThe Contractor shall provide all labour, materials, parts and services necessary to carry out the design, workshop detailing, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification and packaging, together with the provision of all necessary services\\\"\\n
5104 Vessel Dip Tubes13 Jul 1827 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation for the Vessel Dip Tubes, together with the provision of all necessary services
5105 Pachucas and Columns9 Jul 1820 Jul 18 
The fabrication of the pachucas inclusive of all module steelwork. The Contractor shall provide all labour, materials, parts and services necessary to carry out the production of workshop detailing drawings, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification and packaging, together with the provision of all necessary services
5109 Flash Vessels2 Jul 1813 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, together with the provision of all necessary services for the following: LP Flash Vessel, MP Flash Vessel, HP Flash Vessel and PAL Blast Spot\n
5110 PALHeaters2 Jul 1813 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, together with the provision of all necessary services, relating to the following equipment: MT (Medium Temperature) Feed Heater - Train 1, HT (High Temperature) Feed, Heater - Train 1, Trim Heater - Train 1, PAL Water Heater - Train 1, Safety Relief Blast Spool - Train 1, MT (Medium Temperature) Feed Heater - Train 2, HT (High Temperature) Feed Heater - Train 2, Trim Heater - Train 2, PAL Water Heater - Train 2 and Safety Relief Blast Spool - Train 2.\n
5114 Site Erected Tanks (CS SS)2 Jul 1813 Jul 18 
The Scope includes engineering, detailed design and fabrication of the tanks listed below. The Principal will provide Design General Arrangement drawings with specifications and set-out information.\nThe Contractor shall provide all labour, materials, parts and services necessary to carry out the design, workshop detailing, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification and packaging, together with the provision of all necessary services\n\n
5201Thickeners and Clarifiers2 Jul 1824 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, together with the provision of all necessary services, relating to the following equipment: Four (4) feed thickeners (1~4), one (1) tailings thickener, one (1) eluate neutralisation clarifier and one (1) Sc caustic precipitation clarifier.\n
5202 Venturi Scrubber2 Jul 1813 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, together with the provision of all necessary services, relating to the following equipment: one (1) PAL-1 Scrubber and one (1) PAL-2 Scrubber.\n
5203 Ore Sizer2 Jul 1813 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, of Ore Sizer together with the provision of all necessary services\n
5204 Ball Mill4 Jul 1814 Jul 18 
The scope shall comprise the provision of all labour, materials, parts and services necessary to carry out the design, supply, manufacture,\nassembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, of Ore Mill together with \nthe provision of all necessary services\n
5205 Screens4 Jul 1814 Jul 18 
The scope shall comprise the provision of all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, for Screens together with the provision of all necessary services.
5206 Cyclones2 Jul 1823 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, for Screens together with the provision of all necessary services\n
5210 General Agitators2 Jul 1813 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation for General Agitators, together with the provision of all necessary services for all relevant equipment\n
5213 Sulphur Milling Plant Bulk Handling2 Jul 1813 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, together with the provision of all necessary services related to Sulphur Bulk Handling & Milling\n
5216 Ta Lance and Spool2 Jul 1813 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, together with the provision of all necessary services, relating to the two (2) Autoclave Acid Injection Lances - Train 1 and two (2) Autoclave Acid Injection Lances - Train 2.\n
5217 Acid Injection Valves 2 Jul 1824 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportatio for Acid Injection Valves, together with the provision of all necessary services\n
5218 Trommel Screens2 Jul 1813 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, for Trommel Screens together with the provision of all necessary services
5401 Slurry and Sump Pumps2 Jul 1823 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation for Slurry & Sump Pumps, together with the provision of all necessary services \n
5402 Solution Pumps2 Jul 1820 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation for Solution Pumps, together with the provision of all necessary services
5404 Acid Injection Pumps2 Jul 1824 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, together with the provision of all necessary services, relating to the following: two (2) PAL 1 Acid Injection Pumps and two (2) PAL 2 Acid Injection Pumps.
5405 Autoclave Feed Pumps2 Jul 1824 Jul 18 
The Scope includs providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, together with the provision of all necessary services, relating to the following: Four (4) Autoclave Feed Pumps, four (4) Autoclave Feed Pump Air Compressors, two (2) Autoclave Feed Pump Air Receiver and eight (8) Autoclave Feed Pump Accumulators.
5406 Progressive Cavity and Metering Pumps2 Jul 1813 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation for Progressive Cavity & Metering Pumps, together with the provision of all necessary services,
5407 Compressors And Blowers2 Jul 1813 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, together with the provision of all necessary services, relating to the following equipment: one (1) LP Air Aupply Package and one (1) Instrument Air Package.
5408 HP Compressors2 Jul 1813 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation for PAL HP Compressors, together with the provision of all necessary services
5409 Seal Water System2 Jul 1813 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, together with the provision of all necessary services, relating to the following: one (1) PAL1 Pump Mechanical Seal Water System Package, one (1) PAL2 Pump Mechanical Seal Water System Package, one (1) Tails pumping Seal Water Package, forty two (42) API 682 Plan 53A seal support kits Type 1 and sixteen (16) API 682 Plan 53A seal support kits Type 2
5415 Diesel Generator Package2 Jul 1813 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, together with the provision of all necessary services, relating to the following: Three (3) diesel generator sets.
5417 Boiler Package2 Jul 1813 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, together with the provision of all necessary services, relating to the following: LP Boiler Package and HP boiler package.
5501 Apron Feeder2 Jul 1813 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation for Apron Feeder, together with the provision of all necessary services
5502 Conveyor Systems2 Jul 1813 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation to site of Conveyors, together with the provision of all necessary services
5503 Cranes And Hoists 2 Jul 1813 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, workshop detailing, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, training together with the provision of all necessary services, relating to cranes and hoists equipment\n
5504 Screw Feeders13 Jul 1827 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation for the Screw Feeders, together with the provision of all necessary services
5601 Sulphuric Acid Plant2 Jul 1813 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, together with the provision of all necessary services, relating to a Sulphuric Acid Plant, the Sulphuric Acid Storage and Unloading facility has been designated and the Cogeneration plant.
5603 Flocculant and Coagulant Plant13 Jul 1827 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation for the Flocculant & Coagulant Plant, together with the provision of all necessary services
5604 Crystalliser2 Jul 1813 Jul 18 
The Scope includes all works necessary for the design, supply, fabrication, assembly, inspection and testing, delivery to site, mobilisation to and demobilisation from site, construction, installation, training, testing, commissioning and performance (site acceptance) testing, operation and handover of the Crystallisers Plants Package for nickel, cobalt and ammonium sulphate compounds.
5605 Ammonia Unloading and Storage Facility2 Jul 1813 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, installation, erection, testing, commissioning, start up and performance testing, together with the provision of all necessary installation and commissioning labour, support services, training and site acceptance testing relating to the ammonia storage and unloading
5607 Filters2 Jul 1824 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation of Filters, together with the provision of all necessary services
5609 Solvent Extraction Plant13 Jul 1827 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, together with the provision of all necessary installation and commissioning support services, relating to the SX Plant
5613 Limestone Milling Plant2 Jul 1813 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, together with the provision of all necessary installation and commissioning support services, relating to the limestone handling and processing facilities
5614 Process Water Treatment Plant2 Jul 1831 Oct 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, commissioning, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, together with the provision of all necessary installation and site acceptance testing relating to Process Water Treatment facilities \n
5615 Lime Slaking Plant2 Jul 1813 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, together with the provision of all necessary installation and commissioning support services and site acceptance testing relating to the scope for the Quicklime Slaking Plant:
5617 Packaging Plant2 Jul 1813 Jul 18 
The Contractor shall supply all labour, supervision, materials handling equipment, construction equipment, project documentation, services and materials other than the free issue materials listed in section 2.2 and include all works necessary for the design, supply, fabrication, assembly, inspection and testing, delivery to site, mobilisation to and demobilisation from site, construction, installation, training, testing, commissioning and performance (site acceptance) testing, operation and handover of the Packaging Plants
5701 Co-generation Power Plant2 Jul 1813 Jul 18 
The Scope includes design, supply, manufacture, installation, erection, testing, commissioning and performance testing of a Cogeneration Plant, which is a two train electricity generation station comprising of steam turbine generators, air cooled condensers, ejector systems, condensate tanks, condensate pumps, stand and all other ancillary equipment. The Works also includes switchgear, buildings, diesel generator sets and all other associated Works.
5802 Foam Protection System (Mobile Unit)2 Jul 1813 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, installation, erection, testing, commissioning, start up and performance testing, together with the provision of all necessary installation and commissioning labour, support services, training and site acceptance testing relating to the Foam System Package for the SX Area
5902 Laboratory Equipment2 Jul 1818 Jul 18 
The Scope includes the general and detailed engineering design of the laboratory facility, its construction and the supply, installation and commissioning of the major laboratory equipment. The scope shall also comprise the provision of all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, installation, fit-out, commissioning and all other necessary services, relating to the equipment for the on-site laboratory to fulfil the mines and process plant physical data collection and analytical requirements
5903 Slurry Samplers2 Jul 1813 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation of Samplers, together with the provision of all necessary services
5904 Weighbridge13 Jul 1827 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation for the Weighbridge, together with the provision of all necessary services
6101 CS Pipe and Fittings9 Jul 1820 Jul 18 
Supply and manufacture of carbon steel pipes and fittings
6102 SS Pipe and Fittings9 Jul 1820 Jul 18 
Supply and manufacture of Stainless Steel pipes and fittings
6103 Ti Pipes and Fittings9 Jul 1820 Jul 18 
Supply and manufacture of Titanium pipes and fittings
6104 Plastic Pipes and Fittings9 Jul 1820 Jul 18 
Supply and manufacture of HDPE pipes and fittings
6105 Carbon Steel Rubber Lined Piping and Fittings9 Jul 1820 Jul 18 
Supply and manufacture of carbon steel, rubber lined pipes and fittings
6502 Pressure Relief Valves and Bursting Discs2 Jul 1813 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation of Pressure Relieve Valves & Bursting Discs, together with the provision of all necessary services
6504 Severe Service Ball Valves2 Jul 1813 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation of Severe Service Ball Valves, together with the provision of all necessary services
6505 Severe Service Choke Valves9 Jul 1820 Jul 18 
Provision of all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, together with the provision of all necessary services.
7201 Switchrooms And Substations2 Jul 1816 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, together with the provision of all necessary services, relating to the following equipment: one (1) Cooling LV Switchroom, seven (7) 11kV Switchgear, one (1) cRIP LV Switchroom, one (1) SX LV Switchroom, two (2) PAL MV Switchroom, one (1) Ore Prep Switchroom and one (1) Borefield Switchroom.\n
7202 Transformers12 Jul 1827 Jul 18 
Design, supply and testing of all LV and HV transformers. This shall include any ancilliary or related items required for the proper functioning of the equipment.
7801 HV and LV Cabling10 Jul 1820 Jul 18 
Fabricate, test and deliver LV and HV cables as per the datasheets, technical specifications and MTOs
8101 Process Control System9 Jul 1820 Jul 18 
All labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, quality assurance, inspection, testing, identification, packaging and transportation, together with the provision of all necessary services, relating to the Process Control System.
8201 Field Instruments9 Jul 1820 Jul 18 
All labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, together with the provision of all necessary services, relating to the equipment in the Instrument List document.
Examples include Level Transmitter - Radar - Vehicle Detection - up to 30m, Traffic Light, Pull Wire Switch, Underspeed Switch, Belt Drift Switch, Level Switch - Microwave, Beacon / Siren, Density Transmitter - Radiometric, Flowmeter - Mag Flow, Pressure Gauge, Accelerometer, Vibration Transmitter, ph Probe and ph Transmitter.
8202 Onstream Analyser13 Jul 1827 Jul 18 
The Scope includes providing all labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation for the Onstream Analyser, together with the provision of all necessary services
8401 Control Valves9 Jul 1818 Aug 18 
All labour, materials, parts and services necessary to carry out the design, supply, manufacture, assembly, surface protection, quality assurance, inspection, testing, identification, packaging and transportation, together with the provision of all necessary services, relating to the necessary equipment.
D8807 IT Infrastructure25 Oct 189 Nov 18 
Procurement package including design and on-site commissioning of the early works IT Infrastructure for the Project.
D8807 Site Radio System25 Oct 189 Nov 18 
Procurement package including design and on-site commissioning of the early works Site Radio System for the Project.
P7302 MV/LV Motors19 Sep 185 Oct 18 
Design, manufacture, inspection and testing, and preparation for shipment of Medium Voltage (MV) and Low Voltage (LV) electric motors indicated in the attached list for the Clean TeQ Sunrise Project, located in New South Wales, Australia
T8801 Communications Infrastructure25 Oct 189 Nov 18 
Design, procure and construct contract for the early works Communications Infrastructure for the Project