Nolans Project


Project at a glance


NT Australia
Financing and Mining Approvals
ARAFURA RARE EARTHS PTY LTD
AU$1,006M

Contact Details


Industry Capability Network (NT)
+61 8 8922 9422

Arafura Nolans Project Ltd (Arafura) is developing the Nolans Rare Earths project (the Project), which will encompass a mine, beneficiation plant, extraction plant, separation plant, sulphuric acid plant and related non-process infrastructure, to be constructed in the Northern Territory. The project site is located on Aileron Station, approximately 135 kilometres NW of Alice Springs.


The Project mining operation will use conventional open-pit truck and excavator mining methods, supplemented by drill and blasting for ore and waste. A JORC-compliant Ore Reserve supports an initial mine life of 38 years, with mining and processing of all known mineral resources extending the project's operational life to beyond 45 years. Ore Reserves are based on an average mining rate of 7.6 million tonnes per annum to produce 1 to 1.3 million tonnes of ROM ore each year and 316,000 tpa of concentrate through the hydrometallurgical plant to produce a range of rare earth products and a phosphoric acid by-product.


Project Status

The site enabling works, consisting of minor bulk earthworks and borefield headworks installation, were completed in late 2023.

In March 2024 Arafura received conditional support from the Commonwealth government with a debt finance package of US$533 million. This announcement was a catalyst for Arafura to advance the remaining debt and equity funding for the project. Once this remaining funding is secured Arafura will be ready to make a final investment decision on Nolans and move immediately into construction. Arafura is committed to providing updates on timing of construction commencement and other milestones.

Project Documents
ASX Announcements
Project Presentations
Support Services

Share this project on:

FB Twitter LinkedIn

Work Package
Documents
Full Scope EOI
Partial Scope EOI
Status
Accordian collapse

Miscellaneous

AccordianPlus Keep me updated

Full Scope EOI

Create EOI
Closes: 
31 Dec 2024 (ACST)

Partial Scope EOI

  Open
Accordian collapse

Work Packages

Full Scope EOI

Partial Scope EOI

  No longer required
AccordianPlus Bulk Earthworks

Full Scope EOI

Partial Scope EOI

  Under evaluation

Full Scope EOI

Partial Scope EOI

  Under evaluation

Full Scope EOI

Partial Scope EOI

  Under evaluation
AccordianPlus Modular Buildings

Full Scope EOI

Partial Scope EOI

  Under evaluation
AccordianPlus Steel Frame Buildings

Full Scope EOI

Partial Scope EOI

  Under evaluation
AccordianPlus Minor Earthworks

Full Scope EOI

Closed: 
18 Feb 2022 (ACST)

Partial Scope EOI

Closed: 
18 Feb 2022 (ACST)
  Awarded

Full Scope EOI

Closed: 
07 Mar 2022 (ACST)

Partial Scope EOI

Closed: 
07 Mar 2022 (ACST)
  Awarded

Full Scope EOI

Closed: 
24 Jun 2022 (ACST)

Partial Scope EOI

Closed: 
24 Jun 2022 (ACST)
  Awarded

Full Scope EOI

Closed: 
24 Jun 2022 (ACST)

Partial Scope EOI

Closed: 
24 Jun 2022 (ACST)
  Awarded

Full Scope EOI

Closed: 
30 Jun 2022 (ACST)

Partial Scope EOI

Closed: 
30 Jun 2022 (ACST)
  Awarded
AccordianPlus Hydromet Construction

Full Scope EOI

Closed: 
28 Feb 2023 (ACST)

Partial Scope EOI

Closed: 
27 Apr 2023 (ACST)
  Awarded

Full Scope EOI

Closed: 
13 Sep 2021 (ACST)

Partial Scope EOI

  Awarded

Full Scope EOI

Closed: 
28 Jan 2020 (ACST)

Partial Scope EOI

  Awarded
AccordianPlus Sulphuric Acid Plant

Full Scope EOI

Closed: 
27 Feb 2023 (ACST)

Partial Scope EOI

  Awarded

Full Scope EOI

Closed: 
31 Oct 2021 (ACST)

Partial Scope EOI

Closed: 
31 Oct 2021 (ACST)
  Closed

Full Scope EOI

Partial Scope EOI

Closed: 
31 Dec 2021 (ACST)
  Closed

Full Scope EOI

Partial Scope EOI

Closed: 
31 Dec 2021 (ACST)
  Closed

Full Scope EOI

Partial Scope EOI

Closed: 
31 Dec 2021 (ACST)
  Closed

Full Scope EOI

Partial Scope EOI

Closed: 
31 Dec 2021 (ACST)
  Closed

Full Scope EOI

Closed: 
25 Aug 2023 (ACST)

Partial Scope EOI

Closed: 
25 Aug 2023 (ACST)
  Closed

Full Scope EOI

Closed: 
23 Nov 2022 (ACST)

Partial Scope EOI

  Closed
Note: The closing date/s for expressions of interest are subject to change.